ROAD WORK WEEKLY REPORT

 

Scheduled roadwork for the week beginning November 27, 2005, for the Department of Design & construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch).  Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

EWA

Ewa Villages, Extension of Kapolei Parkway, Phase 8A - Renton Road at future extension of Kapolei Parkway:  Construct new intersection including sewer, drainage, sidewalk, curb ramps, street lights, and landscape work.

            (Estimated completion date, December 2005)

 

HALEIWA

Bridge Rehabilitation at Anahulu Stream:  Remove deteriorated concrete and reinforcement, reconstruct and repair areas, modify existing railings and paint structure.

            (Estimated completion date, December 2005)

 

HONOLULU

Rehabilitation of Harding Avenue from 1st Avenue to Luawai Street, 6th Avenue from Harding Avenue to Palolo Avenue, Leahi Avenue from Kapahulu Avenue to Noela Street, 5th Avenue from Harding Avenue to Dead End:  The work primarily consists of reconstruction, milling and resurfacing the roadways.  Also, included is the reconstruction of some concrete curbs, gutters, driveways, aprons, sidewalks, and some new drainage improvements.  Installation of pavements, markings, traffic sensors and adjustment of utility covers to grade will complete the project.

            (Estimated completion date, May 2006)

 

Kalaiopua Place Improvements:  Relocate utility poles, reconstruct roadway, install guardrail and resurface roadway.

            (Estimated completion date, December 2005)

 

King Street Improvements, Phase 3 - North King Street between Liliha Street and Desha Lane and Austin Lane and Morris Lane:  Construction of concrete driveways, sidewalks, curb ramps, planting of trees; construction of street lighting system.  Pending revised scope of work.  Trees to be deleted.

            (Estimated completion date, November 2005)

 

Guardrail improvements at Lai Road:  Install new metal guardrail and object marks.            (Estimated completion date, December 2005)

 

Curb Ramps at Liliha Street/Kuakini Street, Liliha Street/Kunawai Lane/Elena Street, Liliha Street/Borges Lane/Dayton Lane, Liliha Street/Bates Street, Nuuanu Avenue between Judd Street and Robinson Lane and Wyllie Street, Pacific Heights Road/Pauoa Road:  Construct new curb ramps, sidewalks, AC transitions and driveways.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, December 2005)

 

Rehabilitation of Various Streets, Palolo Valley--Orchid Street, Palolo Avenue to Jasmine Street, Ginger Street; Gardenia Street, Ginger St to Carlos Long; Myrthle Street, Carlos Long to End; Narcissus Street and Place:  Remedial work.

            (Estimated completion date, October 2005)

 

Rehabilitation of Streets St. Louis Drive, Dole Street, Frank Street, Eugene Place, Alphonse Place, and Robert Place:  Reconstruct concrete driveway, installation of signs and complete punchlist.

            (Estimated completion date, December 2005)

 

KAHALUU

Miscellaneous Guardrail Improvements Lihikai Drive and Lanani Drive:  Install new metal guardrail and object marks.

            (Estimated completion date, December 2005)

 

KAILUA

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Kuulei Road: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6:00 p.m.

 

KAIMUKI

Reconstruction of Concrete Sidewalks in Kaimuki area - Harding Avenue, Pahoa Avenue, Kaimuki Avenue, Maunaloa Avenue, Kilauea Avenue, Maunalei Avenue, Lua Wai Place, Keanu Street, Pilialo Street, Ocean View Drive, Sunset Avenue, Pokole Street, 6th to 16th Avenue and 22nd Avenue:

Demolish and reconstruct existing sidewalks, driveway aprons, curbs and gutters.

            (Estimated completion date, November 2005)

 

KALIHI

Curb Ramps at Mokauea Street/Auiki Street, Mokauea Street/Hart Street, Mokauea Street/Kalani Street, Mokauea Street/Hau Street, Mokauea Street/Colburn Street, Dillingham Boulevard between Kalihi/McNeil Street, and Dillingham Boulevard between Alakawa/Kokea Street:  Construct new curb ramps and sidewalks.  Install pavement striping and markings.

            (Estimated completion date, December 2005)

 

MAKAKILO

Curb Ramps at Various Locations, FY 2002(5) Panama Street/Hame Street/Welo Street: Construct new curb ramps and AC transitions.

