September 6, 2002

ROAD WORK WEEKLY REPORT

Scheduled roadwork for week beginning September 8, 2002, for the Department of Design & Construction – Civil Design and Engineering (Construction Management Branch), Wastewater Design and Engineering (Construction Management Branch). Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

NEW PROJECTS:

 

CONTINUING PROJECTS:

AIEA

Curb Ramps – Hinu Place and Noelani Street, Kamahao Street and Noelani Street, Koaheahe Street and Noelani Street and Moanalua Road/Kaonohi Street/Moanalua Loop

Construct new curb ramps, sidewalks and driveways.  Install traffic signal and streetlight system, traffic signs, striping, markings and markers.

            (Estimated completion date, October 2002)

Curb Ramps at Ulune Street and Wiliko Street:

Installing striping, markings and markers.

            (Estimated completion date, November 2002)

 

EWA BEACH

Curb Ramps – Papipi Place and Papipi Road, Ihipehu Street and Pohakupuna Road, Pohahawai Place and Pohahawai Street:

Localized pavement, curb ramp, striping and marker repairs at various areas.

            (Estimated completion date, October 2002)

 

HONOLULU

Ala Moana Boulevard Beautification, Kalia Road to Kalakaua Avenue:

Install new concrete sidewalk and curb ramps, new street lighting and traffic signal systems, and landscape planting and irrigation system. PROJECT SUSPENDED ~ WORK WILL RESUME IN AUGUST 2002

 

Curb Ramps– Adams Lane/Bishop Street, Alakea Street/Merchant Street, Alakea Street/Queen Street, Alakea Street between South King Street & South Beretania Street, Bethel Street/Chaplain Lane, Maunakea Street/North Pauahi Street, Bishop Street/Merchant Street, Bishop Street/Queen Street, Chaplain Lane/Nuuanu Avenue, Maunakea Street/North Kukui Street:

Construct new curb ramps, transitional sidewalks, curbs gutters & pavement markings.

            (Estimated completion date in September 2002)

 

Curb Ramps – 10th Avenue/La’i Road, 10th Avenue/Hardesty Street, 10th Avenue/Kiwila Street, 10th Avenue/Maluhia Street; Kilauea Avenue/Malia Street, Pueo Avenue/Pahoa Avenue:

Construct new curb ramps, transitional sidewalks, curbs, gutters and pavement transitions.

            (Estimated completion date, November 2002

Curb Ramps– Isenberg/Fern, Isenberg/Lime, Seaside/Manukai, Kaiulani/Prince Edward, Prince Edward/Uluniu, Kamoku/Lauiki, King/Kapaakea, Kapiolani/Kaaha, Alohea/Kepuhi, Kiwili/Ahe, Dole/Wilder, Dole Midblock, Kalawao/Lowery:

Construct new curb ramps, transitional sidewalks, curbs and gutters and pavement markings.

            (Estimated completion date, September 2002)

 

Curb Ramps – Ainakoa/Aliikoa, 22nd/Kaimuki, Ahuli/Pahoa, Moho/Pahoa, Moa/Pahoa, Moa/Pueo, Ahuawa/Kilauea, Pikake/Wyllie, Wyllie/Wyllie Place, Hele/Lekeona. Construct new curb ramps, transitional sidewalks, curbs, gutters and pavement marking.

            (Estimated completion date, November 2002)

 

Punchbowl Street Improvements

Reconstruct curb ramps and restripe at King Street and Beretania Street intersection. PROJECT SUSPENDED ~ WORK WILL RESUME IN LATE 2002~

 

Rehabilitation of Streets - Mooheau Avenue, Monsarrat Avenue, Booth Road, Nuuanu Avenue, Dole Street and McCully Street:

            Reconstruct road pavement, sidewalks, curbs, gutters, curb ramps, driveways and drainage system. Relocate and/or adjust existing electrical facilities for HECO, Verizon, traffic signal, street light and appurtenances. Resurface, adjust manhole frame and cover to new grade and restripe.  **AREAS IN BOLD – INDICATE WORK IN PROGRESS FOR THIS WEEK**

            (Estimated completion date, December 2002)

 

Rehabilitation of Lusitania Street (Pauoa Road to Iolani Avenue): PROJECT SUSPENDED ~AWAITING CONSULTANT’S REVISIONS ~

            (Estimated completion date, August 2002)

 

Reconstruction of Streets – University Avenue (Sea View Avenue to Oahu Avenue), Old Pali Road.

