You are here:  Main / Customer Services / Public Communications Division / 2007 / Road Work Weekly Report

ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning February 18, 2007, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Miscellaneous Guardrail Improvements at Aiea Heights Drive:  Work includes metal guardrails, concrete, asphalt concrete pavement, concrete rubble masonry, and other incidental related work.

            (Estimated completion date, April 2007)

 

Kaonohi Street / Moanalua Road Intersection Improvements:  Work includes additional left turn lanes from Kaonohi Street to Moanalua Road, both directions; adding dedicated right turn lanes on Moanalua Road to Kaonohi Street, both directions; retrofitting countdown pedestrian signal heads; adding emergency vehicle preemption (EVP) detectors; installing new mast arms with standards and traffic signal heads for the traffic signal system; constructing a raised concrete median with chain link fence on Kaonohi Street Makai; pavement markings.  Contract work completed.  Extra work remains to be done.

            (Estimated completion date March 2007)

 

DIAMOND HEAD

Curb Ramps at Diamond Head Road & Coconut Avenue, Diamond Head Road & Beach road, Diamond Head Road & Kahala Avenue:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.

            (Estimated completion date, May 2007)

 

EWA

Fort Weaver Road Manhole and Pipe Rehabilitation:  Rehabilitate the existing sewer line with CIPP along Fort Weaver Road from Renton Road to Geiger Road.

            (Estimated completion date, February 2007)

 

HALEIWA

Miscellaneous Guardrail Improvements Haleiwa Road: Work includes metal guardrails, concrete, asphalt concrete pavement, concrete rubble masonry and other incidental related work.

            (Estimated completion date, April 2007)

 

HONOLULU

Rehabilitation of Beretania Street from N. King St. to Alapai St.  Traffic signal work at Alapai St.

            (Estimated completion date, September 2007)

 

Curb Ramps at Bishop Street between South Hotel Street and South King Street, Kekaulike Street/North Hotel Street, North Hotel Street/River Street, South King Street/Ward Avenue, Cooke Street/South King Street, Auahi Street/Kamakee Street, Middle Street/Rose Street, Kahauiki Street/Middle Street, Kamehameha IV Road/School Street, Hihio Place/Kamehameha IV Road, Kamehameha IV Road/Kilolani Place, Kamehameha IV Road/Kilohi Street, Kamehameha IV Road/Aoao Street, Kamehameha IV Road/Kalena Drive, Kamehameha IV Road (mid-block), Horner Lane/Kaua Street, Kamehameha IV Road/Kino Street, Campbell Avenue/Herbert Street, Campbell Avenue/Castle Street, Campbell Avenue/Brokaw Street, Campbell Avenue/Catherine Street, Campbell Avenue/Kaunaoa Street, Kanaina Avenue/Kaunaoa Street, Campbell Avenue/Esther Street:  Construct new curb ramps, sidewalks and AC transition.  Install pedestrian push buttons, pull boxes, vehicle detector loops, striping, marking and markers.

            (Estimated completion date, February 2007)

 

Resurfacing of a Portion of Dillingham Boulevard, Waiakamilo Road to Middle Street.  Reconstruction, cold milling and resurfacing of asphalt roadway; reconstruction of asphalt bus pads; adjustment of utilities to grade; installation of pavement markings and vehicle loop detectors.  The paving will be performed at night; all other activities are anticipated to be performed during daylight hours.

            (Estimated completion date, March 2007)

 

Curb Ramps at Emerson Street & Prospect Street, Iolani Avenue & Queen Emma Street (School Street & Lusitana Street), Hotel Street & Hale Makai Street:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

            (Estimated completion date, May 2007)

 

Fort St. Mall & Hotel Street Sewer Replacement/Rehabilitation:  Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

            (Estimated completion date, February 2007)

 

Rehabilitation of Harding Avenue from 1st Avenue to Luawai Street, 6th Avenue from Harding Avenue to Palolo Avenue, Leahi Avenue from Kapahulu Avenue to Noela Street, 5th Avenue from Harding Avenue to Dead End:  Installation of additional arrows at 6th Avenue and Waialae Avenue.

            (Estimated completion date, February 2007)

 

Emergency Reconstruction of Wall in the Vicinity of 2839 Pacific Heights Road.  Reconstruct a retaining wall in the vicinity of 2839 Pacific Heights Road.  Work includes removing the existing damaged CRM wall and landslide spoils, temporarily relocate plants in the work area, install temporary excavation support and BMPs, install drill shaft piles and construct a reinforced concrete retaining wall.

            (Estimated completion date, June 2007)

 

Round Top Drive Emergency Roadway Repairs:  Install drilled caissons and tie-back systems, reconstruct roadway pavement and curbs, relocate existing water line, and install guardrails.

            (Estimated completion date, May 2007)

 

School Street Emergency Drain Replacement School Street between Frog Lane and Liliha Street:  Remove and reconstruct existing damaged drainline, construct new catch basins, reset curbs, reconstruct sidewalks, driveways and thru gutters; restore asphalt pavement and markings.

