You are here:  Main / Customer Services / Public Communications Division / Honolulu News Releases 2003 / Road Work Weekly Report

March 13, 2003

ROAD WORK WEEKLY REPORT

Scheduled roadwork for the week beginning March 16, 2003, for the Department of Design & Construction. Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Curb ramps —Ulune Street and Wiliko Street:  installing, striping, markings and markers.

 (Estimated completion date, March 2003)

 

EWA

Old Fort Weaver Road, Mokuola Street & North Road Sidewalk Improvements - Old Fort Weaver Road from Farrington Highway to Fort Weaver Road: Construct new asphalt concrete sidewalk, curb, CRM wall, and driveway aprons.

(Estimated completion date, March 2003)

 

HONOLULU

Rehabilitation of Streets - Dillingham Boulevard (from King Street to Waiakamilo Street):

Cold milling, asphalt paving, striping, and utility manhole adjustments.

            (Estimated completion date, March 2003)

 

Reconstruction of Sidewalks, Ala Moana Area – Alohi Way, Elm Street, Pensacola Street, Piikoi Street, Hoolai Street, Kamaile Street, Alder Street, Birch Street, Cedar Street, Liona Street, Sheridan Street, Keeaumoku Street, Rycroft Street, Lauula Way, Makaloa Street: Demolish and reconstruct existing concrete sidewalks.

            (Estimated completion date, August 2003)

 

Curb ramps – Pensacola Street/Wilder Avenue: construct new curb ramps, transitional sidewalks, curbs and gutters and pavement transitions.

            (Estimated completion date, March 2003)

 

Rehabilitation of streets - Nuuanu Avenue, Dole Street and McCully Street: reconstruct road pavement, sidewalks, curbs, gutters and driveways.  Construct curb ramps, bus pads and drainage system.  Relocate and/or adjust existing electrical facilities for HECO, Verizon, traffic signal, street light and appurtenances.  Resurface, adjust manhole frame and cover to new grade and restripe.  Install traffic signs.

(Estimated completion date, April 2003)

 

Curb Ramps - Dole Street/East-West Road:  Construct new curb ramps, transitional sidewalks, curbs and gutters, and pavement transitions.

(Estimated completion date, March 2003)

 

Lusitana Street/Ladd Lane Emergency Sewer Line Reconstruction –Lusitana Street between the Pauoa Road Intersection and Auwaiolimu Intersection:  Road will be one-way flowing from Pauoa Road toward Auwaiolimu Street.  Sewer line repair work (cured in place pipe, approximately 160’).

            (Estimated completion date, February 2003)

 

KAILUA

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

(Estimated completion date, December 2003)

 

KAIMUKI

Curb ramps – 13th Avenue and Mahina Avenue, 21st Avenue and Pahoa Avenue, Olokele Avenue and Winam Avenue:  install striping, markings and markers.

(Estimated completion date, February 2003)

 

KALIHI

Emergency Sewer Repair: Amelia Street/Kalihi Stream

(March 17, 2003 to April 17, 2003)

 

Curb ramps –Houghtailing Street and North School Street: Construct new curb ramps, sidewalks, and driveways.  Replace traffic signal and streetlight system, traffic signs, striping, markings and markers.

(Estimated completion date, March 2003)

 

MAKIKI

Curb Ramps at Various Locations - Piikoi Street and Wilder Avenue, Liholiho Street and Wilder Avenue: Construct new curb ramps and sidewalks.  Replace traffic signal system, traffic signs, striping, marking and markers.

            (Estimated completion date, March 2003)

 

MANOA

Curb Ramps – East Manoa Road and Koaniani Way: Install striping, markings, and markers.

            (Estimated completion date, March 2003)

 

MOANALUA

Curb ramps – Mahiole Street (mid-block) between Onipa’a Street and Pineapple Place, Maalahi Street and Mahiole Street: installing striping, markings and markers.

(Estimated completion date, March 2003)

 

NUUANU

Fencing at 2527A  Henry Street:  Cleaning of existing drainage ditch and constructing a debris fence.

