KAILUA REGIONAL WWTP CONSTRUCTION MAP 

(All Projects in 2013 & 2014)

FAQ-Odors for Kailua RWWTP

 

KEY KAILUA RWWTP PROJECTS STATUS CONTRACTOR
Digesters Covers Project Ongoing - April 2014 (est.) Oceanic Companies Inc.
Dewatering Building Structural Modifications Est. Start - May 2014 - Nov. 2014 (est.) Kaikor construction
Secondary Clarifier Rehabilitation Ongoing - Aug. 2014 (est.) Oceanic Companies Inc.
Odor Control Improvements - Phase 1 Delayed Civil Mechanical Contractors
Odor Control Improvements - Phase 2 Dependent on Phase 1 Jas. W. Glover Ltd.

1, 3, 4

Miscellaneous Improvements Work Areas 1, 3, 4, shown in red. Start - Oct. 2013 - Jan. 2015 (Est. Compl.) Hawaiian Dredging

2

Energy Saving Performance Contract (ESPC) - Job covers entire plant, staging space to be negotiated at a later time. Work Areas 2 shown in red. Phase 1:  Start - Oct. 2013 - Aug. 2014 (est.) Phase 2:  Start -Aug. 2014 - July 2015 (est.) ENV (NORESCO )
Kaneohe / Kailua Sewer Tunnel Start: Jan. 2014 - Jan. 2017 (est.) Southland Mole JV