 CONSTRUCTION WEEKLY REPORT

 

Scheduled construction for week beginning January 5, 2009 for the Department of Design & Construction, Civil Division (Construction Management Branch), & Wastewater Division (Construction Management Branch).  Roadwork is normally done between the hours of 8:30 AM & 3:30 PM unless otherwise noted. 

 

***Motorists should anticipate intermittent lane closures when traversing through the area.

 

AIEA

 

Rehabilitation of Streets, Unit 61 Kaamilo Street (Neki Street to Aiea Heights Drive), Iliee Street (Pakonane Place to Kaamilo Street), Kulawai Street (Kaamilo Street to Akaaka Street), Akaaka Street (Kulawai Street to End), Kalamoho Place (Kaamilo Street to End), Kalawina Place (Kaamilo Street to End)

 

Limited reconstruction of concrete curbs and gutters and replacement of concrete panels at Alolua Street.  Construction of thirteen (13) asphalt bus pads.  Reconstruction and resurfacing of asphalt pavements.  Adjusting manhole to finish grade and permanent pavement markings.  

 

            (Estimated completion date, November 2008)

 

Kaamilo Ditch Repair

 

Work includes:  demolishing and removing existing rock walls, trees; constructing new reinforced concrete channel; installing new 4'-0" chain link fence; providing reinforced concrete jacket for existing 8-inch sewer.

 

            (Estimated completion date, May 2009)

 

HALAWA

 

Aliipoe Ditch Reconstruction Halawa Heights, Lalawai Drive and Kahema Place area:

 

Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18" drain pipes.  Install new chain link fence.

 

            (Estimated completion date, March 2009)

 

HAWAII KAI

 

CONSTRUCTION SUSPENDED

Reconstruction of Concrete Sidewalks, Kawaihae Street Area, Hawaii Kai:

Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the

areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

 

(Estimated completion date, February 2008)

 

HONOLULU

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G and 1I:

 

New sewer line and manhole installation on Liliha Street (between Maui Street and Hawaii Street), Kuakini Street (between Nuuanu Avenue and Pali Highway).  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

           

(Estimated completion date, March 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1E:

 

New sewer line and manhole installation on Vinyard Blvd., Malanai Lane, School Street and Stillman Lane.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

           

(Estimated completion date, February 2009)

 

Kapiolani Area Revised Sewer System Improvements:

 

New sewer line, CIPP lining, and manhole installation on Kalauokalani, Kona Street, Atkinson Drive, and Ala Moana Blvd.  Sewerwork is ongoing on Kalauokalani.  One lane will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

 

            (Estimated completion date, March 2009)

 

Nuhelewai Stream Improvements

Project includes:  demolishing and removing existing rock walls and trees; constructing new concrete channels, retaining walls and grouted rubble paved work; installing 6-foot-high chain link fence; and installing permanent erosion control.

 

            (Estimated completion date, October 2008)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:

 

New sewer line and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Sewerwork is ongoing on Pua Lane.  Repaving of King, Peterson and Pua lane to follow after sewer work is complete.  Pua Lane One lane in mauka bound direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

 

            (Estimated completion date, March 2009)

 

CONSTRUCTION SUSPENDED ~ REVISING CURB AND PAVING PLAN

Reconstruction of Lusitana Street From Pauoa Avenue to Iolani Avenue

 

The work includes the reconstruction and resurfacing of the above street; construction of concrete bus landings; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

 

            (Estimated completion date, September 2009)

 

Rehabilitation of Various Streets on Oahu:  Work on Malia Street between Ainakoa and Kilauea Street is expected to begin in November, 2008.  Paving work is complete on Kahala Avenue.  Striping of Malia Street and Ainakoa Avenue will be completed on December 24, 2008. 

 

            (Estimated completion date, December 2008)

 

CONSTRUCTION SUSPENDED FOR HOLIDAY SEASON PER DTS

Rehabilitation of Street, Unit 38 Kilauea Avenue from Hunakai Street (Mauka of H-1) to 18th Avenue

 

The work includes the reconstruction and resurfacing of the above street; construction of concrete bus pads; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

 

            (Estimated completion date, January 2009)

 

Rehabilitation of Streets, Unit 49 Alewa Drive:   Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street: Work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

            (Estimated completion date, October 2008)

 

Saint Louis Heights Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

 

            (Estimated completion date, January 2009)

 

Kuliouou Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.

           

            (Estimated completion date, February 2009)

 

Sewer rehabilitation on various streets on Wilhelmina Rise

Wilhelmina Rise Sewer Rehabilitation will be starting next week.

 

(Est Completion date Nov. 2010)

 

KAILUA

 

Ilimalia Loop/Mokapu Boulevard Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP) and manhole rehabilitation within Ilimalia Loop and Mokapu Boulevard.

 

            (Estimated completion date, August 2008)

 

Maunawili Bridge 2 Over Kamakalepo Stream, Bridge No. 444:

Guard and bicycle rail installation problem:  waiting for Kaikor to address problem of misalignment and over drilled holes in guard & bicycle rails.