            Reconstruct roadway pavement and base.  Adjust manhole frames and covers, street monument covers, and utility boxes to grade.  Install striping and pavement markers.

            (Estimated completion date, October 2002)

 

KAHUKU

Sidewalk Improvements at Pualalea Street: PROJECT SUSPENDED ~AWAITING CONSULTANT’S REVISIONS

 

KALIHI

Curb Ramps – Houghtailing Street/North King Street/Waikamilo Road, Houghtailing Street and Olomea Street, Bernice Street and Houghtailing Street, Mookaula Street and Waikamilo Road, Houghtailing and Monte Cooke Place, Houghtailing and Peter Buck, Houghtailing Street and Kohou Street, Koapaka Street/Lagoon Drive/Waiwai Loop:

Construct new curb ramps, sidewalks and driveways.  Install traffic signal and streetlight system, traffic signs, striping, markings and markers.

            (Estimated completion date, November 2002)

 

Curb Ramps –Halina Street and Naai Street, Kaua Street and Middle Street, Haumana Place / Middle Street / Notley Street, Ahonui Street and North School Street, Dement Street and North School Street, Bernice Street and Kapalama Avenue, Gregory Street and Kapalama Avenue, Kapalama Place and Palapala Place, Kapalama Avenue and North School Street, Kaikuahine Street and Kapalama Avenue, Houghtailing Street and North School Street, Aupuni Street and North School Street, North School Street and Pohaku Street, Kokea Street and North School Street, Kamenani Street and North King Street, Long Lane and North King Street, Morris Lane and North King Street, Hoapili Lane and North King Street, Kokea Street and North King Street, Hikina Lane and North King Street, Kanoa Street and Palama Street, Lopez Lane and Palama Street, Kanoa Street and Pua Lane, Emmeluth Lane and Iao Lane, Alneo Street (Mid-block) between Kuakini Street and North School Street, North School Street (Mid-block) between Momolio Street and Liliha Street, Holokahana Lane and Liliha Street, Liliha Street and Liliha Street, Halapia Street and Liliha Street, Kaliawa Street and Sand Island Access Road, Auiki Street and Puuhale Road, Iwilei Road and Kuwili Street, Iwilei Road and Pacific Street, Puuhale Place and Puuhale Road, Kahai Street and Kalihi Street, Democrat Street and Libby Street, Hart Street and Waiakamilo Road, Kalani Street and McNeill Street, Colburn Street and Waikamilo Road, Kaumualii Street and McNeill Street, Kaiwiula Street and McNeill Street, Alokele Street and Kaiwiula Street, Moonui Street and Moowaa Street, Kaumualii Street and Moowaa Street, Kaumualii Street and Kohou Street.

Construct new curb ramps, sidewalks, and driveways.  Install traffic signal and streetlight system, traffic signs, striping, markings and markers.

**AREAS IN BOLD – INDICATE WORK IN PROGRESS FOR THIS WEEK**

            (Estimated completion date, November 2002)

 

Rehabilitation of west bound lanes of Dillingham Boulevard between Kokea Street and Waikamilo Road:

            (Estimated completion date, September 2002)

 

KAILUA: Curb Ramps – Hele/Lekeona, Kailua/Hoolai: Construct new curb ramps, transitional sidewalks, curbs and gutters and pavement markings.

            (Estimated completion date, November 2002)

Oneawa Street Sidewalk Improvements, Oneawa Street from Olomana Street to Kawainui Street: Construct new asphalt concrete sidewalk, curb ramps, curbs and gutters and pavement markings.

