ROAD WORK WEEKLY REPORT

 

Scheduled roadwork for the week beginning November 14, 2004, for the Department of Design & Construction. Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AHUIMANU

Rehabilitation of Ahuimanu Place (Kahekili Highway to Ahuimanu Road) and Hui Ulili Street (Ahuimanu Place to Hui Iwa Street): Reconstruction and resurfacing of roadways, adjustment of utility manholes and installation of permament pavement markings.

            (Estimated completion date, November 2004)

 

AIEA

Curb Ramps at Heleconia Place and Moanalua Road: construct new curb ramps and sidewalks.  Install pavement striping and markings.  Adjust utility boxes to new grade.  Upgrade the traffic signal system.

            (Estimated completion date, February 2005)

 

AINA HAINA

Curb Ramps at West Hind Drive/Apo Drive/Nohu Street: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

HAWAII KAI

Curb Ramps at Lanipuao Street/Kaumakani Street, Kekupua Street/Kaumakani Street.  Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

HONOLULU

Curb Ramps at Adams Lane/Bishop Street, Chaplain Lane/Nuuanu Avenue, Fort Street/S. Kukui Street, Queen Emma Square/Queen Emma Street/S. Kukui Street: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

Curb Ramps at Akoko Street/Cedar Street/South King Street, Artesian Street/South Beretania Street, Artesian Street/South King Street, South King Street/Elsie Lane, South Beretania Street/Farrington Street, Hauoli Street/South King Street, Hoawa Lane/South King Street, Kaheka Street/Rycroff Street, Makiki Street/South Beretania Street, Pawaa Lane/South Beretania Street, Poha Lane/South King Street, South King Street/Elsie Lane/Punahou Street: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

Ala Wai Boulevard Improvements:  Construct bulbouts and landscaping.

            (Estimated completion date, November 2004)

 

Curb Ramps at Ala Wai Boulevard and Pau Street, Ala Wai Boulevard and Kaiolu Street, Kaiulani Avenue and Prince Edward Street:  Construct new curb ramps, sidewalks, and AC transitions.  Install pedestrian push buttons, striping, marking, and markers.

            (Estimated completion date, January 2005)

 

Guardrail Improvements at Alewa Drive at Aulii Street:  Install new guardrails.

            (Estimated completion date, November 2004)

 

Seismic Retrofit of Dillingham Boulevard Bridge over Kapalama Canal:  Install shear keys and carbon composite laminate on the abutments and pile caps.

            (Estimated completion day, December 2004)

 

Curb Ramps at - Mililani Street and Merchant Street, Kinau Street and Lunalilo Street.  Construct new curb ramps, sidewalks, and AC transitions.  Relocate existing signs and posts.  Install loops, striping, marking and markers.

            (Estimated completion date, January 2005)

 

Emergency Resurfacing of Kapiolani Boulevard from Kalakaua Avenue to Date Street:  Installation of permanent pavement marking to be performed at night Monday thru Friday, 7 pm to 5am.  Adjustment of utility manholes and installation of traffic loop sensors, Monday thru Friday 9 am to 3 pm.

            (Estimated completion date, November 2004)

 

Kapiolani Boulevard Sewer Emergency Repair:  Sewer work from Atkinson Drive to Pensacola Avenue on Kapiolani Blvd.

(Estimated completion date, November 2004)

 

Wheelchair Ramps at Keeaumoku Street and Nehoa Street, Aala Street and Aala Place, River Street and Pauahi Street:  Construct new curb ramps, sidewalks, AC transitions and traffic signal work.  Install striping and markers.

            (Estimated completion date, December 2004)

 

King Street Improvements, Phase 3 - North King Street between Liliha Street and Desha Lane and Austin Lane and Morris Lane:  Construction of concrete driveways, sidewalks, curb ramps, planting of trees; construction of street lighting system;

            (Estimated completion date, February 2005)

 

Maunakea Street Sidewalk Improvements: Reconstruct curb, gutter, and sidewalk on Maunakea Street between Beretania Street and King Street. Work includes installation of new granite tile surface sidewalks, signs, utility boxes, and roadway resurfacing.

            (Estimated completion date, November 2004)

 

Rehabilitation of Piikoi Street from Kapiolani Boulevard to Matlock Avenue:  Reconstruction of curbs and gutters, adjustment of utility covers, pruning of trees, curb ramp construction and resurfacing of roadways.

            (Estimated completion date, December 2004)

 

Punchbowl Street Improvements, Phase 2, Punchbowl Street between Ala Moana Boulevard and just beyond King Street:  Modify the traffic signals, streetlights, parking meters, traffic signs, pavement striping, marking and markers to accommodate two-way traffic; reconstruct the curb ramps, sidewalks, curbs, gutters and bus pads; upgrade the sewer and drainage systems; install tree wells, street trees and irrigation system; reconstruct the road pavement and resurface; adjust utility boxes, manholes and street monuments.