                                    (Estimated completion date, February 2003)

 

SALT LAKE

Curb ramps- Ala Akulikuli Street and Ala Laulani Street, Ala Lilikoi Street and Ala Loke Street, Ala Ilima Street and Ala Nioi Place, Ala Makahala Place and Ala Napunani Street, Ala Napunani Street and Ala Poha Place, Ala Napunani Street and Likini Street: install striping, markings and markers.

(Estimated completion date, March 2003)

 

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:

Upgrade roadway to include 2 additional lanes in each direction, with designated left and right turning lanes. Provide traffic controls, mass grading, temporary security fencing and electrical overhead lines, sidewalks, curbs, gutters, curb ramps and property adjustments, including demolishing and reconstructing new structures and constructing new walls. Install detention basins, drainage, water, sewer, traffic signal, streetlights, underground electrical system, oil lines, gas lines, pavement striping, markings and markers, and traffic signs, irrigation and landscaping.

            (Estimated completion date, June 2004)

 

WAHIAWA

Curb Ramps at Various Locations, FY 2001(6) – California Avenue/Rose Street:

Construct new curb ramps, transitional sidewalks, curbs and gutters, and pavement transitions.

            (Estimated completion date, February 2003)

 

WAIANAE

Mailiilii Stream Slope Lining Repairs: Construct new channel lining.  Install new metal guardrail.

(Estimated completion date, February 2003)

 

WAIPAHU

Curb Ramps at - Puamano Place and Waipahu Street: Installing striping, markings and markers.

            (Estimated completion date, March 2003)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

Sun.,March 16
5 PM - 7:30PM

HONOLULU FESTIVALS PARADE sponsored by JTB Hawaii/Honolulu Festival Organizing Committee.  The event is expected to have 6,000 marchers, 20 vehicles, 5 floats, 3 bands, 12 Mikoshi.  It will start at Kalakaua Ave. at Saratoga Rd., kkhd on Kalakaua Ave., to end at Waikiki Shell parking lot, Queen Kapiolani Park. SPECIAL NOTE: Kalakaua Ave., all lanes, between, Kapiolani Blvd. to Kalaimoku St. will be closed prior to start of parade (about 2:45 pm) for movement of large float/displays from Hawaii Convention Center to staging areas.Contact Nelson Fujio 591-8311 Fax: 591-0257 For more info, visit http://www.honolulufestival.com

Mon,March 17
Noon - 1 PM

ST. PATRICK'S DAY PARADE sponsored by Friendly Sons of Saint Patrick of Hawaii. The event is expected to have 500 marchers, 30 vehicles, 4 bands. It will start at Atkinson/Ala Moana Blvd., to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave., to end at Queen Kapiolani Park. Contact Kevin Kelly 956-6651 Fax: 956-5308

Mon, March 17
6 PM - 11 PM

ST. PATRICK'S DAY BLOCK PARTY sponsored by Murphy's Bar & Grill. The event is expected to have 3,000+ participants. Curb lanes will be closed from 3 pm for setup. The event will close 1) NUUANU AVE., all traffic lanes/sidewalk areas, from King St. to Nimitz Hwy. 2) MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St. 3) MARIN LN, all traffic lanes/sidewalk areas. Contact Don Murphy 531-0422 Fax: 533-4943

Sat, March 22
12:30PM -1:30PM

GREAT HAWAIIAN RUBBER DUCKIE RACE PARADE sponsored by United Cerebal Palsy Assoc. of Hawaii. The event is expected to have 100 marchers, & 2 vehicles. It will start at McCully Shopping Center, to McCully St., to Ala Wai Blvd., across Kalakaua Ave., into Ala Wai Promenade finish area. Contact Donna Fouts 532-6744 Fax: 532-6747

The above is based on the most current information available from the event organizers as of March 13, 2003.  TST Division, Department of Transportation Services  Phone: 808-527-6009  Fax: 808-523-4446.

Thursday, March 13, 2003

© Copyright 2002-2006 City and County of Honolulu, Hawaii
Privacy Statement | Technical Support | Customer Service | Policy | Accessibility | Diversity Statement