ROAD WORK WEEKLY REPORT

 

Scheduled roadwork for the week beginning August 22, 2004, for the Department of Design & Construction. Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AHUIMANU

Curb Ramps at - Hui Aeko Place /Hui Aeko Way: Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

Rehabilitation of Ahuimanu Place (Kahekili Highway to Ahuimanu Road) and Hui Ulili Street (Ahuimanu Place to Hui Iwa Street): Reconstruction and resurfacing of roadways, adjustment of utility manholes and installation of permament pavement markings.

            (Estimated completion date, November 2004)

 

AINA HAINA

Curb Ramps at West Hind Drive/Apo Drive/Nohu Street: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

EWA

Curb Ramps at - Papipi Road /Papipi Place, Koka Street /Kolowaka Drive, Waimomona Place/Kolowaka Drive, Waihua Place/Kolowaka Drive, Waiapo Place/Kolowaka Drive, Wailewa Place/Kolowaka Drive, Poowai Place/Kolowaka Drive, Pahika Street /Renton Road, Renton Road at West Loch Villages: Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

Fort Weaver Road/Hapalua Street Sewer Rehabilitation: Installation of liner in sewer lines at the intersection of Fort Weaver Road and Hapalua Street.

Estimated completion date, August 2004.

 

HAWAII KAI

Curb Ramps at Lanipuao Street/Kaumakani Street, Kekupua Street/Kaumakani Street.  Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

HONOLULU

Curb Ramps at Adams Lane/Bishop Street, Chaplain Lane/Nuuanu Avenue, Fort Street/S. Kukui Street, Queen Emma Square/Queen Emma Street/S. Kukui Street: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

Ala Wai Boulevard Improvements:  Construct bulbouts and landscaping.

            (Estimated completion date, November 2004)

 

Curb Ramps at - Iolani Avenue/Miller Street, Iolani Avenue/Pele Street: Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

Curb Ramps at - Lukepane Avenue/Leialoha Avenue, Waialae Avenue/5th Avenue/6th Avenue, University Avenue/Hihiwai Street, Date Street/Coolidge Street, Date Street/Citron Street, Young Street/Pawaa Lane, Young Street/Kemole Lane, Rycroft Street/Birch Street, Young Street/Wong Ho Lane, Young Street/Victoria Street, Captain Cook Avenue/Emerson Street, Alapai Street/Manele Street, Palolo Avenue/Carlos Long Street, Prospect Street/Nehoa Street, Nehoa Street/Lewalani Street, Nehoa Street/Kewalo Street, Cedar Street/Rycroff Street, Palolo Avenue/Uilani Place, Palolo Avenue/Paliahina Place, Lowery Avenue/Kalawao Street, Woodlawn Drive/Lowery Avenue/Pamoa Road, Kamehemeha Avenue/Oahu Avenue, Palolo Avenue midblock, Pauoa Road/Namokueha Street/Akaka Lane, S. School Street/Barron Lane, N. School Street/Diamond Lane, Aala Street/N. Kukui Street, Palama Street/Iao Lane, Palama Street/Panalaau Street, N. Kuakini Street/Kaluhikai Lane, N. Kuakini Street/Bachelot Street/Sereno Street, Kaiulani Avenue/Koa Avenue, Uluniu Avenue/Koa Avenue, N. School St/Old Palama Street, Palama Street/Iao Lane, N. School Street/Kokea Street/Lanakila Avenue, Iwilei Road/Sumner Street, N. School Street/Frog Lane, Liliha Street/Kuakini Street/Holokahana Street/Palama Street/Panalaau Street, Old Palama Street/Iao Lane,

N. School Street/Loikalo Place/Pahaku Street:  Construct new curb ramps, sidewalks, driveways.  Install striping, marking and markers.

            (Estimated completion date, August 2004)

 

Emergency Resurfacing of Kapiolani Boulevard from Kalakaua Avenue to Date Street:  Reconstruction and asphalt resurfacing, permanent pavement marking to be performed at night Monday thru Friday, 7 pm to 5am.  Adjustment of utility manholes and installation of traffic loop sensors, Monday thru Friday 9:00 am to 3 pm.

            (Estimated completion date, August 2004)

 

Kapiolani Boulevard Sewer Emergency Repair:  Sewer work from Atkinson Drive to Pensacola Avenue on Kapiolani Blvd.

(Estimated completion date, October 2004)

 

Maunakea Street Sidewalk Improvements: Reconstruct curb, gutter, and sidewalk on Maunakea Street between Beretania Street and King Street. Work includes installation of new granite tile surface sidewalks, signs, utility boxes, and roadway resurfacing.

