The departments of Facility Maintenance (FM) and Design & Construction (DC), and the Board of Water Supply (WS) have scheduled the following roadwork for the week of July 7 between 8:30 a.m. and 3:30 p.m. unless otherwise noted. Estimated completion date is in parentheses.

Contacts: Design & Construction: 523-4049; Water Supply: 527-6148

New Projects: none

Continuing Projects:

Hawaii Kai: Construct an eight-inch main along Hawaii Kai Drive, from Pohoiki Place to Pepeekeo Street, and four-inch mains along various side streets in between. In addition, construct a 12-inch main along Kawaihae Street from Kalanianaole Highway to May Way, and eight-inch mains along May Way from Maunalua Avenue to Makaniolu Place, and along the entire length of Makaniolu Place. (Completion by 12/02) WS

Honolulu: Install new water main on Dillingham Boulevard between Waiakamilo Road and Liliha Street. (Completion by 9/02) WS

            Reconstruct Alewa Drive and Alencastre Street. (Completion by 9/02) DC

            Construct curb ramps at various locations.

            Dole Street, McCully Street and Nuuanu Avenue are next on the schedule for reconstruction. Mooheau Avenue is being completed. (Completion by 10/02) DC

Kaneohe: Rehabilitation of Streets: 47-357 Ahuimanu Road, Hakuhale Street, Waipaipai Street, Henoheno Street & Henoheno Place, Waipua Place, Kinana Way, Ahulimanu Way, Ahuilimanu Place, Hio Place, Apau Loop, Apau Place, Poomau Street, Keohapa Place, Kapehe Street, Kialua Street, Hoopala Street, Hui Kelu Street & Hui Kelu Place, Hui Akiki Place, Hui Akepa Place and Miomio Loop. (Completion by July 2002) DC

Maili: Rehabilitate Ehu and Meaulu roads and Alapaki, Kakalena and Milikami streets. (Completion by 8/02) DC

Nanakuli: Rehabilitate Hakimo Road, Laumania Avenue, Keaulana Avenue and Pohakunui Street. (Completion by 8/02) DC

Salt Lake: Curb ramps at various locations. (Completion 11/02) DC

            Salt Lake Boulevard Widening from Bougainville Drive to Maluna Street: Upgrade roadway to include 2 additional lanes in each direction and designated left and right turning lanes. Provide traffic controls, mass grading, temporary security fencing, sidewalks, curbs, gutters, curb ramps and property adjustments, including demolishing and reconstructing new structures and constructing new walls. Install drainage, water, sewer, traffic signal, streetlights, underground electrical system, oil lines, gas lines, pavement striping, markings and markers and traffic signs. (Completion by 6/04) DC

Sunset Beach: Install 12-inch to 16-inch water main along Kamehameha Highway from Paumalu Place to Kahae Road. (Completion by 12/02) WS

Waipahu: Rehabilitate Waipahu Street between Kunia Road and Mahoe Street. (Completion by 8/02) DC

            Construct improvements for Mokuola Street between Kahuailani Street and Nali Street, Hikimoe Street and Mokuola Street. (Completion by 10/02) DC

 

Parades, Walks, Races & Other Street Closures

 

None scheduled this week.

The above is based on the most current information available from the event organizers as of July 5, 2002 to the Department of Transportation Services.

###

Tuesday, July 09, 2002

© Copyright 2002-2006 City and County of Honolulu, Hawaii
Privacy Statement | Technical Support | Customer Service | Policy | Accessibility | Diversity Statement