            (Estimated completion date, March 2005)

 

Rehabilitation of - Queen Street (Fort Street Mall to Ward Avenue), Laula Way (Elm Street to Rycroft Street), Iolani Avenue (Lusitana Street to Alapai Street), Hookui Street (Auwaiolimu Street to Puowaina Street), Malua Drive (Alewa Drive to Paina Street), Beckley Street (Gulick Avenue to Kalihi Street), and Gulick Avenue (Mauka Ano Lane to School Street):  Reconstruct weakened pavement; cold plane and resurface roadway; adjust utility manholes to grade; and restore vehicle detector loops and pavement striping.

            (Estimated completion date, December 2004)

 

Rehabilitation of St. Louis Drive, Dole Street, Frank Street, Eugene Place, Alphonse Place, Robert Place, Maigret Street:  Installation of water mains, hydrants & service materials.  Reconstruction and resurfacing of roadway and installation of pavement markings.

            (Estimated completion date, February 2005)

 

KAILUA

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

(Estimated completion date, January 2005)

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Dune Circle: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6:00 p.m.  During non-work hours, one lane for northbound traffic along Kalaheo Avenue will be re-opened with the other lane closed as an on-site staging are for equipment.

 

Wheelchair Ramps at - Keolu Drive and Akamai Street, Keolu Drive and Akalani Loop, Keolu Drive and Akahai Street and Akalani Loop, Keolu Drive and Punana Loop and Manulani Street, Keolu Drive and Punana Loop.  Construct new curb ramps, sidewalks, ac transitions and traffic signal work.  Install striping and markers.

            (Estimated completion date, December 2004)

 

Guardrail Improvements at Maunawili Road:  Install new guardrails.

            (Estimated completion date, November 2004)

 

Rehabilitation of Streets Mokapu Boulevard, Kaneohe Bay Drive to the Entrance to Kaneohe Marine Base Hawaii.  Reconstruction and resurfacing of roadways, adjustment of utility manholes and installation of permanent pavement markings.

            (Estimated completion date, October 2004)

 

KAIMUKI

Curb Ramps at Maunaloa Avenue/7th Avenue, Maunaloa Avenue/Paahana Avenue: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, November 2004)

 

Curb Ramps at Kapahulu Avenue and Kihei Place, 10th Avenue and Keanu Street, 10th Avenue and Kaau Street, and Palolo Avenue and Kiwila Street:  Construct new curb ramps, sidewalks thru gutter, and AC transitions.  Relocate existing signs on new post.  Install pedestrian push buttons, pullboxes and loops, sriping, marking and markers.

            (Estimated completion date, January 2005)

 

KAKAAKO

Curb Ramps at - King Street and Pensacola Street, Alder Street and Kamaile Street, Alder Street and Rycroft Street, Alder Street and Elm Street, Amana Street and Kanunu Street, Amana Street and Makaloa Street, Kaheka Street and Liona Street, Kanunu Street and Poni Street, Makaloa Street and Poni Street, Dominis Street and Punahou Street, and Griffiths Street and South Beretania Street:  Construct new curb ramps, sidewalks, and AC transitions.  Relocate existing signs and posts.  Relocate street light pullbox.  Install pedestrian push buttons, striping, marking and markers.

            (Estimated completion date, January 2005)

 

KALIHI

Curb Ramps at Democrat Street and Mokauea Street, and Kalani Street and Waiakamilo Road:  Construct new curb ramps and sidewalks.  Install pavement striping and markings.  Upgrade the traffic signal system.  Adjust utility boxes to new grade.  Relocate existing signs and posts.

            (Estimated completion date, February 2005)

 

KANEOHE

Kamehameha Highway Reconstructed Sewer-Kamehameha Highway (fronting Windward Mall), Mehana Street and Kawa Street.  Rehabilitation of 27-inch sewer lines.

            (Estimated completion date, November 2004)

 

Rehabilitation of Haiku Road, Heeia Street, Alaloa Street: Reconstruction and resurfacing of roadways, adjustment of utility manholes and installation of permanent pavement markings.

            (Estimated completion date, November 2004)

 

Seismic Retrofit of Kamehameha Highway Bridge over Keaahala Stream:  Install steel shear keys on the abutments.

            (Estimated completion date, November 2004)

 

MAPUNAPUNA

Curb Ramps at Mapunapuna Street and Pukoloa Street:  Construct new curb ramps and sidewalks.  Install pavement striping and markings.  Adjust utility boxes to new grade.  Upgrade the traffic signal system.

            (Estimated completion date, February 2005)

 

MOANALUA

Rehabilitation of Streets & Moanalua Water System Improvements:  Ala Aolani Place and portions of Ala Aolani Street, Ala Lani Street and Place, Ala Kiao Place, Ala Iolani Street and Place, Kapulei Street:  Installation of 4 and 8 water mains, reconstruction and resurfacing of roadways, adjustment of utility manholes, installation of pavement markings.

