ROAD WORK WEEKLY REPORT

 

Scheduled roadwork for the week beginning February 27, 2005, for the Department of Design & Construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch). Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AINA HAINA

Curb Ramps at West Hind Drive/Apo Drive/Nohu Street: Install pavement markings.

            (Estimated completion date, March 2005)

 

EWA

Ewa Villages, Extension of Kapolei Parkway, Phase 8A - Renton Road at future extension of Kapolei Parkway:  Construct new intersection including sewer, drainage, sidewalk, curb ramps, street lights, and landscape work.

            (Estimated completion date, December 2005)

 

HAWAII KAI

Curb Ramps at Kawaihae Street and Milolii Place:  Construct new curb ramps, sidewalks, and AC transitions.  Install striping, markings and markers.

            (Estimated completion date, March 2005)

 

Curb Ramps at Lanipuao Street/Kaumakani Street, Kekupua Street/Kaumakani Street.  Install pavement markings.

            (Estimated completion date, March 2005)

 

HONOLULU

Curb Ramps at Adams Lane/Bishop Street, Chaplain Lane/Nuuanu Avenue, Fort Street/S. Kukui Street, Queen Emma Square/Queen Emma Street/S. Kukui Street: Install pavement markings.

            (Estimated completion date, March 2005)

 

Miscellaneous Guardrail Improvements at Alewa Drive at Aulii Street: Install new guardrails.

            (Estimated completion date, March 2005)

 

Curb Ramps at Akoko Street/Cedar Street/South King Street, Artesian Street/South Beretania Street, Artesian Street/South King Street, South King Street/Elsie Lane, South Beretania Street/Farrington Street, Hauoli Street/South King Street, Hoawa Lane/South King Street, Kaheka Street/Rycroff Street, Makiki Street/South Beretania Street, Pawaa Lane/South Beretania Street, Poha Lane/South King Street, South King Street/Elsie Lane/Punahou Street:  Install pavement markings.

            (Estimated completion date, March 2005)

 

Curb Ramps at Ala Wai Boulevard and Pau Street, Ala Wai Boulevard and Kaiolu Street, and Beachwalk Street and Kalia Road:  Construct new curb ramps, sidewalks, and AC transitions.  Install pedestrian push buttons, striping, marking, and markers.

            (Estimated completion date, March 2005)

 

Ala Wai Boulevard Improvements:  Landscape maintenance work.

            (Estimated completion date, March 2005)

 

Kapiolani Boulevard Sewer Emergency Repair:  Sewer work from Atkinson Drive to Pensacola Avenue on Kapiolani Blvd.

(Estimated completion date, March 2005)

 

Wheelchair Ramps at Keeaumoku Street and Nehoa Street, and Aala Street and Aala Place:  Construct new curb ramps, sidewalks, AC transitions and traffic signal work.  Install striping and markers.

            (Estimated completion date, March 2005)

 

King Street Improvements, Phase 3 - North King Street between Liliha Street and Desha Lane and Austin Lane and Morris Lane:  Construction of concrete driveways, sidewalks, curb ramps, planting of trees; construction of street lighting system;

            (Estimated completion date, March 2005)

 

Bridge Replacement at La’i Road Bridges Nos. 379 &380.  Remove existing wooden bridges and replace with new concrete bridges.

            (Estimated completion date, June 6, 2005)

 

Curb Ramps at North School Street and Stillman Lane, Iwilei Road, Kuwili Street and Pine Street, Merchant Street and Nuuanu Avenue, Mililani Street and Merchant Street, Kinau Street and Lunalilo Street:  Construct new curb ramps, sidewalks, and AC transitions.  Relocate existing signs and posts.  Install loops, striping, marking and markers.

            (Estimated completion date, March 2005)

 

Punchbowl Street Improvements, Phase 2, Punchbowl Street between Ala Moana Boulevard and just beyond King Street:  Modify the traffic signals, streetlights, parking meters, traffic signs, pavement striping, marking and markers to accommodate two-way traffic; reconstruct the curb ramps, sidewalks, curbs, gutters and bus pads; upgrade the sewer and drainage systems; install tree wells, street trees and irrigation system; reconstruct the road pavement and resurface; adjust utility boxes, manholes and street monuments.

            (Estimated completion date, March 2005)

 

Rehabilitation of St. Louis Drive, Dole Street, Frank Street, Eugene Place, Alphonse Place, Robert Place, Maigret Street:  Installation of water mains, hydrants & service materials.  Reconstruction and resurfacing of roadway and installation of pavement markings.