           

            (Estimated completion date, August 2008)

 

SUSPENDED ~ AWAITING BRIDGE JOINT DETAILS

Rehabilitation of Streets, Unit 42 Kainehe Street (Kihapai Street to Kailua Road) and Hamakua Drive (Kailua Road to Keolu Drive):

 

Paving, traffic signal upgrades, adjustment utility manholes frames and covers to grade, vehicle detector loops and pavement markings complete.  Installation of, traffic signs, bridge deck joints and deficiency require intermittent lane closures and punchlist.

 

            (Estimated completion date, November 2007)

 

 

Rehabilitation of Streets, Unit 46 Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):  Notice to Proceed scheduled for Nov. 17, 2008.

 

Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings.

 

 

Kailua Road Sewers Improvement District No. 276:

 

Installation of new sewer line along Kailua Road between Hahani Street and Aoloa Road.

 

            (Estimated completion date, April 2008)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:

 

Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

 

            (Estimated completion date, January 2009)

           

KANEOHE  

 

Guardrail Improvements - FY2006

(4 site locations:  2 sites in Kapolei/Makakilo on Farrington Hwy, 2 sites in Kaneohe on Kamehameha Hwy at Heeia Kea and Lilipuna Road)

Lilipuna Road site: existing guardrails and posts removed, new guardrails and posts installed.  Work completed.

Heeia Kea site:  existing guardrails and posts removed, new guardrails and posts installed.  Site signage to be completed.

 

KAPOLEI

 

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):

 

Clearing, grubbing and mass grading for construction of new 6-lane wide roadway with bike lane, raised median strips, sewer, water, drainage, street lighting and traffic signal systems, fences, sidewalks, curbs, gutters and subdrains, irrigation and landscaping, pavement markings and traffic signs.  Installation of erosion controls and dust fences throughout the project.

 

            (Estimated completion date March 2009)

           

 

Ewa Villages, Extension of Kapolei Parkway, Phase 8C (Renton Road to Kolowaka Street)

 

Work includes Civil, Structural, Electrical and Landscape work to complete the extension of Kapolei Parkway from Renton Road to Kolowaka Street.

 

            (Estimated completion date, May 2009)

 

Guardrail Improvements - FY2006

(4 site locations:  2 sites in Kapolei/Makakilo on Farrington Hwy, 2 sites in Kaneohe on Kamehameha Hwy at Heeia Kea and Lilipuna Road)

2 sites at Kapolei/Makakilo:  start date pending energy absorbing system submittal by contractor.

 

MAKAKILO

 

Bridge Rehabilitation Palahia Street Bridge Over Awanui Stream

Repair spalling in bridge elements, replace deck expansion joints, construct new concrete approach slabs, reconstruct gutters, and repair settlements in sidewalk.

 

            (Estimated completion date, February 2009)

           

 

MANOA

 

Rehabilitation of Streets, Unit 50 Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end):

 

Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings.

 

            (Estimated completion date, November 2008)

 

 

University Avenue/Maile Way Retaining Wall Repair

 

Demolish and reconstruct existing retaining wall including new railings.  Replace affected sidewalks, curbs, gutters and asphalt pavement.  Construct new wheelchair ramps, install new crosswalks, replace street markings, signs and traffic signals. Adjust utility frames and covers; manhole frames and covers; and utility boxes to new finish grade.

 

            (Estimated completion date, February 2009)

 

NUUANU

 

Seismic Retrofit Of City Bridges, Pelekane Drive Bridge Over Nuuanu Stream (Bridge No. 267)

 

Work involves installation of concrete shear keys, dowels for shear keys and girder strengthening for Pelekane Drive bridge.  Bridge repairs will be provided for the spalled areas along the girders, bottom of bridge slab and sidewalk, corroded rebars along the bridge bottom slab and shear cracks along the girders.  BMP measures and traffic controls will be installed.

 

            (Estimated completion date, November 2009)

 

PEARL CITY

 

REMAINING WORK TEMPORARILY SUSPENDED (Awaiting work schedule from Bonding Company)

Reconstruction of Concrete Sidewalks, Moanalua Road and Kaahumanu Street:

 

Reconstruct sidewalks, driveways, curbs, gutters and AC pavement.  Adjust utility boxes to new sidewalk grade.  Tree trimming, root pruning, installing root barriers and removal of trees where required.

Work substantially completed on November 1, 2007. Contractor needs to complete internal punchlist items.  Awaiting Surety Company contractor to complete the work.

 

SALT LAKE

 

Bridge Rehabilitation, Salt Lake Boulevard Bridge Over Halawa Stream:

 

Repair cracks at bridge abutments, girders and deck.  Provide concrete in-fill with reinforcing steel and install steel hangers and reinforce fabric material for strengthening the bridge girders.

Provide bridge deck restoration for installation of steel hanger assembly.  Repair reinforce fabric deficiencies (internal punch list work).

 

            (Estimated completion date, January 2009)

 

WAIMANALO

 

Hihimanu Street Sidewalk Improvement:

 

Installation of sidewalks; curbs and gutters along the makai side of Hihimanu Street.  Also work includes constructing curb inlets, headwalls, retaining walls, steel pipe railings; adjusting manhole covers and fire hydrants; and reconstructing driveway aprons.

 

            (Estimated completion date, January 2009)

 

Wednesday, December 31, 2008