FOR IMMEDIATE RELEASE                                                                               May 10, 2006

 

 

ROAD WORK WEEKLY REPORT

 

Scheduled roadwork for the week beginning May 14, 2006, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch).  Roadwork is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

ALEWA

Curb Ramps at Gulick Avenue/North School Street, Hala Drive/Makuahine Street, Hauiki Street/North School Street, Kino Street/North School Street, Linapuni Street/North School Street, Makuahine Street/North School Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, August 2006)

 

EWA

Ewa Villages, Extension of Kapolei Parkway, Phase 8A - Renton Road at future extension of Kapolei Parkway:  Construct new intersection including sewer, drainage, sidewalk, curb ramps, street lights, and landscape work.

            (Estimated completion date, May 2006)

 

HALEIWA

Bridge Rehabilitation at Anahulu Stream:  Remove deteriorated concrete and reinforcement, reconstruct and repair areas, modify existing railings and paint structure.

            (Estimated completion date, June 2006)

 

HAWAII KAI

Curb Ramps at West Hind Drive & Nenue Street, Ulua Street & Mamaki Street, Ulua Street & Mahimahi Street, Awini Street & Kawaihine Street, Pepeekeo Street & Pepeekeo Place, Ainapo Street & Pepeekeo Place, Pepeekeo Street & Driveway, Hahaione Street & Hawaii Kai Drive, Ehu Wai Place, Hawaii Kai Drive & Kaluanui Road, Hawaii Kai Drive & Wailua Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

HONOLULU

Curb Ramps at Alakea Street/Merchant Street, Alakea Street/Queen Street, Bethel Street/Merchant Street, Bishop Street/Merchant Street, Halekauwila Street/Mililani Street, Maunakea Street/North Kukui Street, Merchant Street/Richards Street, Mililani Street/Queen Street, North Kukui Street/Nuuanu Street, North Kukui/River Street, Pauahi Street/Nuuanu Avenue, Queen Street/Richards Street, Queen Emma Street/Vineyard Street:  Construct new curb ramps, sidewalks, AC transitions.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, August 2006)

 

Curb Ramps at Bishop Street between South Hotel Street and South King Street, Kekaulike Street/North Hotel Street, North Hotel Street/River Street, South King Street/Ward Avenue, Cooke Street/South King Street, Auahi Street/Kamakee Street, Middle Street/Rose Street, Kahauiki Street/Middle Street, Kamehameha IV Road/School Street, Hihio Place/Kamehameha IV Road, Kamehameha IV Road/Kilolani Place, Kamehameha IV Road/Kilohi Street, Kamehameha IV Road/Aoao Street, Kamehameha IV Road/Kalena Drive, Kamehameha IV Road (mid-block), Horner Lane/Kaua Street, Kamehameha IV Road/Kino Street, Campbell Avenue/Herbert Street, Campbell Avenue/Castle Street, Campbell Avenue/Brokaw Street, Campbell Avenue/Catherine Street, Campbell Avenue/Kaunaoa Street, Kanaina Avenue/Kaunaoa Street, Campbell Avenue/Esther Street:  Construct new curb ramps, sidewalks and AC transition.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated Completion Date, November 2006)

 

Rehabilitation of Harding Avenue from 1st Avenue to Luawai Street, 6th Avenue from Harding Avenue to Palolo Avenue, Leahi Avenue from Kapahulu Avenue to Noela Street, 5th Avenue from Harding Avenue to Dead End:  The work primarily consists of reconstruction, milling and resurfacing the roadways.  Also, included is the reconstruction of some concrete curbs, gutters, driveways, aprons, sidewalks, and some new drainage improvements.  Installation of pavements, markings, traffic sensors and adjustment of utility covers to grade will complete the project.

            (Estimated completion date, May 2006)

 

King Street Improvements, Phase 3 - North King Street between Liliha Street and Desha Lane and Austin Lane and Morris Lane:  Construction of concrete driveways, sidewalks, curb ramps, planting of trees; construction of street lighting system.  Pending revised scope of work.  Trees to be deleted.

            (Estimated completion date, April 2006)

 

Punchbowl Street Improvements, Phase I Reconstruct curb ramps, update traffic signal system and restripe pavement markings at King Street and Beretania Street intersection.

            (Estimated completion date, May 2006)

 

KAHALA

Curb Ramps at Hunakai Street between Pueo Street & Waialae Avenue:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

KAILUA

Curb Ramps at Kaneohe Bay Drive & Molo Street, Kailua Road & Oneawa Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

Kainehe, Hamakua, & Keolu Reconstructed Sewer: CIP work on Kainehe Street and Keolu Drive; Shaft Construction and Microtunneling on Hamakua Drive.

