January 16, 2003

ROAD WORK WEEKLY REPORT

Scheduled roadwork for the week beginning January 19, 2003, for the Department of Design & Construction. Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Curb ramps —Ulune Street and Wiliko Street:  installing, striping, markings and markers.

 (Estimated completion date, January 2003)

 

EWA

Old Fort Weaver Road, Mokuola Street & North Road Sidewalk Improvements - Old Fort Weaver Road from Farrington Highway to Fort Weaver Road: Construct new asphalt concrete sidewalk, curb, CRM wall, and driveway aprons.

(Estimated completion date, March 2003)

 

HONOLULU

Curb ramps – Pensacola Street/Wilder Avenue, Piikoi Street/Pensacola Street: construct new curb ramps, transitional sidewalks, curbs and gutters and pavement transitions.

 

Curb ramps – Adams Lane/Bishop Street, Alakea Street/Merchant Street, Alakea Street/Queen Street, Alakea Street between South King Street & South Beretania Street, Bethel Street/Chaplain Lane, Maunakea Street/North Pauahi Street, Bishop Street/Merchant Street, Bishop Street/Queen Street, Chaplain Lane/Nuuanu Avenue, Maunakea Street/North Kukui Street:  construct new curb ramps, transitional sidewalks, curbs,and gutters and pavement markings.

 

Rehabilitation of streets - Mooheau Avenue, Monsarrat Avenue, Nuuanu Avenue, Dole Street and McCully Street: reconstruct road pavement, sidewalks, curbs, gutters and driveways.  Construct curb ramps, bus pads and drainage system.  Relocate and/or adjust existing electrical facilities for HECO, Verizon, traffic signal, street light and appurtenances.  Resurface, adjust manhole frame and cover to new grade and restripe.  Install traffic signs.

(Estimated completion date, April 2003)

 

 

Curb Ramps - Paoa Place, Kapahulu Avenue/Ala Wai Golf Course entrance, Piikoi Street/Pensacola Street, Beretania Street from Piikoi Street to Waiau Place, Piikoi Street/Kinau Street, Dole Street/East-West Road:  Construct new curb ramps, transitional sidewalks, curbs and gutters, and pavement transitions.

(Estimated completion date, January 2003)

 

Lusitana Street/Ladd Lane Emergency Sewer Line Reconstruction –Lusitana Street between the Pauoa Road Intersection and Auwaiolimu Intersection:  Road will be one-way flowing from Pauoa Road toward Auwaiolimu Street.  Sewer line repair work (cured in place pipe, approximately 160’).

            (Estimated completion date, January 31, 2003)

 

KAILUA

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

(Estimated completion date, December 2003)

 

Oneawa sidewalk improvements, Oneawa Street from Olomana Street to Kawainui Street: construct new asphalt concrete sidewalk, curb ramps, curbs and gutters and pavement markings.  

                                    (Estimated completion date, February 2003)

 

KAIMUKI

Curb ramps – 13th Avenue and Mahina Avenue, 21st Avenue and Pahoa Avenue, Olokele Avenue and Winam Avenue:  install striping, markings and markers.

(Estimated completion date, January 2003)

 

KALIHI

 

Curb ramps - Halina Street and Naai Street, Kaua Street and Middle Street, Haumana Place / Middle Street / Notley Street, Ahonui Street and North School Street, Dement Street and North School Street, Bernice Street and Kapalama Avenue, Gregory Street and Kapalama Avenue, Kapalama Place and Palapala Place, Kapalama Avenue and North School Street, Kaikuahine Street and Kapalama Avenue, Houghtailing Street and North School Street, Aupuni Street and North School Street, North School Street and Nad Pohaku Street, Kokea Street and North School Street, Kamenani Street and North King Street, Long Lane and North King Street, Morris Lane and North King Street, Hoapili Lane and North King Street, Kokea Street and North King Street, Hikina Lane and North King Street, Kanoa Street and Palama Street, Lopez Lane and Palama Street, Kanoa Street and Pua Lane, Emmeluth Lane and Iao Lane, Alneo Street (Mid-block) between Kuakini Street and North School Street, North School Street (Mid-block) between Momolio Street and Liliha Street, Holokahana Lane and Liliha Street, Liliha Street and Liliha Street, Halapia Street and Liliha Street, Kaliawa Street and Sand Island Access Road, Auiki Street and Puuhale Road, Iwilei Road and Kuwili Street, Iwilei Road and Pacific Street, Puuhale Place and Puuhale Road, Kahai Street and Kalihi Street, Democrat Street and Libby Street, Hart Street and Waiakamilo Road, Kalani Street and McNeill Street, Colburn Street and Waiakamilo Road, Kaumualii Street and McNeill Street, Kaiwiula Street and McNeill Street, Alokele Street and Kaiwiula Street, Moonui Street and Moowaa Street, Kaumualii Street and Moowaa Street, Kaumualii Street and Kohou Street:

Construct new curb ramps, sidewalks, and driveways.  Replace traffic signal and streetlight system, traffic signs, striping, markings and markers.

(Estimated completion date, March 2003)

 

 

Curb ramps – Houghtailing Street/North King Street/Waiakamilo Road, Bernice Street/Houghtailing Street:  replace traffic signal system, construct new curb ramps, transitional sidewalks, curbs, gutters and pavement transition.  Install traffic signs, striping, markings and markers.