(Estimated completion date, February 2007)

 

Rehabilitation of South King Street between McCully Street and Old Waialae Road, East/West Hind Drive, Luinakoa Street, Kirkwood Place, Kupaua Place.  Reconstruction, cold milling and resurfacing of asphalt roadway; construction of concrete bus pads; reconstruction of curbs and gutters; adjustment of utilities to grade; installation of pavement markings and vehicle loop detectors.

            (Estimated completion date, May 2007)

 

KAILUA

Curb Ramps at Akiohala Street & Keolu Drive, Pahumele Place & Keolu Drive, Hui Street& Keolu Drive, Keolu Drive & Akaakaawa Street, Kahili Street (Makai) & Akumu Street, Kahili Street (Mauka) & Akumu Street, Lopono Loop (Mauka) & Akumu Street, Hoolea Place & Akumu Street, Lopono Loop(Makai) & Akumu Street, Holoholo Street & Akumu Street, Halula Place & Akumu Street, Alahaki Street & Akumu Street, Akalei Place & Akumu Street, Akiu Place & Akumu Street, Akumu Place & Akumu Street:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Upgrade traffic signal system (Keolu Drive & Akakaawa Street only).

            (Estimated completion date, May 2007)

 

Kalaheo Avenue Reconstructed Sewer, from Kainui Drive to Kuulei Road: Road Closure for work on sewerline will be Monday thru Friday 8:30 a.m. to 6:00 pm and Saturday 9:00 a.m. to 6:00 p.m.

            (Estimated completion date, February 2007)

 

Curb Ramps at Keolu Drive & Kupau Street, Keolu Drive & Nanialii Street:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.

            (Estimated completion date, May 2007)

 

Reconstruction of Concrete Sidewalks - Kuulei Road, Uluniu Street, Kainehe Street, Kailua Road, Hahani Street, Hoolai Street, Aulike Street: Removal and reconstruction of damaged concrete sidewalk, curb and gutter areas, trimming of trees and cutting and removal of tree roots where the roots have damaged the areas, installing root barriers were required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

            (Estimated completion date, May 2007)

 

Rehabilitation of Kainehe Street (Kihapai Street to Kailua Road) and Hamakua Drive (Kailua Road to Keolu Drive):  Roadway reconstruction, cold planning and resurfacing; construction of asphalt concrete and concrete bus pad; construction of curb ramps and associated traffic signal upgrades; reconstruction of existing concrete curbs and/or gutters, tree trimming and root pruning; adjustment of utility manholes frames and covers; pavement markings and vehicle detector loops.

            (Estimated completion date, July 2007)

 

Reconstruction of Concrete Sidewalks on Keolu Drive: The work involves the reconstruction of existing sidewalks, curbs and gutters and trimming of trees.

            (Estimated completion date, February 2007)

 

KAIMUKI

Pooleka Street Drainage Improvements Pooleka Street to Waiomao Stream: Construct new drainage system.  Final cleanup and grass maintenance.

            (Estimated completion date, February 2007)

 

KALIHI

Curb Ramps at Lehua Street & Nihi Street, Amelia Street & North School Street:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.

            (Estimated completion date, May 2007)

 

KANEOHE

Curb Ramps at Kamehameha Highway & Kolokio Street, Kamehameha Highway & Kapalai Road, Kamehameha Highway & Hoene Place:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.

            (Estimated completion date, May 2007)

 

Reconstruction of Concrete Sidewalks on Alaloa Street, Haiku Road, Kahuhipa Street, Kamehameha Highway, Kawa Street, Mehana Street:  Removal and reconstruction of damaged concrete sidewalk, curb, and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the area; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

            (Estimated completion date, February 2007)

 

Curb Ramps at Hui Aeko Street and Hui Aeko Place, Hui Iwa Street between Kahekili Street and Hui Iwa Place, Hui Akikiki Place and Hui Iwa Street, Alaloa Street and Haiku Road, Kahuhipa Street and Alaloa Street, Kam Hwy., Lilipuna Street and Kahuhipa Street, Kam Hwy., Keaahala Street and William Henry Road, Kam Hwy., Paleka Road and Waikalua Road:  Upgrade traffic signal system.

            (Estimated completion date, May 2007)

 

Kawa Ditch Improvements:  Naumanu Place & Nakuluai Street, Kaneohe:  Removal existing trapezoidal concrete drain channel lining and reconstruction new concrete rectangular channel.

            (Estimated completion date, August 2007)

 

MAKIKI

Curb Ramps at Anianiku Street and Auwaiolimu Street, Lewalani Drive, Mott-Smith Drive & Piikoi Street, Wilder Avenue and Kewalo Street, Wilder Avenue and Keeaumoku Street, Wilder Avenue and Makiki Street, Punahou Street and Wilder Avenue, Punahou Street and Clark Street, Punahou Street, Manoa Road and Nehoa Street, Wilder Street and Alexander Street, Wilder Street, Farrington Street and

Metcalf Street:  Upgrade traffic signal system.

