Project Name:  Kaneohe/Kailua Sewer Tunnel.

 

Contract Amount:  $173,114,296.

 

Contractor:  Southland Mole JV.

 

Scope:  Construction of approximately three (3) miles of 10-feet diameter sewer pipe to convey and store wet weather wastewater flows from Kaneohe Pre-Treatment Facility to Kailua RWWTP.  Please visit http://kkgravitytunnel.org for more details regarding the project.

 

Project Start Date:  January 2014.

Completion Date:  January 2017 (estimated).

 

Status:  Contractor given Notice to Proceed (NTP) in January 2014.  Pre-excavation work ongoing at Kaneohe and Kailua shafts.