            (Estimated completion date, February 2003)

 

KANEOHE

Rehabilitation of Streets –47-357 Ahuimanu Road, Hakuhale Street, Waipaipai Street, Henoheno Street & Henoheno Place, Waipua Place, Kinana Way, Ahulimanu Way, Ahuilimanu Place, Hio Place, Apau Loop, Apau Place, Poomau Street, Keohapa Place, Kapehe Street, Kialua Street, Hoopala Street, Hui Kelu Street & Hui Kelu Place, Hui Akiki Place, Hui Akepa Place, Miomio Loop, Hinalani Place & Hinalani Street, Hinapu Street, Kohina Street, Halaulani Street, Ahu Nani Place, Kalimaloa Street, Heeia Street, Hilinama Street, Humu Street & Place, Kapea Street & Place, Nana Place, Nahiku Street & Place, Punalei Place, Nakoa Place, Keoe Way & Place, Yacht Club Street & Place, Grote Road & Place, Haleloke Place, Haunani Place, Seabury Place, Halliday Place, 45-227 Kahanahou Circle, Wailele Road, Kailiwai Place, William Henry Road, Makena Place and Street, Kuneki Street, Holouka Place, Maeha Place, Kauhaa Place, Kumoo Loop & Place, Pilina Way & Place, Kuahulu Way & Place, Kulukeoe Place & Street; Kapoo Street, Pua Alowalo Street, Lanipola Place, Pua Inia Street, Pikoiloa Place, Wainana Street, Onekai Street, Wena Street, Halekou Road:

Reconstruction and resurfacing of roadways, adjust utility manholes and pavement markings.

            (Estimated completion date, January 2003)

 

Rehabilitation of Kamehameha Highway from Heeia Street to Long Bridge:

Utility manhole adjustment and pavement markings.

            Estimated completion date, August 2002)

 

MAKAKILO

Curb Ramps Panana Street and Weio Street:

Localized pavement, curb ramp, striping and marker repair work at various areas.

            (Estimated completion date, October 2002)

MILILANI

Curb Ramps at – Anania Drive/Noholoa Loop, Kaholo Street/Anania Drive, Kaholo Street/Kapuahi Street, Kaholo Street/Anania Drive, Hokualii Court/Hokualii Street/Welehu Street, Makapipipi Street/Makohilani Street, Hokulewa Loop/Hokulewa Street/Kuahelani Avenue, Nawenewene Circle, Waihau Street/Waimakua Drive:

Construct new curb ramps, transitional sidewalks, curbs and gutters and pavement transitions.

            (Estimated completion date, October 2002)

 

Rehabilitation of Kuahelani Avenue and Meheula Avenue:

Construct new curb ramps, sidewalks, and driveways. Install traffic signal system, streetlight system, traffic signs, striping, markings and markers.

            (Estimated completion date, December 2002)

 

MOANALUA

Curb Ramps at – Mahiole Street (Mid-block) between Onipa’a Street and Pineapple Place, Maalahi Street and Mahiole Street:

Installing striping, markings and markers.

            (Estimated completion date, November 2002)

 

PEARL CITY

Curb Ramps at – Aalii Place/Auhuhu Street, Anini Place/Auhuhu Street:

Construct new curb ramps, transitional sidewalks, curbs, gutters and pavement transitions.

            (Estimated completion date, November 2002)

 

Rehabilitation of Hooni Place/Komo Mai Drive, Hoolehua Street/Komo Mai Drive, Hookupa Street/Komo Mai Drive, Hooulu Street/Komo Mai Drive; Hoomalu Street/Komo Mai Drive:

Construct new curb ramps, transitional sidewalks, curbs and gutters, and pavement transitions.

