Official website of the City and County of Honolulu
 
  You are here:  Main / Environmental Services / WWM / Dewatering Building Structural Modifications
 


 
 

Dewatering Building Structural Modifications

 

Project Name:  Kailua Regional WWTP Dewatering Building Structural Modifications.

 

Contract Amount:  $501,643.42.

 

Contractor:  Kaikor Construction Company, Inc.

 

Scope:  Structural modifications of existing dewatering building to rehabilitate the damaged concrete slab and to accommodate future installation of a new centrifuge.

 

Estimated Project Start Date:  May 2014 (estimated).

 

Estimated Completion Date:  November 2014 (estimated).

 

Status:  Construction currently on hold.  City and contractor negotiating cost for agreed upon revised scope of work.

Last Reviewed: Tuesday, April 15, 2014