ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning November 5, 2006, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Miscellaneous Guardrail Improvements, FY 2005 - 99-274 Aiea Heights Drive:  Work includes metal guardrails, concrete, asphalt concrete pavement, concrete rubble masonry, and other incidental related work.

            (Estimated completion date, April 2007)

 

EWA

Fort Weaver Road Manhole and Pipe Rehabilitation:  Rehabilitate the existing sewer line with CIPP along Fort Weaver Road from Renton Road to Geiger Road.

            (Estimated completion date, November 2006)

 

HALEIWA

Miscellaneous Guardrail Improvements Haleiwa Road: Work includes metal guardrails, concrete, asphalt concrete pavement, concrete rubble masonry and other incidental related work.

            (Estimated completion date, April 2007)

 

HAWAII KAI

Curb Ramps at West Hind Drive & Nenue Street, Ulua Street & Mamaki Street, Ulua Street & Mahimahi Street, Awini Street & Kawaihine Street, Pepeekeo Street & Pepeekeo Place, Ainapo Street & Pepeekeo Place, Pepeekeo Street & Driveway, Hahaione Street & Hawaii Kai Drive, Ehu Wai Place, Hawaii Kai Drive & Kaluanui Road, Hawaii Kai Drive & Wailua Street:  Install pavement striping, markings and markers.

            (Estimated completion date, November 2006)

 

HONOLULU

Rehabilitation of Streets, Unit 5A, Beretania Street from N. King St. to Alapai St.  Install catch basins and drainpipe between Lisbon Street & Lauhala Street.

            (Estimated completion date, September 2007)

 

Curb Ramps at Bishop Street between South Hotel Street and South King Street, Kekaulike Street/North Hotel Street, North Hotel Street/River Street, South King Street/Ward Avenue, Cooke Street/South King Street, Auahi Street/Kamakee Street, Middle Street/Rose Street, Kahauiki Street/Middle Street, Kamehameha IV Road/School Street, Hihio Place/Kamehameha IV Road, Kamehameha IV Road/Kilolani Place, Kamehameha IV Road/Kilohi Street, Kamehameha IV Road/Aoao Street, Kamehameha IV Road/Kalena Drive, Kamehameha IV Road (mid-block), Horner Lane/Kaua Street, Kamehameha IV Road/Kino Street, Campbell Avenue/Herbert Street, Campbell Avenue/Castle Street, Campbell Avenue/Brokaw Street, Campbell Avenue/Catherine Street, Campbell Avenue/Kaunaoa Street, Kanaina Avenue/Kaunaoa Street, Campbell Avenue/Esther Street:  Construct new curb ramps, sidewalks and AC transition.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, December 2006)

 

Fort St. Mall & Hotel Street Sewer Replacement/Rehabilitation:  Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

            (Estimated completion date, December 2006

 

Rehabilitation of Harding Avenue from 1st Avenue to Luawai Street, 6th Avenue from Harding Avenue to Palolo Avenue, Leahi Avenue from Kapahulu Avenue to Noela Street, 5th Avenue from Harding Avenue to Dead End:  Installation of additional arrows at 6th Avenue and Waialae Avenue.

            (Estimated completion date, November 2006)

 

King Street Improvements, Phase 3 - North King Street between Liliha Street and Desha Lane and Austin Lane and Morris Lane:  Construction of concrete driveways, sidewalks, curb ramps, planting of trees; construction of street lighting system.  Pending revised scope of work.  Trees to be deleted.

            (Estimated completion date, November 2006)

 

Curb Ramps at Lowrey Avenue/Kaloauiki Place, Lowrey Avenue/Kanu Street, Woodlawn Drive near Manoa Stream: Construct new curb ramps, sidewalks, AC transitions.  Install pavement striping, adjust utility boxes, and relocate street signs and posts.