            (Estimated completion date, October 2004)

 

Rehabilitation of Piikoi Street from Kapiolani Boulevard to Matlock Avenue:  Reconstruction of curbs and gutters, adjustment of utility covers, pruning of trees, curb ramp construction and resurfacing of roadways.

            (Estimated completion date, August 2004)

 

Punchbowl Street Improvements, Phase 2, Punchbowl Street between Ala Moana Boulevard and just beyond King Street:  Modify the traffic signals, streetlights, parking meters, traffic signs, pavement striping, marking and markers to accommodate two-way traffic; reconstruct the curb ramps, sidewalks, curbs, gutters and bus pads; upgrade the sewer and drainage systems; install tree wells, street trees and irrigation system; reconstruct the road pavement and resurface; adjust utility boxes, manholes and street monuments.

            (Estimated completion date, March 2005)

 

Rehabilitation of - Queen Street (Fort Street Mall to Ward Avenue), Laula Way (Elm Street to Rycroft Street), Iolani Avenue (Lusitana Street to Alapai Street), Hookui Street (Auwaiolimu Street to Puowaina Street), Malua Drive (Alewa Drive to Paina Street), Beckley Street (Gulick Avenue to Kalihi Street), and Gulick Avenue (Mauka Ano Lane to School Street):  Reconstruct weakened pavement; cold plane and resurface roadway; adjust utility manholes to grade; and restore vehicle detector loops and pavement striping.

            (Estimated completion date, October 8, 2004)

 

Rehabilitation of St. Louis Drive, Dole Street, Frank Street, Eugene Place, Alphonse Place, Robert Place, Maigret Street:  Installation of water mains, hydrants & service materials.  Reconstruction and resurfacing of roadway and installation of pavement markings.

            (Estimated completion date, February 2005)

 

KAHALUU

Curb Ramps at - Waihee Road (between Ahilama Road & Kamehemeha Highway): Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

KAILUA

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

(Estimated completion date, January 2005)

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Dune Circle: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6 p.m.  During non-work hours, one lane for northbound traffic along Kalaheo Avenue will be re-opened with the other lane closed as an on-site staging are for equipment.

 

Curb Ramps at - Kihapai Place/Kihapai Street, Oneawa Street /Wailepo Street, Aulike Street/Kuulei Road, Maluniu Avenue (between Kuulei Road/ Uluniu Street), Hahani Street (between Hekili Street/Kailua Road, Alala Road/Alala Place, Alala Road/Paumakua Place.  Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

KAIMUKI

Curb Ramps at Maunaloa Avenue/7th Avenue, Maunaloa Avenue/Paahana Avenue: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

KAKAAKO

Curb Ramps at - Mission Lane & Queen Street, Keawe Street & Queen Street, Emily Street & Kawaiahao Street: Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

KALIHI

Republican Street Emergency Sewer Line Replacement Republican Street between Libby Street and Kalihi Street: 1 2 lane closure as necessary.  Work will be from Monday thru Friday, and Saturdays as required.

            (Estimated completion date, October 2004)

 

KANEOHE

Curb Ramps at - Kahuhipa Street/Lolii Street, Kahuhipa Street/Kawa Street, Haiku Road/Heeia Street, Haiku Road/Ohala Street: Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

Curb Ramps at Various Locations, FY 2002(2) Kamehameha Highway/Lilipuna Road: Construct new curb ramps, sidewalks. Install striping, marking and markers.

            (Estimate completion date, August 2004)

 

Rehabilitation of Haiku Road, Heeia Street, Alaloa Street: Reconstruction and resurfacing of roadways, adjustment of utility manholes and installation of permanent pavement markings.

            (Estimated completion date, August 2004)

 

Lulani Street Water Systems Improvements.  Lulani Street, Lulani Place & portions of Kamehameha Highway between Lulani Street to Laenani Drive.  Manhole adjustments and pavement marking restoration.

Estimated completion date, August 2004.

 

MAKAKILO

Curb Ramps at - Panana Street/Ulele Place:  Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

MILILANI

Curb Ramps at Aaahi Street & Aaahi Place, Aaahi Street & Elau Place, Aaahi Street & Kupulau Place, Ahiku Street & Lanikuhana Avenue, Ahiku Street & Ualalehu Street, Kaloapau Street & Kehepue Loop, Kailiula Loop & Kaloapau Street Kipapa Drive & Wehewehe Loop, Kipapa Drive & Nawenewene Circle, Kanamee Street & Noholoholo Street, Kipapa Drive at Mililani Shopping Center, Kipapa Drive at Jack in the Box, Kipapa Drive & Wainihi Street, Wakalani Drive &  Waikalani Place, Ainamakua Drive & Ainamakua Drive, Ainamakua Drive & Meheula Parkway, Ukuwai Street & Makaikai Street, Ainamakua Drive & Meheula Parkway, Ukuwai Street & Makaikai Street, Ainamakua Drive & Makaikai Street, Kaapeha Drive & Meheula Parkway, Koolani Drive & Meheula Parkway:  Construct new curb ramps, pedestrian push button, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