(Estimated completion date, February 2003)

 

KANEOHE

Rehabilitation of streets, Unit 21 – Pilina Way & Place, Kuahulu Way & Place, Kulukeoe Place & Street; Kapoo Street, Pua Alowalo Street, Lanipola Place, Pua Inia Street, Pikoiloa Place, Wainana Street, Onekai Street, Wena Street, Halekou Road, Meakaua Street, Namoku Place, Pailaka Place, Mikihilina Street, Keana Road, Malulani Street, Pailaka Place, Mikihilina Street and Keana Road, Aumoana Way & Place, Kaimalino Street & Place, Launa Aloha Place, Ilikai Street, Milokai Street & Place, Nunu Street, Old Mokapu Road, Omao Street, Palapu Street, Ohana Street, Makua Street, 327 Hualani Street, Kawainui Street:

Reconstruction and resurfacing of roadways, adjust utility manholes and pavement markings. 

(Estimated completion date, January 2003)

 

MAKIKI

Curb ramps – Piikoi Street and Wilder Avenue, Liholiho Street and Wilder Avenue, Poki Street and Wilder Avenue, Enos Lane and Makiki Street: striping, markings and markers.

(Estimated completion date, March 2003)

 

Emergency Wall Repair @ Kamamalu Avenue – At the Rear of Property 1619 Lusitana Street: Construct foundation and concrete wall with guardrail.  Demolish existing CRM wall and gunite slope.

            (Estimated completion date, February 2003)

 

MANOA

Curb ramps  – East Manoa Road and Koaniani Way: install striping, markings and markers.

(Estimated completion date, March 2003)

 

 

MILILANI

Rehabilitation of Streets, Unit 12B – Kuahelani Avenue and Meheula Avenue: construct new curb ramps, sidewalks, driveways.  Install traffic signal system, streetlight system, traffic signs, striping, markings and markers.

(Estimated completion date, March 2003)

 

MOANALUA

Curb ramps – Mahiole Street (mid-block) between Onipa’a Street and Pineapple Place, Maalahi Street and Mahiole Street: installing striping, markings and markers.

(Estimated completion date, March 2003)

 

SALT LAKE

Curb ramps- Ala Akulikuli Street and Ala Laulani Street, Ala Lilikoi Street and Ala Loke Street, Ala Ilima Street and Ala Nioi Place, Ala Makahala Place and Ala Napunani Street, Ala Napunani Street and Ala Poha Place, Ala Napunani Street and Likini Street: install striping, markings and markers.

(Estimated completion date, March 2003)

 

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:

Upgrade roadway to include 2 additional lanes in each direction, with designated left and right turning lanes. Provide traffic controls, mass grading, temporary security fencing and electrical overhead lines, sidewalks, curbs, gutters, curb ramps and property adjustments, including demolishing and reconstructing new structures and constructing new walls. Install detention basins, drainage, water, sewer, traffic signal, streetlights, underground electrical system, oil lines, gas lines, pavement striping, markings and markers, and traffic signs, irrigation and landscaping.

            (Estimated completion date, June 2004)

 

WAIANAE

Mailiilii Stream Slope Lining Repairs:

Construct new channel lining.  Install new metal guardrail.

(Estimated completion date, February 2003)

 

WAIPAHU

Curb Ramps at - Puamano Place and Waipahu Street: Installing striping, markings and markers.

            (Estimated completion date, March 2003)

 

 

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

January 19, 2003 Sunday
9:00AM Starts
1:00PM Ends

BRUNCH ON THE BEACH STREET FESTIVAL sponsored by the Waikiki Improvement Assn./C&C Honolulu.  The event is expected to have 5,000+ participants.  Traffic will be diverted starting 2:30 am for setup. The event will close Kalakaua Avenue, all traffic lanes/sidewalk areas, from Kaiulani Avenue to Liliuokalani Avenue. Contact: DTS-TST Div. 527-6009

January 20, 2003 Monday
9:00AM Starts
11:00AM Ends

DR. MARTIN LUTHER KING JR. DAY PARADE sponsored by Martin Luther King Coalition. The event is expected to have 2,000 marchers, 16 vehicles, 4 bands.  It will start at Ala Moana Park to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave., end at Waikiki Shell Parking Lot in Queen Kapiolani Park.  Contact: Marsha Joyner 395-4612 Fax: 396-3595

 

January 25, 2003 Saturday
9:00AM Starts
11:00PM Ends

NIGHT IN CHINATOWN, Chinese New Years STREET FESTIVAL sponsored by the Chinatown Merchants Association. The event is expected to have 10,000 + participants. Traffic will be diverted starting 2:30 am for setup. The event will close all traffic lanes/sidewalk areas: 1) MAUNAKEA ST., Beretania St to King St., 2) PAUAHI ST., River St to Smith St., 3) HOTEL ST, Richards St. to River St., Contact Sun Hung Wong 595-6417. For more info on Chinatown events, visit their website www.chinatownhi.com

January 25, 2003 Saturday
4:00PM Starts
5:30PM Ends

NIGHT IN CHINATOWN PARADE sponsored by the Chinatown Merchants Association. Parade will consist of 1000 marchers, 30 vehicles, 3 bands. It will start at Richards St./Hotel St., to Hotel St., ewa bound to end at Aala Park. Contact Sun Hung Wong 595-6417. For more info on Chinatown events, visit their website www.chinatownhi.com

The above is based on the most current information available from the event organizers as of January 16, 2003.  TST Division, Department of Transportation Services  Phone: 808-527-6009  Fax: 808-523-4446