            (Estimated completion date, January 2006)

 

MILILANI

Reconstruction of Concrete Sidewalks, Mililani Area - Lanikuhana Avenue, Poiki Street., Poiki Place., Awiki Street., Opo Place, Kaukoe Street, Paionia Place, Keaolani Street, Awiwi Place, Kikalake Place, Kamaio Street, Aaahi Street, Meheula Parkway, Mahapili Street, Kauakapuu Loop, Hakianalia Place, Holanialii Street, Apele Street, Kikiula Loop, Mahinahou Street, Kamalei Street,  Waileia Place, Nui Street, Kealakaa Street, Ihuhanu Place, Kealohi Street, Makapipipi Street, Keehuiwa Street., Makohilani Street, Ukalalii Place, Puaahi Place, Hokulili Street:  Removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the areas; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

(Estimated Completion Date, November 2005)

 

Curb Ramps at Hokuiwa Street/Kawau Street, Kaloapau Street/Kehepue Loop, Alapoai Street/Alapoai Place, Hokuala Street/Hokuili Street, Anania Drive/Puanane Loop, Anania Drive/Hakamoa Street, Anania Drive/Kiaha Loop, Anania Drive/Kaukalia Street, Anania Drive/Lanikuhana Ave, Anania Drive/Hokualii Street, Anania Drive/Kapuahi Street, Waihonu Street/Waimakua Drive, Waiehu Place/Waimakua Drive, Kipapa Drive/Moenamanu Street, Hookelewaa Street/Kipapa Drive:  Construct new curb ramps, sidewalks, AC transitions and driveways.  Install striping, marking and markers.

            (Estimated completion date, January 2006)

 

MOANALUA

Rehabilitation of Streets & Moanalua Water System Improvements:  Ala Aolani Place and portions of Ala Aolani Street, Ala Lani Street and Place, Ala Kiao Place, Ala Iolani Street and Place, Kapulei Street:  Install under drain, reconstruction and resurfacing of roadways, adjustment of utility manholes, installation of pavement markings.

            (Estimated completion date, November 2005)

 

NORTH SHORE

Curb Ramps at Various Locations, FY2002 (5) Akule Street/Aweoweo Street, Au Street/Aweoweo Street, Au Street/Apuhihi Street, Akule Street/Apuhihi Street:  Construct new curb ramps, sidewalks, AC transitions.  Install striping, marking and markers.

            (Estimated completion date, December 2005)

 

PEARL CITY

Rehabilitation of Waimano Home Road from Kamehameha Highway to Komo Mai Drive:  Install curb ramps and traffic signals relocation.  Reconstruct failed pavement areas and resurface roadways.  Install vehicle loop sensors, and pavement markings and adjust utilities to grade.

            (Estimated completion date, June 2006)

 

PORTLOCK

Reconstruction of Concrete Sidewalks, Portlock Area:  Poipu Drive, Nawiliwili Street, Makaweli Street, Lawai Street, Lumahai Street, Lumahai Place, Hanapepe Loop, Hanapepe Place, Polihale Place, Kalalau Street, Waialae Avenue, Anahola Street.  Removal and reconstruction of damaged concrete sidewalk, curb, and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the areas; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

            (Estimated Completion Date, February 2006).

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:  Final inspection punch list and change order work.

            (Estimated completion date, November 2005)

 

Guardrail improvements at Salt Lake Boulevard:  Install new metal guardrail and object marks. (Estimated completion date, December 2005)

 

WAHIAWA

Curb Ramps at California Avenue/Kaalalo Place, Kilani Avenue/Mango Street, Kilani Avenue/Westervelt Street, Kilani Avenue/Lehua Street, California Avenue/Lehua Street/Muliwai Avenue, California Avenue/North Cane Street, Kilani Avenue/North Cane Street, California Avenue/Uuku Street:  Construct new curb ramps, sidewalks, AC transitions and driveways.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, December 2005)

 

WAIALUA

Rehabilitation of Waialua Beach Road:  Reconstruct bridge joint.

            (Estimated completion date, December 2005)

 

Curb Ramps at Kupahu Street/Nahoa Street:  Construct new curb ramps.  Install striping and markers.