MOANALUA

Rehabilitation of Ala Oli Street, Haloa Drive, Piikea Street, Halupa Street, Hakupapa Street, Epukane Street & Punihi Street.  Reconstruction and resurfacing of roadways, adjustment of utility manholes and installation of permanent pavement markings.

            (Estimated completion date, August 2004)

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:

Upgrade roadway to include 2 additional lanes in each direction, with designated left and right turning lanes. Provide traffic controls, mass grading, temporary security fencing and electrical overhead lines, sidewalks, curbs, gutters, curb ramps and property adjustments, including demolishing and reconstructing new structures and constructing new walls. Install detention basins, drainage, water, sewer, traffic signal, streetlights, underground electrical system, oil lines, gas lines, pavement striping, markings and markers, and traffic signs, irrigation and landscaping.

            (Estimated completion date, August 2004)

 

WAHIAWA

Curb Ramps at - Kahelu Avenue/Wikao Street, Kahelu Avenue/Palii Street, Akamainui Street/Palii Street, Akamainui Street/Wikao Street, California Avenue/Walker Avenue, California Avenue/Mango Street, Mango Place/Mango Street, California Avenue/Makani Avenue, Kilani Street/Palm Street, Kilani Avenue/Koa Street, California Avenue (between Iliwai Drive/Uuku Street):

Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

WAIKELE

Curb Ramps at Various Locations, FY 2002(3) Aoku Street/Lumiauau Street, Alau Street/Lumiauau Street, Pulelo Street/Lumiaina Street, Paiwa Street/Pakela Street: Construct new curb ramps, sidewalk transition and pavement markings.

(Estimated completion date, August 2004)

 

WAIPAHU

Curb Ramps at - Kupuna Loop & Kupuohi Street (both intersections), Kaaholo Street & Kaaoki Place:  Construct new curb ramps, sidewalk transition and pavement markings.

            (Estimated completion date, August 2004)

 

Village Park Connector Road: Construction of a two-way connector road between Kupuna Loop in Village Park and Loaa Street in Waipahu.  Work includes roadway grading, construction of roadways, sidewalks, curb ramps and CRM and CMU walls; and installation of water lines, drain lines, electrical lines, streetlights, irrigation lines and landscaping.

            (Estimated completion date, March 2005)

 

WAIPIO

Reconstruction of Concrete Sidewalks:  Waipio Uka Boulevard, Meahale Street, Leko Place, Mahua Place, Mikilana Place, Akeu Place, Pohu Place, Manino Place, Polinahe Place, Mohalu Street, Pulai Street, Nanilihilihi Street,  Noheaiki Street, Nakili Place, Nuao Place, Noheaiki Way, Mele Street, Koliana Street, Waiolina Street, Pupuhi Street, Puana Street, Palaiki Street, Oli Loop, Kahimoe Street, Ohilau Place, Kepakepa Street, Lauwi Place, Ukee Place, Ukee Street:  reconstruct damaged sidewalks.

(Estimated completion date, January 2005)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

 

August 22, 2004 Sunday
9:00AM Starts
1:00PM Ends

BRUNCH ON THE BEACH STREET FESTIVAL sponsored by the Waikiki Improvement Assn./C&C Honolulu.  The event is expected to have 5,000+ participants.  Traffic will be diverted starting 3:30 am for setup. The event will close Kalakaua Avenue, all lanes from Kaiulani Avenue to Liliuokalani Avenue. Contact: DTS-TST Div. 527-6009

 

August 28, 2004 Saturday
7:00AM Starts
9:00AM Ends

MEMORY WALK/5K RUN sponsored by Alzheimer's Association, Aloha Chapter. The event is expected to have 1,000 participants. It will start at Fisherman's Wharf, near Ward Ave., to Ala Moana Blvd., to Kkhd entrance to Ala Moana Park, circle Magic Island, exit park at Ewa entrance and end at start area. Contact: Janet Bender Eli 591-2771

 

The above is based on the most current information available from the event organizers as of date on bottom.  TST Division, Department of Transportation Services  Phone: 808-527-6009 Fax: 808-523-4446 Email:  ikodani@co.honolulu.hi.us

- 30 -