            (Estimated completion date, November 2006)

 

Rehabilitation of Various Streets, Unit 37 –South King Street between McCully Street and Old Waialae Road, East/West Hind Drive, Luinakoa Street, Kirkwood Place, Kupaua Place.  Reconstruction, cold milling and resurfacing of asphalt roadway; construction of concrete bus pads; reconstruction of curbs and gutters; adjustment of utilities to grade; installation of pavement markings and vehicle loop detectors.  Night paving of South King Street, from McCully Street to Old Waialae Road, begins October 16, 2006, Sunday to Friday, 8:00 p.m. to 5:00 a.m.

            (Estimated completion date, May 2007)

 

KAHALA

Curb Ramps at Hunakai Street between Pueo Street and Waialae Avenue:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, November 2006)

 

KAILUA

Curb Ramps at Kaneohe Bay Drive and Molo Street, Kailua Road and Oneawa Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, November 2006)

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Kuulei Road: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6:00 p.m.

            (Estimated completion date, October 2006)

 

Reconstruction of Concrete Sidewalks, Kailua Area – Kuulei Road, Uluniu Street, Kainehe Street, Kailua Road, Hahani Street, Hoolai Street, Aulike Street: Removal and reconstruction of damaged concrete sidewalk, curb and gutter areas, trimming of trees and cutting and removal of tree roots where the roots have damaged the areas, installing root barriers were required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

            (Estimated completion date, November 2006)

 

Reconstruction of Concrete Sidewalks, Keolu Drive: The work involves the reconstruction of existing sidewalks, curbs and gutters and trimming of trees.

            (Estimated completion date, January 2007)

 

KAIMUKI

Curb Ramps at 16th Avenue and Waialae Avenue:  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, November 2006)

 

Pooleka Street Drainage Improvements – Pooleka Street to Waiomao Stream: Construct new drainage system.  Upgrade the existing water system and restore existing driveway.

            (Estimated completion date, February 2007)

 

KAKAAKO

Curb Ramps at South Street and Kawaiahao Street, Ward Street and HECO driveway:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, November 2006)

 

KANEOHE

Reconstruction of Concrete Sidewalks, Kaneohe Area: Alaloa Street, Haiku Road, Kahuhipa Street, Kamehameha Highway, Kawa Street, Mehana Street:  Removal and reconstruction of damaged concrete sidewalk, curb, and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the area; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

            (Estimated completion date, November 2006)

 

Curb Ramps at Hui Aeko Street and Hui Aeko Place, Hui Iwa Street between Kahekili Street and Hui Iwa Place, Hui Akikiki Place and Hui Iwa Street, Alaloa Street and Haiku Road, Kahuhipa Street and Alaloa Street, Kam Hwy., Lilipuna Street and Kahuhipa Street, Kam Hwy., Keaahala Street and William Henry Road, Kam Hwy., Paleka Road and Waikalua Road:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, November 2006)

 

KAPAHULU

Curb Ramps at Date Street & Hausten Street:  Construct new curb ramps, sidewalks and A.C. transition.  Install pavement striping, markings and markers.

            (Estimated completion date, November 2006)

 

MAKIKI

Curb Ramps at Anianiku Street and Auwaiolimu Street, Lewalani Drive, Mott-Smith Drive & Piikoi Street, Wilder Avenue and Kewalo Street, Wilder Avenue and Keeaumoku Street, Wilder Avenue and Makiki Street, Punahou Street and Wilder Avenue, Punahou Street and Clark Street, Punahou Street, Manoa Road and Nehoa Street, Wilder Street and Alexander Street, Wilder Street, Farrington Street and Metcalf Street:  Install pavement striping, markings and markers and upgrade traffic signal system.

            (Estimated completion date, November 2006)

 

MILILANI

Rehabilitation of Streets - Lanikuhana Avenue, Meheula Parkway (East Int.) to Ahiku Street.  Roadway reconstruction, cold planning and resurfacing; construction of asphalt concrete and concrete bus pad; reconstruction of existing concrete curbs and/or gutters, tree trimming and rootpruning; adjustment of utility manholes frames and covers; pavement markings and vehicle detector loops.