            (Estimated completion date, December 2002)

 

SALT LAKE

Curb Ramps at – Palahinu Place/Piikea Street, Ekupane Street/Hakupapa Street, Haloa Drive/Hakupapa Street, Haloa Drive/Molina Street, Manuwa Street/Keaka Drive, Ala Lilikoi Street/Ala Lilikoi Place, Ala Ilima Street/Ala Laulani Street, Lunalilo Home Road, Kawaihae Street/Hakalau Place, Ala Akulikuli Street and Ala Laulani Street, Ala Lilikoi Street and Ala Loke Street, Ala Ilima Street and Ala Nioi Place, Ala Makahala Place and Ala Napunani Street, Ala Napunani Street and Ala Poha Place, Ala Napunani Street and Likini Street:

Construct new curb ramps, transitional sidewalks, curbs and gutters, and pavement transitions.

            (Estimated completion date, November 2002)

 

Salt Lake Boulevard Widening Bougainville Drive to Maluna Street:

Upgrade roadway to include 2 additional lanes in each direction, with designated left and right turning lanes. Provide traffic controls, mass grading, temporary security fencing, sidewalks, curbs, gutters, curb ramps and property adjustments, including demolishing and reconstructing new structures and constructing new walls. Install detention basins, drainage, water, sewer, traffic signal, streetlights, underground electrical system, oil lines, gas lines, pavement striping, markings and markers and traffic signs.

            (Estimated completion date, June 2004)

 

VILLAGE PARK

Curb Ramps at – Kaaholo Street and Kimi Street, Kaaholo Street and Kupuna Loop, Kahakea Street and Kupuna Loop, Kehela Street and Kupuna Loop:

Installing traffic signs, striping, markings and markers.

            (Estimated completion date, October 2002)

 

WAHIAWA

Rehabilitation of – Puninoni Street, Puninoni Place, Kaliko Drive, Dole Road, Rose Street, Loko Drive, Loki Place, Kilau Place, Plum Street, Neal Avenue, Lemi Street, Olive Avenue, Mala Street, Ilima Street:

Reconstruct and resurface roadways, adjust manholes, monuments and gratings to new road grade and restore pavement striping.

            (Estimated completion date, October 2002)

 

WAIANAE: Curb Ramps – Analipo Place/Analipo Street, Analipo Street/Puhano Street:

Construct new curb ramps, transitional sidewalks, curbs and gutters and pavement markings.

            (Estimated completion date, November 2002)

 

WAIPAHU

Curb Ramps – Hiapo Street and Mahoe Street, Hikimoe Street and Kahuailani Street, Hikimoe Street and Kahuailani Street and Mokuola Street, Honowai Street and Kipou Street, Leoku Street and Farrington Highway/Leolua Street, Mahoe Place and Mahoe Street, Pupukahi Street and Pupumomi Street, Pupukahi Street and Pupupuhi Street, Pupukupa Street and Pupupuhi Street and Waikele Road, Pupumomi Street and Pupunohe Street, Pupumomi Street and Pupupuhi Street, Pupunohe Street and Pupupuhi Street, Pupuole Street and Pupupuhi Street.

Installing striping, markings and markers.

            (Estimated completion date, October 2002)

 

Curb Ramps at Puamano Place and Waipahu Street:

Installing striping, markings and markers.

            (Estimated completion date, November 2002)

 

Roadway Improvements for Mokuola Street (Kahuailani Street to Nali Street):  Reconstruct roadway pavement and base, curbs and gutters, sidewalks and driveway.  Install striping and pavement markings.  Pavement rehabilitation work on Hikimoe Street and Mokuola Street:  Reconstruct roadway pavement, resurface and restripe.

            (Estimated completion date, October 2002)

 

WAIPIO

Curb Ramps at – Lelepua Street and Waipio Uka Street:

Construct new curb ramps, sidewalks and driveways. Install traffic signal and streetlight system, traffic signs, striping, markings, and markers.

            (Estimated completion date, November 2002)

 

WEST LOCH

Curb Ramps at - Olepekupe Street, Nahawele Street, Pa Street, Panapanapuhi Street, Paua Place:

Localized pavement, curb ramp, striping and marker repairs at various areas.

