ROAD WORK WEEKLY REPORT

 

Scheduled roadwork for the week beginning July 2, 2006, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch).  Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

ALEWA

Curb Ramps at Gulick Avenue/North School Street, Hala Drive/Makuahine Street, Hauiki Street/North School Street, Kino Street/North School Street, Linapuni Street/North School Street, Makuahine Street/North School Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, August 2006)

 

EWA

Ewa Villages, Extension of Kapolei Parkway, Phase 8A - Renton Road at future extension of Kapolei Parkway:  Construct new intersection including sewer, drainage, sidewalk, curb ramps, street lights, and landscape work.

            (Estimated completion date, July 2006)

 

Fort Weaver Road Manhole and Pipe Rehabilitation:  Rehabilitate the existing sewer line with CIPP along Fort Weaver Road from Renton Road to Geiger Road.

            (Estimated completion date, October 2006)

 

HALEIWA

Bridge Rehabilitation at Anahulu Stream:  Remove deteriorated concrete and reinforcement, reconstruct and repair areas, modify existing railings and paint structure.

            (Estimated completion date, July 2006)

 

HAWAII KAI

Curb Ramps at West Hind Drive & Nenue Street, Ulua Street & Mamaki Street, Ulua Street & Mahimahi Street, Awini Street & Kawaihine Street, Pepeekeo Street & Pepeekeo Place, Ainapo Street & Pepeekeo Place, Pepeekeo Street & Driveway, Hahaione Street & Hawaii Kai Drive, Ehu Wai Place, Hawaii Kai Drive & Kaluanui Road, Hawaii Kai Drive & Wailua Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

HONOLULU

Curb Ramps at Alakea Street/Merchant Street, Alakea Street/Queen Street, Bethel Street/Merchant Street, Bishop Street/Merchant Street, Halekauwila Street/Mililani Street, Maunakea Street/North Kukui Street, Merchant Street/Richards Street, Mililani Street/Queen Street, North Kukui Street/Nuuanu Street, North Kukui/River Street, Pauahi Street/Nuuanu Avenue, Queen Street/Richards Street, Queen Emma Street/Vineyard Street:  Construct new curb ramps, sidewalks, AC transitions.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, August 2006)

 

Rehabilitation of Harding Avenue from 1st Avenue to Luawai Street, 6th Avenue from Harding Avenue to Palolo Avenue, Leahi Avenue from Kapahulu Avenue to Noela Street, 5th Avenue from Harding Avenue to Dead End:  Completing installation of pavements, markings, traffic sensors and adjustment of utility covers to grade.

            (Estimated completion date, July 2006)

 

King Street Improvements, Phase 3 - North King Street between Liliha Street and Desha Lane and Austin Lane and Morris Lane:  Construction of concrete driveways, sidewalks, curb ramps, planting of trees; construction of street lighting system.  Pending revised scope of work.  Trees to be deleted.

            (Estimated completion date, November 2006)

 

Punchbowl Street Improvements, Phase I Reconstruct curb ramps, update traffic signal system and restripe pavement markings at King Street and Beretania Street intersection.

            (Estimated completion date, July 2006)

 

KAHALA

Curb Ramps at Hunakai Street between Pueo Street & Waialae Avenue:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

KAILUA

Curb Ramps at Kaneohe Bay Drive & Molo Street, Kailua Road & Oneawa Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Kuulei Road: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6:00 p.m.

            (Estimated completion date, October 2006)

 

Reconstruction of Concrete Sidewalks, Kailua Area Kuulei Road, Uluniu Street, Kainehe Street, Kailua Road, Hahani Street, Hoolai Street, Aulike Street: Removal and reconstruction of damaged concrete sidewalk, curb and gutter areas, trimming of trees and cutting and removal of tree roots where the roots have damaged the areas, installing root barriers were required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

            (Estimated completion date, July 2006)

 

Reconstruction of Concrete Sidewalks, Keolu Drive: The work involves the reconstruction of existing sidewalks, curbs and gutters and trimming of trees.

            (Estimated completion date, January 2007)

 

KAIMUKI

Curb Ramps at 16th Avenue & Waialae Avenue:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, October 2006)

 

KAKAAKO

Curb Ramps at South Street & Kawaiahao Street, Ward Street & HECO driveway:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

KALIHI

Curb Ramps at Kalihi Street/Lehua Street, Kalihi Street/Kuikele Street:  Construct new curb ramps, sidewalks and A.C. transitions.  Install pedestrian push buttons and striping.

            (Estimated completion date, August 2006)

 

KANEOHE

Reconstruction of Concrete Sidewalks, Kaneohe Area: Alaloa Street, Haiku Road, Kahuhipa Street, Kamehameha Highway, Kawa Street, Mehana Street:  Removal and reconstruction of damaged concrete sidewalk, curb, and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the area; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

            (Estimated completion date, July 2006)

 

Curb Ramps at Hui Aeko Street & Hui Aeko Place, Hui Iwa Street between Kahekili Street and Hui Iwa Place, Hui Akikiki Place & Hui Iwa Street, Alaloa Street & Haiku Road, Kahuhipa Street & Alaloa Street, Kam Hwy., Lilipuna Street & Kahuhipa Street, Kam Hwy., Keaahala Street & William Henry Road, Kam Hwy., Paleka Road & Waikalua Road:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, October 2006)

 

KAPAHULU

Curb Ramps at Date Street & Hausten Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