            (Estimated completion date, December 2005)

 

WAIKIKI

Reconstruction of concrete sidewalks - Ala Wai Boulevard, Ainakea Way, Wai Nana Way, Hobron Lane, Lipeepee Street, Ena Road, Kaioo Drive, Paokalani Avenue, Kaneloa Road, Saratoga Road, Beach Walk, Lewers Street, Aloha Drive, Royal Hawaiian Avenue, Seaside Avenue, Nohonani Street, Walina Street, Kanekapolei Street, Kaiulani Avenue, Uluniu Avenue, Prince Edward Street, Koa Avenue, McCully Street, Liliuokalani Avenue, Kealohilani Avenue, Ohua Avenue, Kapili Street, Cleghorn Street, Kapuni Street, Kaiolu Street, Launiu Street, Kalaimoku Street, Olohana Street, Namahana Street, Kuamoo Street, Keoniana Street, Niu Street, and Helumoa Street:  Demolish and reconstruct existing sidewalks, driveway aprons, curbs and gutters.

            (Estimated completion date, November 2005)

 

Curb Ramps at Ala Wai Boulevard/Ohua Street, Ala Wai Boulevard/Walina Street, Ala Wai Boulevard/Nahua Street, Ala Wai Boulevard/Nohonani Street:  Construct new curb ramps and sidewalks.  Install pedestrian push bottons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, December 2005)

 

WAIMALU

Curb Ramps at Kamahao Pl./Kamahao St., Kaahumanu St./Oihana Pl./Kuahao Pl., Kaahele St./Moanalua Rd., Kilinoe St./Kaahele St., Kaahele St./Lulu St., Kaonohi St. at Moanalua Rd., Koauke St./Moanalua Rd./Pali Momi St., and Iho Pl./Palula Wy.:  Construct new curb ramps, sidewalks, AC transitions and driveways.  Install pedestrian push buttons, pull boxes, vehicle loop detectors, striping, marking and markers.

            (Estimated completion date, January 2006)

 

WAIPAHU

Village Park Connector Road: Construction of a two-way connector road between Kupuna Loop in Village Park and Loaa Street in Waipahu.  Work includes roadway grading, construction of roadways, sidewalks, curb ramps and CRM and CMU walls; and installation of water lines, drain lines, electrical lines, streetlights, irrigation lines and landscaping.

            (Estimated completion date, December 2005)

 

Curb Ramps at Waipahu Street/Hene Street, Waipahu Street/Leowahine Street, Waipahu Street/Amokii Street, Waipahu Street/Ikepono Pl., Leokane Street/Leoleo Street, Pupuole Street/Pupuole Pl., Waipahu Street/Waipahu Depot Street,, Waipahu Street/Paiwa Street, and Waipahu between Mokuloa Street and Paiwa Street, Waipahu Street,/Ana Lane/Mahoe Street:  Construct new curb ramps, sidewalks, AC transitions and driveways.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, December 2005)

 

Kahuanani Street Sewer Replacement/Rehabilitation: Installation of a new sewer line and CIPP installation along Kahuanani Street.

            (Estimated completion date, March 2006)

 

WAIPIO

Curb Ramps at Various Locations, FY2002(5) Ka Uka Boulevard/Ukee Street, Ka Uka Boulevard/Waipio Uka Street/Pauhi Street:  Construct new curb ramps, sidewalks, AC transitions and driveways.  Install striping, marking and markers.

            (Estimated completion date, January 2006)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

 

November 27, 2005 Sunday
10:00AM Starts
11:30AM Ends

MARTIN WAREHOUSING TOYS FOR TOTS CARAVAN sponsored by Martin Warehousing & Distribution. The event is expected to have 200 vehicles.  It will start at Magic Island Parking Lot, to Ala Moana Park Dr., to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave.,  end at Paki/Monsarrat Lot. Contact: Jeff Cadavona  696-4589 

 

December 1, 2005 Thursday to January 3, 2006 Tuesday
various times, 
7 days a week

ANNUAL CHRISTMAS SEASON PARKING BAN by the City and County of Honolulu. No Parking Tow Away Zones: 
Honolulu area
- 6 am to 10:30 pm, 1)Kapiolani Boulevard, makai side, South St. to Atkinson Dr., 2)Keeaumoku Street, both sides, Liona St. to Makaloa St., 3)Kaheka Street, ewa side, Makaloa St. to 800 Kaheka
Pearl City area - 9 am to 9 pm, 1)Puu Kula Street, inner curb, # 808 to 926 Puu Kula Dr., 2)Hoolaulea Street, makai side, Waimano Home Rd., to Hoomalu St.,  Contact: DTS Street Usage 523-4022

