Project Name:  Odor Control Improvements, Phase I

 

Phase I Contract Amount:  $12,503,099.00 (includes change orders)

 

Phase I Contractor:  Civil Mechanical Contractors.

 

Scope:  Improvements and upgrades to major odor control systems throughout the treatment plant to minimize fugitive odors and reduce response time to collect and contain odors.  Work includes new calcium nitrate chemical supply facilities at the treatment plant and at pump stations within the collection system to minimize odors. 

Phase I Project Start Date:  November 2010.

Phase I Estimated Completion Date:  Delayed.

 

Status:  The project is delayed.  The Contractor is unable to meet the city's milestone dates.