You are here:  Main / Customer Services / Public Communications Division / 2007 / Road Work Weekly Report

ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning December 2, 2007, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Kaonohi Street / Moanalua Road Intersection Improvements:  Work includes additional left turn lanes from Kaonohi Street to Moanalua Road, both directions; adding dedicated right turn lanes on Moanalua Road to Kaonohi Street, both directions; retrofitting countdown pedestrian signal heads; adding emergency vehicle preemption (EVP) detectors; installing new mast arms with standards and traffic signal heads for the traffic signal system; constructing a raised concrete median with chain link fence on Kaonohi Street Makai; pavement markings.  Contract work completed.  Extra work remains to be done.

            (Estimated completion date December 2007)

 

Newtown Neighborhood Kaahele Street Improvements, Vicinity of Komo Mai Drive to Moanalua Road.  Work includes adding left turn pockets, pavement markings, and signs.  Change order work has been completed.  Additional extra work may be added.

            (Estimated completion date, December 2007)

 

HAWAII KAI

Reconstruction of Concrete Sidewalks, Kawaihae Street Area, Hawaii Kai  Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

            (Estimated completion date, February 2008)

 

HONOLULU

Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street; work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

            (Estimated completion date, October 2008)

 

Curb ramps at Alexander Street/S. Beretania Street, Isenberg Street/S. Beretania Street, Kaheka Street/Kanunu Stree, Kaheka Street/Makaloa Street, Kalauokalani Way/Makaloa Street, Punahou Street/S. King Street, S. Beretania Street/Keeaumoku Street/Piikoi Street, Kinau Street/Victoria Street, S. Beretania Street/Pensacola Street/Victoria Street, S. Beretania Street/Victoria Street, S. Beretania Street/Ward Avenue, Coyne Street/University Avenue, Dole Street/East-West Road, Dole Street/University Avenue, Kahuna Lane/South King Street, University Avenue/Varsity Place, and Pawaina Street/Paumaka Place:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

            (Estimated completion date, December 2007)

 

Rehabilitation of Beretania Street from N. King St. to Alapai St.  Traffic signal system work Fort Street to Maunakea Street.  Reconstruct curb and gutter and sidewalks from Bishop Street to Maunakea Street.  Night paving of Beretania Street begins on November 20, 2007 from Lauhala Street proceeding West bound.

            (Estimated completion date, April 2008)

 

Curb Ramps at Date Street & University Avenue.  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Upgrade the traffic signal systems.

            (Estimated completion date, December 2007)

 

Resurfacing of a Portion of Dillingham Boulevard, Waiakamilo Road to Middle Street.  Adjusting utilities to grade; installation of pavement markings and vehicle loop detectors.

            (Estimated completion date, December 2007)

 

Fort St. Mall & Hotel Street Sewer Replacement/Rehabilitation:  Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

            (Estimated completion date, December 2007)

 

Curb Ramps at Various Locations, FY 2005(3) Hausten Street/South King Street, Kalakaua Avenue/Kapiolani Boulevard, Hoonanea Street/ Metcalf Street, Campus Road/Metcalf Street/University Avenue, Waialae Avenue/Wihelmina Rise/ 12th Avenue/Alohea Avenue, Alohea Avenue/Wela Street, Alohea Avenue/Edna Street, Mikihana Street/Mooheau Avenue, Francis Street/Upper Street, George Street/Upper Street, Hayden Street/Upper Street, Date Street/Kamoku Street/Kapiolani Boulevard, Young Street/Kaheka Street, 14th Avenue (A)/Waialae Avenue, 14th Avenue (B)/Waialae Avenue, and Elizabeth Street/Waialae Avenue:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

            (Estimated completion date, March 2008)

 

