ROAD WORK, PARADES AND OTHER STREET ACTIVITIES
The departments of Facility Maintenance (FM) and Design & Construction (DC), and the Board of Water Supply (WS) have scheduled the following roadwork for the week of February 11, between 8:30 a.m. and 3:30 p.m. unless otherwise noted. Estimated completion date is in parentheses.
Contacts: Facility Maintenance: 523-4472; Design & Construction: 523-4049; Water Supply: 527-6148
Pedestrian and Bikeway Improvements
Continuing Projects:
Mililani: Install raised median, new curbs, gutters, street trees and irrigation system on Lanikuhana Avenue, plus traffic slowing measures:and a raised median and pedestrian crossing island on Lanikuhana Avenue. (Completion by 3/01) DC
         Street and Utilities Work
Continuing Projects:
Aiea: Install water mains and fire hydrants along Kaamilo, Neki and Ulune streets. (Completion by 3/01) WS
Install new and replacement sewer lines Nimitz Highway and River Street to end at Hotel Street. (Completion by 2/01) DC Besides the regular working hours, the contractor is working intermittently at night from 6 p.m. to 6 a.m.
East Oahu: Install water mains. WS Kaimoku Place and Kaimoku Way, Niuiki Circle, Kuliouou Road, Keoki Place, Wakine Place and Pahukula Place. (Completion by 3/01)
Haleiwa: Install water lines and equipment along Haleiwa Road, Kaika Place, Nalimu Road, Naoiwi Lane, Niuula Road and Walikanahele Road. (Completion by 6/02) WS
Honolulu: Punchbowl Street Improvements, Phase I: Reconstruct traffic island and relocate traffic signal light poles at Punchbowl Street and Beretania Street Intersection. Reconstruct gutter area and resurface and stripe Punchbowl Street between King and Beretania streets. (Estimated completion is March 31, 2001) DC

Phase 4: Widen both sides of Punchbowl Street between Vineyard Boulevard and Beretania Street. Improvements include reconstructing rock wall, sidewalks, curbs, driveways and curb ramps; install new drainage and water facilities, grass, trees, irrigation system, planters on median strip, and street light system. Provide pavement striping, markings, and markers. (Estimated completion is June 1, 2001) DC
Kahaluu: Install water lines along Kamehameha Highway from Lihikai to Laenani drives and along the two drives. Install fire hydrants along Ahilama Road, Ahuimanu Road, Mapele Place and Road, and Pulama Road. (Completion by 7/01) WS
Kailua: Install water main along Kaha Street and Loop, Kaimake Loop and Kaipiha Street. (Completion by 9/01) WS
Kaneohe: A 42-inch water main with fire hydrants is being placed along Kahekili Highway from Ahuimanu Road to Haiku Road and from Kulukeoe Street to Likelike Highway, Likelike Highway from Kahekili Highway to Kamehameha Highway. (Completion by 6/8/02) WS
Install water mains along Yacht Club Street, Keoe Way and Place. (Completion by 8/01) WS
Rehabilitate Ahuimanu Road and Mokulele Drive. DC
Maili: Install water mains Mynah Street and Place, Monilial Place, Heleuma Street, Okokomo Street and Okohola Street. (Completion by 9/01) WS
Manoa: Install waterlines along University Avenue and fire hydrants from Oahu Avenue to Sea View Avenue. (Completion by 4/01) WS
Maunawili: Install a 16-inch water main and fire hydrants along Auloa Road from Castle Junction to near Lunaai Street. (Completion by 10/01) WS
Moiliili: Install water main on Date Street between Isenberg Street and University Avenue. (Completion by 3/01) WS
Pearl City: Rehabilitation of Komo Mai Drive and resurfacing from Lanikeha Street to Apoepoe Street.
Resurface Waimano Home Road to Kaahele Street.
Adjust manholes on Kaohohi Street. (Completion by 9/01) DC
Waialua: Install water lines and related equipment along Aikaula, Haona,Kanalu, Kuoha, Naluahi and Nauahi streets and Goodale Avenue. (Start 7/01 and Completion by 6/02) WS
Install eight and four-inch water mains with hydrants along Awaia, Awanei and Pupuole Streets and Pupuole Place. (Completion by 5/01) WS
Install water mains on Awanui and Paiwa streets. (Completion by 4/01) WS
Wilhelmina Rise: Install water mains under Maunahilu Place, Paula Drive, Puumalu Place and Paula Place. (Completion by 9/01) WS

Parades, Walks, Races & Other Street Closures
Contact Transportation Services: 527-5836
February 10 & 11: The annual Oahu Permiter Relay foot race will start at 4 p.m. on Saturday from Queen Kapiolani Park near the Queen's Beach Bath House and finish at the location Sunday betwee 11 am. and 5 p.m. There will be parking restrictions at the start/finish area.