            (Estimated completion date, March 2007)

 

MILILANI

Rehabilitation of Streets - Lanikuhana Avenue, Meheula Parkway (East Int.) to Ahiku Street.  Paving complete, Contractor adjusting utility manholes frames and covers to grade; installing pavement markings and vehicle detector loops.

            (Estimated completion date, February 2007)

 

PEARL CITY

Reconstruction of Concrete Sidewalks, Moanalua Road and Kaahumanu Street:  Reconstruct sidewalks, driveways, curbs, gutters and AC pavement.  Adjust utility boxes to new sidewalk grade.  Tree trimming, root pruning, installing root barriers and removal of trees where required.          (Estimated completion date, November 1, 2007)

 

Curb Ramps at Noelani St. & Nola St.  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Relocate regulatory signs.

            (Estimated completion date, March 2007)

 

SALT LAKE

Salt Lake Boulevard Widening Phase 2A, Bougainville Drive to Maluna Street:  Landscape maintenance.

            (Estimated completion date, July 2007)

 

Curb Ramps at Ala Puumalu St. & Ala Oliko Pl., Ala Puumalu St. & Ala Punene Pl., Ala Puumalu St. & Ala Puumalu Pl.  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Relocate regulatory signs.

            (Estimated completion date, April 2007)

 

WAIALUA

Waialua Beach Road Sidewalk Improvements, Phase II Waialua Beach Road (between Goodale Avenue and Haleiwa Road):  Final inspection punch list work in progress; continue landscaping maintenance.

            (Estimated completion date, February 2007)

 

WAIANAE

Hakimo Road Drainage Improvements, Hakimo Road and Ulehawa Street:  Construct and install new storm drain inlet structures, RC pipe, manholes, outlet structure, riprap and chain link fence.  Cold plan and repave existing A.C. pavement.

            (Estimated completion date, June 2007)

 

WAIKIKI

Curb Ramps at Horbon Lane & Holomoana Street, Ena Road & Kalakaua Avenue, Koa Avenue & Liliuokalani Avenue, Kapahulu Avenue & Makee Road, Kapahulu Avenue & Campbell Avenue, Kapahulu Avenue & Kanaina Avenue:   Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Upgrade the traffic signal system.

            (Estimated completion date, May 2007)

 

WAIMANALO

Miscellaneous guardrail improvements at 41-771 Kumuhau Street:  Work includes metal guardrails, concrete, asphalt concrete pavement, concrete rubble masonry, and other incidental related work.

            (Estimated completion date, April 2007)

 

WAIPAHU

Waikele Road Improvements:  Work includes widening of Waikele Road and addition of curb and sidewalk fronting Waipahu Intermediate School, from Farrington Highway to Waipahu Flood Control Channel; adjustment of manholes, and boxes on the roadway being widened.

            (Estimated completion date, June 2007)

 

Waipahu Street Drainage Improvements:  Construct a new drainage system with 18, 24, 30, and 36 RCP drain lines; drain inlets with concrete aprons; drain manholes; a special catch basin; concrete headwall and concrete swales.  Other work includes the lowering of the existing water line, installing concrete jackets over the existing sewer lines, protecting the existing utility facilities, and necessary restoration work.

            (Estimated completion date, January 2008)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

February 19, 2007 Monday
6:45AM Starts
11:00AM Ends

HAWAIIAN TELCOM GREAT ALOHA RUN sponsored by Great Aloha Run/Carole Kai Charities. The event is expected to have 26,000 runners. It will start on Nimitz Hwy. at Nuuanu Ave., to Nimitz Hwy., ewa bound, to Kamehameha Hwy then under the H-1 viaduct, to Kamehameha Hwy., to Aloha Stadium service road into the main gate of Aloha Stadium, to finish in the north end zone of Aloha Stadium. Contact Carol Jaxon 528-7388, Fax:  528-7392.  For more info, visit their website: http://www.greataloharun.com/  

 

February 20, 2007 Tuesday
6:00PM Starts
10:30PM Ends

NUUANU MARDI GRAS STREET FESTIVAL sponsored by Honolulu Culture & Arts District Association. The event is expected to have 300+ participants.  Traffic will be diverted starting 3 pm for setup. The event will close NUUANU AVE., all traffic lanes/sidewalk areas, from Pauahi to King Sts.  Contact:  Ed Korybski 538-2220, Fax:  842-1962

 

February 21, 2007 Wednesday
8:45AM Starts
10:00AM Ends

WAIPAHU ELEMENTARY SCHOOL DRUG FREE WALK sponsored by Waipahu Elem. School. The event is expected to have 1,000 participants. It will start at Waipahu Elem. School on Waikele Rd., to Pupupuhi St., to Pupukahi St., to Farrington Hwy., to Pupupuhi St., to Waikele Rd., to finish at Waipahu Elem. School. Contact Roschelle Kalili 675-0150 ext. 268 Fax:

 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 523-4882, Wastewater Management Division, Construction Management - 527-5879, Department of Transportation Services, TST Division 768-8387.

 

Thursday, February 15, 2007

© Copyright 2002-2008 City and County of Honolulu, Hawaii
Privacy Statement | Technical Support | Customer Service | Policy | Accessibility | Diversity Statement