Curb Ramps at Various Locations, FY 2004(3) Kapiolani Boulevard & Paani Street, Kapiolani Boulevard & Wiliwili Street, Kapiolani Boulevard & Pumehana Street, Kaaha Street & University Avenue, Kalakaua Avenue & Young Street, Kalakaua Avenue & South King Street, Kalakaua Avenue & Philip Street, Kalakaua Avenue & South Beretania Street, Pensacola Street & Nehoa Street, Pensacola Street & Karratti Lane, Pensacola Street & Davenport Street, Pensacola Street & Hassinger Street, Pensacola Street & Kinau Street, Pensacola Street & South Beretania Street, Pensacola Street & Young Street, Pensacola Street & Alohi Way, Pensacola Street & Elm Street, Pensacola Street & Rycroft Street, Pensacola Street & Hoolai Street, Pensacola Street & Kaimaile Street:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Upgrade the traffic signal systems.

            (Estimated completion date, January 2008)

 

Rehabilitation of Keeaumoku Street between Kapiolani Boulevard to Kinau Street; Rycroft Street from Kaheka Street to Sheridan; Sheridan Street between Kapiolani Boulevard to South King Street; South Street from Ala Moana Boulevard to South King Street; University Avenue between Coyne Street to Hihiwai Street.  Reconstruction of concrete curbs and gutters, and new bus pads.  Reconstruction and resurfacing of asphalt pavements.  Adjusting manhole to finish grade, installation of vehicle loop detectors, and permanent pavement markings.

            (Estimated completion date, April 2008)

 

Round Top Drive Emergency Roadway Repairs:  Drilled caissons, tie-back systems, waterline & curbs installed.  Resurfacing and guardrails suspended until completion of Site 3, Phase 1.

            (Estimated completion date, December 2007)

 

Round Top Drive Emergency Roadway Repairs, Site 3, Phase I:  Clearing and grubbing of crib wall area complete.  Installed wire welded fabric in preparation of shotcrete application of existing crib wall.

            (Estimated completion date, December 2007)

 

Round Top Drive Emergency Roadway Repairs, Site 3, Phase II:  Micro-pile installation complete.  Installing reinforcement for crib wall tie-back system and rigid pavement; also included shotcrete wall finish; construct rigid pavement, concrete crib and guardrails.

(Estimated completion date, December 2007)

 

Sand Island Basin Miscellaneous Sewer Rehabilitation:  Continue replacement of sewer manhole frame and covers and manhole rehabilitation in various locations.  Rehabilitation of the Ward Avenue sewer tunnel, Sand Island Access Road sewerline, Ala Moana Park sewerline, Moanalua sewerline and Nuuanu sewerline are forthcoming.  Ward Avenue (between Kinau Street and South Beretania Street)

            (Estimated completion date, December 2007)

 

KAILUA

Rehabilitation of Kainehe Street (Kihapai Street to Kailua Road) and Hamakua Drive (Kailua Road to Keolu Drive):  Paving, traffic signal upgrades, adjustment utility manholes frames and covers to grade, and vehicle detector loops complete.  Installation of pavement markings, traffic sign and bridge deck joints require intermittent lane closures.

            (Estimated completion date, December 2007)

 

Maunawili Bridge 2 Over Kamakalepo Stream, Bridge No. 444:  Remove corrosion and debris from prestressed plank rebar, pour upstream half of bridge deck topping, backfill abutments, excavate bridge approach, install temporary guardrails.

            (Estimated completion date, December 2007)

 

KAIMUKI

Curb Ramps at 13th Avenue & Waialae Avenue, 6th Avenue & Keanu Street, Palolo Avenue & Kekona Place, Palolo Avenue & Kaau Street :  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Relocate street and traffic signs.  Upgrade traffic signal system.

            (Estimated completion date, January 2008)

 

Curb Ramps at 7th Avenue & Waialae Avenue, 10th Avenue & Waialae Avenue:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Relocate street and traffic signs.  Upgrade traffic signal system.

            (Estimated completion date, December 2007)

 

KANEOHE

Kawa Ditch Improvements:  Naumanu Place & Nakuluai Street, Kaneohe:  Removal existing trapezoidal concrete drain channel lining and reconstruction of new concrete rectangular channel.