MAKIKI

Curb Ramps at Anianiku Street & Auwaiolimu Street, Lewalani Drive, Mott-Smith Drive & Piikoi Street, Wilder Avenue & Kewalo Street, Wilder Avenue & Keeaumoku Street, Wilder Avenue & Makiki Street, Punahou Street & Wilder Avenue, Punahou Street & Clark Street, Punahou Street, Manoa Road & Nehoa Street, Wilder Street & Alexander Street, Wilder Street, Farrington Street & Metcalf Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, October 2006)

 

MILILANI

Rehabilitation of Streets - Lanikuhana Avenue, Meheula Parkway (East Int.) to Ahiku Street.  Roadway reconstruction, cold planning and resurfacing; construction of asphalt concrete and concrete bus pad; reconstruction of existing concrete curbs and/or gutters, tree trimming and rootpruning; adjustment of utility manholes frames and covers; pavement markings and vehicle detector loops.            (Estimated completion date, January 2007)

 

Rehabilitation of Streets Meheula Parkway (Ainamakua Drive to Kaapehe Street), Ainamakua Drive (Makaikai Street to Ainamakua Drive) (2nd Int.), Makaikai Street (Ainamakua Drive to Ukuwai Street), Ukuwai Street (Makaikani Street to Ainamakua Drive), Kipapa Drive (Ikaloa Street (Honolulu end) to Kipapa Drive (near Kauamea Place),Kipapa Drive (Kaalolo Place to Lelewalo Street):  Roadway reconstruction, cold planning and resurfacing; construction of asphalt concrete and concrete bus pad; reconstruction of existing concrete curbs and/or gutters, tree trimming and rootpruning; adjustment of utility manholes frames and covers; pavement markings and vehicle dector loops.

            (Estimated completion date, December 2006)

 

PEARL CITY

Rehabilitation of Waimano Home Road from Kamehameha Highway to Komo Mai Drive:  Install curb ramps and traffic signals relocation.  Install vehicle loop sensors, and pavement markings and adjust utilities to grade.

            (Estimated completion date, July 2006)

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:  Final inspection punch list and change order work.

            (Estimated completion date, July 2006)

 

WAIALUA

Waialua Beach Road Sidewalk Improvements, Phase II Waialua Beach Road (between Goodale Avenue and Haleiwa Road):  Construct new sidewalks, curb ramps, bus stop and driveways.  Install new chain link fence, traffic signs and landscaping.

            (Estimated completion date, October 2006)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

 

July 2, 2006 Sunday
7:00AM Starts
12Noon Ends

FIRECRACKER SPRINT TRIATHLON sponsored by DeAxle Sports LLC. The event is expected to have 350 participants.  Swim: 500 meters- Nimitz Beach Park out and back course ending on beach near transition area.  Bike: 13.4 mile two loop- transition area, Nimitz Beach, to Coral Sea Rd., end Nimitz Beach Park transition area.  Run: 5K-   Transition area, Nimitz Beach, to Coral Sea Rd., to Tripoli, turnaround, to Tripoli, to Coral Sea Rd., end at Nimitz Beach Park.  Contact Steven Foster 864-0113  Fax:  685-6666

 

July 4, 2006 Tuesday
6:00AM Starts
7:30AM Ends

EPILEPSY FOUNDATION FREEDOM RUN sponsored by Epilepsy Foundation of Hawaii/USA Track & Field. The event will have 300 runners. It will start on Akiohala St. dead end (Kailua High School), to Keolu Dr., to Akake Pl., to turnaround in dead end,  to Akake Pl.,  - to Keolu Dr., to  Akiohala St., to end at Kailua High School Finish area.  Contact: Ed Kemper 524-0330, Fax:  523-1406.  For more info check out their website: www.hawaiiepilepsy.com/efh

 

July 4, 2006 Tuesday
10:00AM Starts
11:30AM Ends

KAILUA 4th OF JULY Independence Day Parade sponsored by Kailua Chamber of Commerce. The event will have 500 marchers, 70 vehicles, 15 floats, & 5 bands It will start at Kainalu Dr./Omao St., to Kainalu Drive, to end at Kailua Intermediate School. Contact: Kailua Chamber of Commerce 261-2727 Fax:262-0867

 

July 4, 2006 Tuesday
8:30PM Starts
8:50PM Ends

ALA MOANA 4TH OF JULY FIREWORKS DISPLAY sponsored by Ala Moana Shopping Center. The event is expected to have 20,000+ participants.  Show will be off Magic Island, Ala Moana Beach Park. Ewa Entrance to Ala Moana Park will be closed to inbound traffic from about 8 am, Sunday. Various traffic controls will be instituted by HPD at end of fireworks show.

 

July 7, 2006 Friday
6:30PM Starts
11:00PM Ends

1ST FRIDAY MERCHANT STREET FESTIVAL sponsored by Murphy's Bar & Grill to revitalize Chinatown. The event is expected to have 3,000+ participants.  The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St.  Street closed at 6:00 pm for set up.  Contact Don Murphy 531-0422, 754-1502 Fax: 533-4943

 

 

The above is based on the most current information available from the event organizers as of date on bottom.  TST Division, Department of Transportation Services  Phone: 808-527-6009 Fax: 808-523-4446 Email:  ikodani@co.honolulu.hi.us

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 523-4882, Wastewater Management Division, Construction Management - 527-5879.