            (Estimated completion date, January 2007)

 

Rehabilitation of Streets – Meheula Parkway (Ainamakua Drive to Kaapehe Street), Ainamakua Drive (Makaikai Street to Ainamakua Drive) (2nd Int.), Makaikai Street (Ainamakua Drive to Ukuwai Street), Ukuwai Street (Makaikani Street to Ainamakua Drive), Kipapa Drive (Ikaloa Street (Honolulu end) to Kipapa Drive (near Kauamea Place),Kipapa Drive (Kaalolo Place to Lelewalo Street):  Adjust utility manholes frames and covers; pavement markings and vehicle dector loops.

            (Estimated completion date, December 2006)

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:  Final inspection punch list and landscape maintenance.

            (Estimated completion date, July 2007)

 

WAIALUA

Waialua Beach Road Sidewalk Improvements, Phase II – Waialua Beach Road (between Goodale Avenue and Haleiwa Road):  Construct new sidewalks, curb ramps, bus stop and driveways.  Install new chain link fence, traffic signs and landscaping.

            (Estimated completion date, November 2006)

 

WAIANAE

Hakimo Road Drainage Improvements, Hakimo Road and Ulehawa Street:  Construct and install new storm drain inlet structures, RC pipe, manholes, outlet structure, riprap and chain link fence.  Cold plan and repave existing A.C. pavement.

            (Estimated completion date, June 2007)

 

WAIMANALO

Miscellaneous guardrail improvements, FY 2005:  41-771 Kumuhau Street:  Work includes metal guardrails, concrete, asphalt concrete pavement, concrete rubble masonry, and other incidental related work.

            (Estiamted completion date, April 2007)

 

PARADES, WALKS, RACES & OTHER STREET CLOSURES

 

November 5, 2006 Sunday
5:30AM Starts
9:00AM Ends

VAL NOLASCO MEMORIAL HALF MARATHON sponsored by RRCA/Mid Pacific Roadrunners Club. The event is expected to have 1,200 runners.  It will start at Kalakaua Ave., mauka side Queen Kapiolani Park, to Monsarrat Ave., to Paki Ave., to Diamond Hd. Rd., to 18th Ave., to Kilauea Ave., to Waialae Ave., to Kalanianaole Hwy., turnaround near W. Hind Dr., to Kealahou St., to Kahala Ave., to Diamond Hd. Rd., to Kalakaua Ave., to Queen Kapiolani Park Bandstand/Hon Marathon Finish.   Contact: John Simonds 373-3609 For more info, visit their website: http://www.mprrc.org/

 

November 5, 2006 Sunday
6:00AM Starts
9:30AM Ends

HALEIWA TRIATHLON sponsored by North Shore Swim Club. The event is expected to have 350 triathletes.  Swim will be offshore of Halewia Beach Park. Bike race will start at Haleiwa Beach Park transition area, to Kamehameha Hwy., to Joseph Leong by pass road, to Weed Junction, to Kamehameha Hwy., to loop around 2 more times on same course, end at Haleiwa Beach Park transition area. Run will start at transition area, to Police Beach along coast, to Eco Camp, to turnaround, to end at Haleiwa Beach Park.  Contact: Chris Gardner 372-8885, Fax:  485-0101

 

November 5, 2006 Sunday
6:30AM Starts
8:00AM Ends

KAILUA BEACH 10K RUN sponsored by Boca Hawaii. The event is expected to have 500 runners.  It will start at Kailua Beach Park Pavilion, to bike path on Kalaheo Ave., to Kawailoa Rd., to Aalapapa Dr., to Lanikai Loop (2 loops), to Mokulua Dr., to Kawailoa Rd., to Kalaheo Ave., to end at start. Contact: Raul Torres 223-2622, Fax:  737-8985.  For more info, visit their website:  http://www.bocahawaii.com/

 

November 10, 2006 Friday
10:00AM Starts
11:00AM Ends

WAHIAWA VETERANS DAY PARADE sponsored by Wahiawa Lions Club. The event is expected to have 1,000 marchers, 20 vehicles, & 5 bands.  It will start at Kaala Elementary, left onto California Ave., across Kam Hwy., end at Wahiawa Regional Park. Contact: Rene Mansho 306-1876 

 

 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 523-4882, Wastewater Management Division, Construction Management - 527-5879, Department of Transportation Services, TST Division 527-6009.

 