            (Estimated completion date, December 2007)

 

Miscellaneous Storm Drainage Improvements at Kaneohe Bay Drive (near Hulakai Place):  This project replaces an existing 6x6 CRM box culvert drain with a new 6x6 precast concrete box culvert crossing Kaneohe Bay Drive near Hulakai Place.  Work includes the restoration of the roadway pavement and existing sidewalk.

            (Estimated completion date, December 2007)

 

PEARL CITY

Reconstruction of Concrete Sidewalks, Moanalua Road and Kaahumanu Street:  Contractor working on internal punchlist items.

            (Estimated completion date, December 2007)

 

Localized Rehabilitation of Streets, Phase 2, Various Streets (Manana & Momilani).  Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

            (Estimated completion date, January 2008)

 

WAIPAHU

Waikele Road Improvements:  Work includes widening of Waikele Road and addition of curb and sidewalk fronting Waipahu Intermediate School, from Farrington Highway to Waipahu Flood Control Channel; adjustment of manholes, and boxes on the roadway being widened.

            (Estimated completion date, December 2007)

 

Localized Rehabilitation of Streets, Phase 2, Various Streets  Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

            (Estimated completion date, January 2008)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

December 2, 2007 Sunday
7:00AM Starts
9:00AM Ends

SAMS MEMORIAL 5K RUN sponsored by sponsored by RRCA/Mid Pacific Roadrunners Club. They expect to have 200 runners.  It will start on Monsarrat Ave. near Waikiki Shell, to Paki Ave., to Kalakaua Ave., to Monsarrat Ave., to Paki Ave., to Kalakaua Ave., end at Honolulu Marathon finish/Kapiolani Bandstand.  Contact: John Simonds 373-3609, E-mail simondsj001@hawaii.rr.com   For more info, visit their website: http://www.mprrc.com/

 

December 2, 2007 Sunday 11:00AM Starts 
1:00PM Ends

STREET BIKERS UNITED-TOYS FOR TOTS CARAVAN sponsored by Street Bikers United Hawaii. The event is expected to have 4,000 motorcycles.  It will start at Magic Island, to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave., to Diamond Hd. Rd. to end at Kapiolani Community College-DH campus.  Contact:  Ray Pagan 282-6419  E-mail:  onerican@hawaii.rr.com

 

December 2, 2007 Sunday 4:00PM Starts 
5:30PM Ends

PEARL CITY SHOPPING CENTER CHRISTMAS PARADE sponsored by Pearl City Shopping Center. The event is expected to have 1,000 marchers, 20 vehicles, & 5 floats.  It will start at Momilani Elementary School, to Hookiekie St., to Hoomoana St., to Hoolaulea St., to end at Pearl City Shopping Center.  Contact:  Kristin Anderson  593-1533  Fax: 593-0569

 

December 6, 2007 Thursday 8:00AM Starts 
10:00AM Ends

LEGENDS 5K RUN part of Honolulu Marathon Series, sponsored by Honolulu Marathon Association. They expect to have 400 runners.  It will start on Kalakaua Ave., near Queen Kapiolani Park Bandstand, to Monsarrat Ave., to Paki Ave., to Kalakaua Ave., to Monsarrat Ave., to Paki Ave., to Kalakaua Ave., end at Honolulu Marathon finish/Kapiolani Bandstand. Contact:  Honolulu Marathon Assn. 734-7200, Fax: 732-7057  For more info, visit their website:  http://www.honolulumarathon.org/ 

 

December 6, 2007 Thursday 6:00PM Starts 
11:00PM Ends

2100 KALAKAUA AVENUE BLOCK PARTY sponsored by HSH 2100, LLC/Waikiki Improvement Association.  The event is expected to have 1,000+ participants.  The event will close Kalaimoku St., all traffic/sidewalk araes, from Kalakaua and Kuhio Aves. Contact:  Brenda Morey 955-2828 or Rick Egged 923-1094.  E-mail:  brenda.morey@cbre.comj or rickegged@waikikiimprovement.com 

 