            (Estimated completion date, April 2005)

 

KAILUA

Kailua Road Underground Ducts – Kailua Road between Kuulei Road and Kaikua District Park.  Cold milling and resurfacing of roadway, pavement markings & utility manhole adjustment.

            (Estimated completion date, March 2005)

 

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

(Estimated completion date, March 2005)

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Dune Circle: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6:00 p.m.  During non-work hours, one lane for northbound traffic along Kalaheo Avenue will be re-opened with the other lane closed as an on-site staging area for equipment.

 

Wheelchair Ramps at - Keolu Drive and Akamai Street, Keolu Drive and Akalani Loop, Keolu Drive and Akahai Street and Akalani Loop:  Construct new curb ramps, sidewalks, ac transitions and traffic signal work.  Install striping and markers.

            (Estimated completion date, March 2005)

 

Guardrail Improvements at Maunawili Road:  Install new guardrails.

            (Estimated completion date, March 2005)

 

Rehabilitation of Mokapu Boulevard, Kaneohe Bay Drive to the Entrance to Kaneohe Marine Base Hawaii; Hele Street, Keolu Drive to Kina Street: Installation of permanent pavement markings and restoration of traffic loop sensors.

            (Estimated completion date, March 2005)

 

KAIMUKI

Curb Ramps at Maunaloa Avenue/7th Avenue, Maunaloa Avenue/Paahana Avenue: Demolish and remove existing pavements, curbs, gutters, sidewalks and other incidentals to install new work per plan.

            (Estimated completion date, March 2005)

 

Curb Ramps at 5th Avenue and H-1 Freeway and Harding Avenue:  Construct new curb ramps, sidewalks thru gutter, and AC transitions.  Relocate existing signs on new post.  Install pedestrian push buttons, pullboxes and loops, sriping, marking and markers.

            (Estimated completion date, March 2005)

 

KAKAAKO

Curb Ramps at Kanunu Street and Poni Street, Makaloa Street and Poni Street, Griffiths Street and South Beretania Street:  Construct new curb ramps, sidewalks, and AC transitions.  Relocate existing signs and posts.  Relocate street light pullbox.  Install pedestrian push buttons, striping, marking and markers.

            (Estimated completion date, March 2005)

 

KALIHI

Curb Ramps at Kalani Street and Waiakamilo Road:  Construct new curb ramps and sidewalks.  Install pavement striping and markings.  Upgrade the traffic signal system.  Adjust utility boxes to new grade.  Relocate existing signs and posts.

            (Estimated completion date, March 2005)

 

MOANALUA

Rehabilitation of Streets & Moanalua Water System Improvements:  Ala Aolani Place and portions of Ala Aolani Street, Ala Lani Street and Place, Ala Kiao Place, Ala Iolani Street and Place, Kapulei Street:  Installation of 4” and 8” water mains, reconstruction and resurfacing of roadways, adjustment of utility manholes, installation of pavement markings.

            (Estimated completion date, November 2005)

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:  Upgrade roadway to include 2 additional lanes in each direction, with designated left and right turning lanes. Provide traffic controls, mass grading, temporary security fencing and electrical overhead lines, sidewalks, curbs, gutters, curb ramps and property adjustments, including demolishing and reconstructing new structures and constructing new walls. Install detention basins, drainage, water, sewer, traffic signal, streetlights, underground electrical system, oil lines, gas lines, pavement striping, markings and markers, and traffic signs, irrigation and landscaping.

            (Estimated completion date, March 2005)

 

WAIMANALO

Rehabilitation of Kumuhau Street, Kalanianaole Highway to Waikupanaha Street; Mahailua Street, Kumuhau Street to Kaikaina Street, Mahailua Street to Mekia Street, Nakini Street, Nalu Street to Poliala Street:Adjustment of utility manholes and installation of permanent pavement markings.

            (Estimated completion date, March 2005)

 

WAIPAHU

Village Park Connector Road: Construction of a two-way connector road between Kupuna Loop in Village Park and Loaa Street in Waipahu.  Work includes roadway grading, construction of roadways, sidewalks, curb ramps and CRM and CMU walls; and installation of water lines, drain lines, electrical lines, streetlights, irrigation lines and landscaping.

            (Estimated completion date, March 2005)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

 

NO EVENTS SCHEDULED

 

The above is based on the most current information available from the event organizers as of date on bottom.  TST Division, Department of Transportation Services  Phone: 808-527-6009 Fax: 808-523-4446 Email:  ikodani@co.honolulu.hi.us

 

-        30 -

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 523-4882, Wastewater Management Division, Construction Management - 527-5879.