            (Estimated completion date, November 2005)

 

PEARL CITY

Repaving - Hoomoana Street, Noelani Street, Kaweloka Street, Waihona Street and Place, Hoomoana Street from Kalauipo to Hookiekie Street, and Kaweloka Street from Noelani to Kuahaka Street.

            (Estimated completion date, November 2004)

 

Repaving - Noelani Street from Paaaina to Kaahumanu Street, and Waihona Street and Place from Kamehameha Hwy to the End.

            (Estimated completion date, December 2004)

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:  Upgrade roadway to include 2 additional lanes in each direction, with designated left and right turning lanes. Provide traffic controls, mass grading, temporary security fencing and electrical overhead lines, sidewalks, curbs, gutters, curb ramps and property adjustments, including demolishing and reconstructing new structures and constructing new walls. Install detention basins, drainage, water, sewer, traffic signal, streetlights, underground electrical system, oil lines, gas lines, pavement striping, markings and markers, and traffic signs, irrigation and landscaping.

            (Estimated completion date, December 2004)

 

Curb Ramps at Kalaloa Street and Salt Lake Boulevard, Lawehana Street and Malaai Street:  Construct new curb ramps and sidewalks.  Install pavement striping and markings.  Upgrade the traffic signal system.  Adjust utility boxes to new grade.

            (Estimated completion date, February 2005)

 

Repaving - Likini Street from Pakini St. to Ala Lilikoi and Wanaka St. to end, Keaka Drive from Puolo Dr. to Ukana St., Ala Ilima St. from Ala Lilikoi to Ala Lilikoi, and Ala Puumalu from Ala Napunani to Honolulu Country Club Entrance.

            (Estimated completion date, November 2004)

 

WAIMANALO

Rehabilitation of - Kumuhau Street, Kalanianaole Highway to Waikupanaha Street; Mahailua Street, Kumuhau Street to Kakaina Street; Kakaina Street, Mahailua Street to Mekia Street; Nakini Street, Nalu Street to Poliala Street.  Reconstruction and resurfacing of roadways, adjustment of utility manholes and installation of permanent pavement markings.

            (Estimated completion date, February 2005)

 

WAIPAHU

Village Park Connector Road: Construction of a two-way connector road between Kupuna Loop in Village Park and Loaa Street in Waipahu.  Work includes roadway grading, construction of roadways, sidewalks, curb ramps and CRM and CMU walls; and installation of water lines, drain lines, electrical lines, streetlights, irrigation lines and landscaping.

            (Estimated completion date, March 2005)

 

Seismic Retrofit of Waipahu Street Bridge over Wailani Stream:  Install concrete shear keys on the abutments.

            (Estimated completion date, October 2004)

 

WAIPIO

Reconstruction of Concrete Sidewalks:  Waipio Uka Boulevard, Meahale Street, Leko Place, Mahua Place, Mikilana Place, Akeu Place, Pohu Place, Manino Place, Polinahe Place, Mohalu Street, Pulai Street, Nanilihilihi Street,  Noheaiki Street, Nakili Place, Nuao Place, Noheaiki Way, Mele Street, Koliana Street, Waiolina Street, Pupuhi Street, Puana Street, Palaiki Street, Oli Loop, Kahimoe Street, Ohilau Place, Kepakepa Street, Lauwi Place, Ukee Place, Ukee Street:  reconstruct damaged sidewalks.

(Estimated completion date, January 2005)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

November 14, 2004 Sunday
7:00AM Starts
9:00AM Ends

FRIENDS OF KAILUA HS FUN RUN/WALK sponsored by Friends of Kailua H.S. The event is expected to have 300 runners. It will start at Kailua High School, to Akiohala St., to Keolu Dr., to Akake Pl., return via same route to finish at Kailua High.  Contact: Ed Kemper 524-0330  Fax: 523-1406

 

November 18, 2004 Thursday
6:00PM Starts
10:00PM Ends

UH BASKETBALL SLAM DUNK BLOCK PARTY sponsored by Murphy's Bar & Grill. The event is expected to have 1,000+ participants.  Traffic will be diverted starting 3:30 pm for setup. The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St. Contact Don Murphy 531-0422

 

November 20, 2004 Saturday
2:00PM Starts
6:00PM Ends

UH TAILGATE SERIES BLOCK PARTY #5 sponsored by Murphy's Bar & Grill. The event is expected to have 1,000+ participants.  Traffic will be diverted starting 1 pm for setup. The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St. Contact Don Murphy 531-0422

 

The above is based on the most current information available from the event organizers as of date on bottom.  TST Division, Department of Transportation Services  Phone: 808-527-6009 Fax: 808-523-4446 Email:  ikodani@co.honolulu.hi.us

 

 

- 30 -