            (Estimated completion date, October 2002)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

September 8, 2002 Sunday
5:45AM Starts
2:00PM Ends

DICK EVANS MEMORIAL BIKE RACE sponsored by the Hawaii State Cycling Association. It will consist of 125 cyclists.  The event will start at Keahole St. near to Hawaii Kai Park & Ride Lot,  to Hawaii Kai Dr., to Kalanianaole Hwy., to Waialae Ave., to Kilauea Ave., to 18th Ave.,  to Diamond Head Rd. to Paki Ave., to Ala Wai Blvd., to Niu St., to Ala Moana Blvd., to Nimitz Hwy., to Kamehameha Hwy., to Farrington Hwy., to Kunia Rd., to Wilikina Dr., to Kamananui Rd., to Kamehameha Hwy., to Joe Leong Hwy., to Kamehmeha Hwy., (around north shore to windward side) to Kahekili Hwy., to Kulukeoe St., to Keneke St., to Anoi Rd., to Likelike Hwy., to Kamehameha Hwy., to Kaneohe Bay Dr., to Mokapu Saddle Rd., to Kapaa Quarry Rd., to Kalanianaole Hwy., to Auloa Rd., to Kalanianaole Hwy., to Kealahou St., to Hawaii Kai Dr., to Lunalilo Home Rd., to Wailua St., to Hawaii Kai Dr., to finish at Oahu Club. Contact: John Kelley 525-8422

 

September 8, 2002 Sunday
7:00AM Starts
9:00AM Ends

ROSIE WALL MEMORIAL 5K RUN/WALK sponsored by Friends of Rosie Wall. The event is expected to have 200 participants. It will start at Kailua Recreation Center, to N. Kainalu Dr., to Kaha St., to Kainui Dr., to N. Kainalu Dr., to end at Kailua Rec. Center. Contact: Charles Wall 532-5880 Email:  cwall@aloha.net

 

September 13, 2002 Friday
3:30PM Starts
4:30PM Ends

WAIALUA HIGH SCHOOL HOMECOMING PARADE sponsored by WAIALUA HIGH SCHOOL .The event is expected to have 400 marchers, 7 vehicles, 9 floats, & 1 band. Vehicles only, will start at WHS Parking Lot to Farrington Hwy., to Kaukonahua Rd., through Haleiwa town, to Wailua District Park, Vehicles joins marchers,  proceed together, to Goodale Ave., to Farrington Hwy., to end at WHS  parking lot. Contact: Gwen Lavarias 637-8249 Fax: 637-8209

 

September 13, 2002 Friday
6:00PM Starts
10:30PM Ends

ALOHA FESTIVALS DOWNTOWN HO'OLAULEA/STREET FEST sponsored by Aloha Festivals. The event is expected to have 30,000+ participants. Traffic will be diverted at 5:30 pm for setup. The event will close: 1) Bishop Street, all lanes, Beretania St. to Nimitz Hwy., 2) Merchant Street, all lanes, Nuuanu Ave. to Bishop St., 3) Queen Street, all lanes, Alakea St. to Fort St. Mall, 4) Hotel Street, River St. to Richards St.  Contact: Moana Yee 589-1771 Fax: 596-4919. For more info, visit their website: www.alohafestivals.com

 

September 14, 2002 Saturday
9:00AM Starts
1:00PM Ends

ALOHA FESTIVALS FLORAL PARADE sponsored by Aloha Festivals. The event is expected to have 3,000 marchers, 9 vehicles, 25 bands, 15 floats, 12 horse units. It will start at Ala Moana Park ewa entrance/exit, to Ala Moana Blvd., to Kalakaua Ave., left onto Monsarrat Ave., end at Waikiki Shell Parking Lot in Queen Kapiolani Park. Contact: Aloha Festivals 589-1771 Fax: 596-4919 For more info, visit their website: http://www.alohafestivals.com/

 

The above is based on the most current information available from the event organizers as of September 6, 2002 to the Department of Transportation Services.