December 6, 2007 Thursday 6:00PM Starts 
8:00PM Ends

KAIMUKI CHRISTMAS PARADE sponsored by Kaimuki Business & Professional Association.  The event is expected to have 1,500 marchers & 40 vehicles.  It will start at St. Louis HS/Chaminade University grounds, to Waialae Ave., to Koko Head Ave., to end at Municipal Parking Lot.  Contact:  John Kobayashi or Jeff Niebling KBPA 734-0277 or 732-7788, Fax:  735-8652, E-mail:  jeff@ngniebling.com

 

December 8, 2007 Saturday 9:00AM Starts 
11:00AM Ends

AIEA COMMUNITY ASSOCIATION CHRISTMAS PARADE sponsored by Aiea Community Association. The event is expected to have 300 marchers, 5 vehicles, & 3 bands.  It will start at Aiea High School Parking lot at Ulune St., to Aiea Heights Dr., to Moanalua Rd., to end at Pearlridge Shopping Center Phase 2 near Starbucks & Inspiration.  Contact:  Claire J. Tamamoto 429-1282, Fax:  946-8347

 

December 8, 2007 Saturday 10:00AM Starts 
11:30AM Ends

GENTRY WAIPIO COMMUNITY ASSOCIATION CHRISTMAS PARADE sponsored by Gentry Waipio Community Association. The event is expected to have 800 marchers, 13 vehicles, & 1 band.  It will start at Gentry Waipio SC, to Waipio Uka St., Ukee St., to Ka Uka Blvd., to Waipio Uka St., to end at Gentry Waipio SC.  Contact:  Laurie Sugue-Tabisola 671-2272  Fax: 671-0996

 

December 8, 2007 Saturday 11:00AM Starts 
1:00PM Ends

KOOLAULOA LIONS NORTH SHORE CHRISTMAS PARADE sponsored by Koolauloa Lions Club. The event is expected to have 5 vehicles.  It will start at Pupukea Rd./Kamehameha Hwy, to Kamehameha Hwy, to end at Swanzy Beach Park parking lot. Contact:  Carol Anamizu 293-1919 or Francis Daquioag, Jr. 293-6200x346, Fax: 293-1574

 

December 8, 2007 Saturday 3:00PM Starts 
4:00PM Ends

WAIPAHU CHRISTMAS PARADE sponsored by Leeward Oahu Lions. The event is expected to have 30 vehicles, 2 floats, 1 band & 10 motorcycle procession.  It will start at Waipahu District Park at Paiwa St., to Farrington Hwy., to Pupukahi St., to Waipahu St., to Leoku St., to end at Leolua St. behind Waipahu Town Centerl.  Contact:  Bryan K. Agbayani 216-7878, Fax:  539-0216

 

December 8, 2007 Saturday 5:00PM Starts 
7:00PM Ends

MANOA COMMUNITY CHRISTMAS PARADE sponsored by East Manoa Lions Club. The event is expected to have 800 marchers, 15 vehicles, 2 floats, & 4 bands.  It will start at Noelani School., to Woodlawn Dr, to Kolowalu St., to East Manoa Rd., to Lowrey Ave., to Manoa Rd., to Manoa Park finish.  Contact: Miyuki Matsuno 988-3819, E-mail:  matsunom001@hawaii.rr.com 

 

December 8, 2007 Saturday 6:00PM Starts 
8:00PM Ends

WEST OAHU HOLIDAY ELECTRIC LIGHT PARADE sponsored by Kapolei City Lights fka West Oahu Holiday Electric Light Parade. The event is expected to have 25  vehicles & 3 floats. It will start at Kapolei Fairgrounds at Kealanani Ave., to Farrington Hwy., to Kamokila Blvd., left into Uluohia St. and finish at Kapolei Hale. Contact:  Patty Teruya 527-5759, Fax:  550-6706

 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8390.

Thursday, November 29, 2007

© Copyright 2002-2008 City and County of Honolulu, Hawaii
Privacy Statement | Technical Support | Customer Service | Policy | Accessibility | Diversity Statement