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Kuulei Road: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6:00 p.m.

            (Estimated completion date, October 2006)

 

Reconstruction of Concrete Sidewalks, Kailua Area Kuulei Road, Uluniu Street, Kainehe Street, Kailua Road, Hahani Street, Hoolai Street, Aulike Street: Removal and reconstruction of damaged concrete sidewalk, curb and gutter areas, trimming of trees and cutting and removal of tree roots where the roots have damaged the areas, installing root barriers were required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

            (Estimated completion date, May 2006)

 

KAIMUKI

Curb Ramps at 16th Avenue & Waialae Avenue:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, October 2006)

 

KAKAAKO

Curb Ramps at South Street & Kawaiahao Street, Ward Street & HECO driveway:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

KALIHI

Curb Ramps at Kalihi Street/Lehua Street, Kalihi Street/Kuikele Street:  Construct new curb ramps, sidewalks and A.C. transitions.  Install pedestrian push buttons and striping.

            (Estimated completion date, August 2006)

 

KANEOHE

Reconstruction of Concrete Sidewalks, Kaneohe Area: Alaloa Street, Haiku Road, Kahuhipa Street, Kamehameha Highway, Kawa Street, Mehana Street:  Removal and reconstruction of damaged concrete sidewalk, curb, and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the area; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

            (Estimated completion date, July 2006)

 

Curb Ramps at Hui Aeko Street & Hui Aeko Place, Hui Iwa Street between Kahekili Street and Hui Iwa Place, Hui Akikiki Place & Hui Iwa Street, Alaloa Street & Haiku Road, Kahuhipa Street & Alaloa Street, Kam Hwy., Lilipuna Street & Kahuhipa Street, Kam Hwy., Keaahala Street & William Henry Road, Kam Hwy., Paleka Road & Waikalua Road:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, October 2006)

 

KAPAHULU

Curb Ramps at Date Street & Hausten Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, October 2006)

 

MAKIKI

Curb Ramps at Anianiku Street & Auwaiolimu Street, Lewalani Drive, Mott-Smith Drive & Piikoi Street, Wilder Avenue & Kewalo Street, Wilder Avenue & Keeaumoku Street, Wilder Avenue & Makiki Street, Punahou Street & Wilder Avenue, Punahou Street & Clark Street, Punahou Street, Manoa Road & Nehoa Street, Wilder Street & Alexander Street, Wilder Street, Farrington Street & Metcalf Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, October 2006)

 

MOANALUA

Rehabilitation of Streets & Moanalua Water System Improvements:  Ala Aolani Place and portions of Ala Aolani Street, Ala Lani Street and Place, Ala Kiao Place, Ala Iolani Street and Place, Kapulei Street:  Install under drain, reconstruction and resurfacing of roadways, adjustment of utility manholes, installation of pavement markings.

            (Estimated completion date, May 2006)

 

PEARL CITY

Rehabilitation of Waimano Home Road from Kamehameha Highway to Komo Mai Drive:  Install curb ramps and traffic signals relocation.  Reconstruct failed pavement areas and resurface roadways.  Install vehicle loop sensors, and pavement markings and adjust utilities to grade.

            (Estimated completion date, June 2006)

 

PORTLOCK

Reconstruction of Concrete Sidewalks, Portlock Area:  Poipu Drive, Nawiliwili Street, Makaweli Street, Lawai Street, Lumahai Street, Lumahai Place, Hanapepe Loop, Hanapepe Place, Polihale Place, Kalalau Street, Waialae Avenue, Anahola Street.  Removal and reconstruction of damaged concrete sidewalk, curb, and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the areas; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

            (Estimated completion date, May 2006)

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:  Final inspection punch list and change order work.

            (Estimated completion date, May 2006)

 

WAIALUA

Rehabilitation of Waialua Beach Road:  Reconstruct bridge joint.

            (Estimated completion date, May 2006)

 

Waialua Beach Road Sidewalk Improvements, Phase II Waialua Beach Road (between Goodale Avenue and Haleiwa Road):  Construct new sidewalks, curb ramps, bus stop and driveways.  Install new chain link fence, traffic signs and landscaping.

            (Estimated completion date, October 2006)

 

WAIPAHU

Village Park Connector Road: Construction of a two-way connector road between Kupuna Loop in Village Park and Loaa Street in Waipahu.  Work includes roadway grading, construction of roadways, sidewalks, curb ramps and CRM and CMU walls; and installation of water lines, drain lines, electrical lines, streetlights, irrigation lines and landscaping.