 

December 1, 2005 Thursday
6:00PM Starts
8:00PM Ends

KAIMUKI XMAS PARADE sponsored by Kaimuki Business & Professional Association. The event is expected to have 1,000 marchers, 30 vehicles, & 5 bands.  It will start at St. Louis HS grounds, to Waialae Ave., to Koko Head Ave., to end at Municipal Parking Lot.  Contact:  Jeff Niebling KBPA 732-7788, Fax:  732-7780

 

December 2, 2005 Friday
6:30PM Starts
8:00PM Ends

WAHIAWA XMAS PARADE sponsored by Wahiawa Community & Buisness Association. The event is expected to have 300 marchers, 10 vehicles, 2 floats, & 2 bands.  It will start at Kaala Elementary School, to California Ave., to North Cane St., end at Center St., Contact: Elizabeth Smithe  621-7097

 

December 3, 2005 Saturday
7:00AM Starts
10:00AM Ends

KALAELOA SPRINT TRIATHLON sponsored by Poayle Sports, LLc. The event is expected to have 300 participants.  Swim: Nimitz Beach Park out and back course ending on beach near transition area.  Bike: Nimitz Beach, to Coral Sea Rd., to Vinson Rd., to Philippine Sea, to Roosevelt Ave., to Essex Rd., to Coral Sea Rd.  Run: Nimitz Beach to Coral Sea Rd., to Tripoli, turnaround and finish at Nimitz Beach.  Contact Steven Foster 864-0113

 

December 3, 2005 Saturday
2:00PM Starts
6:00PM Ends

UH TAILGATE SERIES BLOCK PARTY #7 sponsored by Murphy's Bar & Grill. The event is expected to have 1,000+ participants.  Traffic will be diverted starting 1 pm for setup. The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St. Contact Don Murphy 531-0422

 

December 3, 2005 Saturday
9:00AM Starts
10:30AM Ends

KANEOHE XMAS PARADE sponsored by Kaneohe Christmas Parade Committee.The event is expected to have 1,500 marchers, 30 vehicles, 20 floats, & 6 bands.  It will start at Windward Mall at Haiku Rd., to Kamehameha Hwy., to Kaneohe Bay Dr., to end at Castle High School. Contact:  Anna Kuulei Richardson Olsen 348-2749

 

December 3, 2005 Saturday
10:00AM Starts
11:30AM Ends

WAIANAE COAST XMAS PARADE sponsored by Rotary Club of Waianae Coast. The event is expected to have 1,000 marchers, 30 vehicles, 30 floats, 10 bands, 3 horse units.  It will start at Waianae Boat Harbor parking lot, to Farrington Hwy., end at Waianae Mall.  Contact:  Anson Rego 696-7061  Fax: 696-7765

 

December 3, 2005 Saturday
11:00AM Starts
1:00PM Ends

KOOLAULOA LIONS NORTH SHORE XMAS PARADE sponsored by Koolauloa Lions Club. The event is expected to have 5 vehicles.  It will start at Pupukea Rd./Kamehameha Hwy, to Kamehameha Hwy, to end at Swanzy Beach Park parking lot.   Contact:  Donald Hurlbut 293-8050  Fax: 293-7667

 

December 3, 2005 Saturday
6:00PM Starts
11:00PM Ends

MAYOR'S ANNUAL XMAS TREE LIGHTING CEREMONY/PARADE sponsored by the City and County of Honolulu. The event is expected to have 2,000 marchers, 40 vehicles, 15 floats and 15 bands.  It will start at Aala Park to King St., kokohead on King St., to end in closed off portion of King St., between Punchbowl & South Sts. Contact: Eddie Oi, Department of Customer Services 523-4128

 

The above is based on the most current information available from the event organizers as of date on bottom.  TST Division, Department of Transportation Services  Phone: 808-527-6009 Fax: 808-523-4446 Email:  ikodani@co.honolulu.hi.us

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 523-4882, Wastewater Management Division, Construction Management - 527-5879.