            (Estimated completion date, April 2006)

 

 

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

 

May 14, 2006 Sunday
6:00AM Starts
10:30AM Ends

ITU JAL HONOLULU Triathlon World CHAMPIONSHIP RACE sponsored by USA Triathlon/Honolulu Triathlon Race Committee/Japan Air Lines. The event is expected to have 2,000 participants. Staggered Wave Start 6 am.  Ala Moana Blvd, Nimitz Hwy, and Kamehameha Hwy makai side will be closed to traffic.  Detailed route description will be posted shortly.  Contact:  Bill Burke 1-504-628-3155, Steve Foster 864-0113.  For more info, visit their website:  www.honolulutriathlon.com

 

May 14, 2006 Sunday
7:00AM Starts
8:30AM Ends

PEARL HARBOR BIKE PATH 10K RUN sponsored by RRCA/Mid Pacific Roadrunners Club. The event is expected to have 300 runners. It will start approx. 300 meters makai of Lehua Elem. School on Lehua St., to bike path, to Admiral's Boat House, end at Lehua Elem School.  Contact: John Simonds 373-3609 For more info, visit their website: http://www.mprrc.com/

 

May 20, 2006 Saturday
6:00AM Starts
9:00AM Ends

28th ANNUAL VISITOR INDUSTRY CHARITY walk sponsored by Hawaii Hotel Industry Assn. The event will have 9,000 runners/walkers.  It will start at Ala Moana Park's McCoy Pavilion Key Hole area, clockwise around Ala Moana Park, to             Ala Moana Blvd., mauka sidewalk area, to Ala Wai  Promenade area, to Kalakaua  Ave., makai sidewalk area and curb lane, to Queen Kapiolani Park, counter-clockwise around the park,  to cross Monsarrat Ave., to Paki Ave., makai sidewalk area, to cross Kapahulu Ave., to Ala Wai Blvd., mauka sidewalk and curb lane, to Seaside Ave., to Kalakaua Ave., to Ala Moana Blvd., to end at Ala Moana Park.  Contact: Tina Garcia  923-0407  Fax: 924-3843  Email:  tgarcia@hawaiihotels.org  For more info, visit their website: http://www.charitywalkhawaii.org/ 

 

May 20, 2006 Saturday
7:00AM Starts
9:00AM Ends

Wahiawa Pineapple Run sponsored by Wahiawa CPO Association. The event is in conjunction with the Wahiawa Pineapple Festival Parade.  It is expected to have 1,000 runners/walkersIt will start at Kaala Elementary School, to California Ave., to Kilani Ave., to Kam Hwy., to Kaukonahua Rd., to Kamananui Rd., to Wilikina Dr., to Kam Hwy., to Kam Hwy., to California Ave., to end at Kaala Elementary.  Contact John Cruz 653-0069 Fax: 653-0080

 

May 20, 2006 Saturday
9:00AM Starts
11:00AM Ends

WAHIAWA PINEAPPLE FESTIVAL PARADE sponsored by Wahiawa Community & Business Association. The event is expected to have 300 marchers, & 10 vehicles.  It will start at Kaala Elementary School, to California Ave., to North Cane St., end at Center St., Contact: Elizabeth Smithe  621-7097

 

May 20, 2006 Saturday
6:00PM Starts
10:00PM Ends

MURPHY'S CLAMBAKE BLOCK PARTY sponsored by Murphy's Bar & Grill to promote awareness of childhood cancer. The event is expected to have 3,000+ participants.  Curb lanes will be closed from 3 pm for setup. The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St.  Street closed at 9 am for set up.  Contact Don Murphy 531-0422, 754-1502 Fax: 533-4943

 

May 20, 2006 Saturday
7:00PM Starts
8:30PM Ends

FLORES DE MAYO PROCESSION sponsored by St. Elizabeth Filipino Catholic Club. The event is expected to have 100 participants.  It will start at St. Elizabeth Catholic Church, to Moanalua Rd., to Puakala St., to Kulina St., to Puakala St., to Moanalua Rd., end at St. Elizabeth Catholic Club.  Contact Amy Alejo 487-6658

 

 

The above is based on the most current information available from the event organizers as of date on bottom.  TST Division, Department of Transportation Services  Phone: 808-527-6009 Fax: 808-523-4446 Email:  ikodani@co.honolulu.hi.us

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 523-4882, Wastewater Management Division, Construction Management - 527-5879.