Scheduled construction for week beginning January 5, 2009 for the Department of Design & Construction, Civil Division (Construction Management Branch), & Wastewater Division (Construction Management Branch). Roadwork is normally done between the hours of 8:30 AM & 3:30 PM unless otherwise noted. ***Motorists should anticipate intermittent lane closures when traversing through the area. Rehabilitation of Streets, Unit 61 – Kaamilo Street (Neki Street to Aiea Heights Drive), Iliee Street (Pakonane Place to Kaamilo Street), Kulawai Street (Kaamilo Street to Akaaka Street), Akaaka Street (Kulawai Street to End), Kalamoho Place (Kaamilo Street to End), Kalawina Place (Kaamilo Street to End) Limited reconstruction of concrete curbs and gutters and replacement of concrete panels at (Estimated completion date, November 2008) Kaamilo Ditch Repair Work includes: demolishing and removing existing rock walls, trees; constructing new reinforced concrete channel; installing new 4'-0" chain link fence; providing reinforced concrete jacket for existing 8-inch sewer. (Estimated completion date, May 2009) HALAWA
Aliipoe Ditch Reconstruction – Demolish, remove and reconstruct existing concrete drainage ditch. Construct maintenance access ramp and driveway. Install storm drain manholes, drain inlets, trench drain, and 18" drain pipes. Install new chain link fence. (Estimated completion date, March 2009)
CONSTRUCTION SUSPENDED Reconstruction of Concrete Sidewalks, Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work. (Estimated completion date, February 2008) Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G and 1I: New sewer line and manhole installation on (Estimated completion date, March 2009) Kalihi Nuuanu Area Sewer Rehabilitation Phase 1E: New sewer line and manhole installation on (Estimated completion date, February 2009) Kapiolani Area Revised Sewer System Improvements: New sewer line, CIPP lining, and manhole installation on Kalauokalani, (Estimated completion date, March 2009) Nuhelewai Stream Improvements Project includes: demolishing and removing existing rock walls and trees; constructing new concrete channels, retaining walls and grouted rubble paved work; installing 6-foot-high chain link fence; and installing permanent erosion control. (Estimated completion date, October 2008) New sewer line and manhole installation on (Estimated completion date, March 2009) CONSTRUCTION SUSPENDED ~ REVISING CURB AND PAVING PLAN Reconstruction of The work includes the reconstruction and resurfacing of the above street; construction of concrete bus landings; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning. (Estimated completion date, September 2009) Rehabilitation of Various Streets on (Estimated completion date, December 2008) CONSTRUCTION SUSPENDED FOR Rehabilitation of Street, Unit The work includes the reconstruction and resurfacing of the above street; construction of concrete bus pads; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning. (Estimated completion date, January 2009) Rehabilitation of Streets, Unit 49 – Alewa Drive: Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street: Work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work. (Estimated completion date, October 2008) Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout (Estimated completion date, January 2009) Kuliouou Sewer Rehabilitation: Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines. (Estimated completion date, February 2009) Sewer rehabilitation on various streets on Wilhelmina Rise Wilhelmina Rise Sewer Rehabilitation will be starting next week. (Est Completion date – Nov. 2010) Installation of cured in place pipe (CIPP) and manhole rehabilitation within Ilimalia Loop and (Estimated completion date, August 2008) Guard and bicycle rail installation problem: waiting for Kaikor to address problem of misalignment and over drilled holes in guard & bicycle rails. (Estimated completion date, August 2008) SUSPENDED ~ AWAITING BRIDGE JOINT DETAILS Rehabilitation of Streets, Unit Paving, traffic signal upgrades, adjustment utility manholes frames and covers to grade, vehicle detector loops and pavement markings complete. Installation of, traffic signs, bridge deck joints and deficiency require intermittent lane closures and punchlist. (Estimated completion date, November 2007) Rehabilitation of Streets, Unit 46 – Kailua Road ( Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings. Installation of new sewer line along (Estimated completion date, April 2008) Wanaao Road/Keolu Drive Reconstructed Sewer: Installation of new sewer line along (Estimated completion date, January 2009) Guardrail Improvements - FY2006 (4 site locations: 2 sites in Kapolei/Makakilo on Heeia Kea site: existing guardrails and posts removed, new guardrails and posts installed. Site signage to be completed. KAPOLEI Extension of Clearing, grubbing and mass grading for construction of new 6-lane wide roadway with bike lane, raised median strips, sewer, water, drainage, street lighting and traffic signal systems, fences, sidewalks, curbs, gutters and subdrains, irrigation and landscaping, pavement markings and traffic signs. Installation of erosion controls and dust fences throughout the project. (Estimated completion date March 2009) Ewa Villages, Extension of Work includes Civil, Structural, Electrical and Landscape work to complete the extension of (Estimated completion date, May 2009) Guardrail Improvements - FY2006 (4 site locations: 2 sites in Kapolei/Makakilo on 2 sites at Kapolei/Makakilo: start date pending energy absorbing system submittal by contractor. MAKAKILO
Bridge Rehabilitation – Palahia Street Bridge Over Awanui Stream Repair spalling in bridge elements, replace deck expansion joints, construct new concrete approach slabs, reconstruct gutters, and repair settlements in sidewalk. (Estimated completion date, February 2009) MANOA Rehabilitation of Streets, Unit 50 – Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end): Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings. (Estimated completion date, November 2008) University Demolish and reconstruct existing retaining wall including new railings. Replace affected sidewalks, curbs, gutters and asphalt pavement. Construct new wheelchair ramps, install new crosswalks, replace street markings, signs and traffic signals. Adjust utility frames and covers; manhole frames and covers; and utility boxes to new finish grade. (Estimated completion date, February 2009) NUUANU Seismic Retrofit Of City Bridges, Pelekane Drive Bridge Over Nuuanu Stream (Bridge No. 267) Work involves installation of concrete shear keys, dowels for shear keys and girder strengthening for (Estimated completion date, November 2009)
REMAINING WORK TEMPORARILY SUSPENDED (Awaiting work schedule from Bonding Company) Reconstruction of Concrete Sidewalks, Reconstruct sidewalks, driveways, curbs, gutters and AC pavement. Adjust utility boxes to new sidewalk grade. Tree trimming, root pruning, installing root barriers and removal of trees where required. Work substantially completed on November 1, 2007. Contractor needs to complete internal punchlist items. Awaiting Surety Company contractor to complete the work. Bridge Rehabilitation, Salt Lake Boulevard Bridge Over Halawa Stream: Repair cracks at bridge abutments, girders and deck. Provide concrete in-fill with reinforcing steel and install steel hangers and reinforce fabric material for strengthening the bridge girders. Provide bridge deck restoration for installation of steel hanger assembly. Repair reinforce fabric deficiencies (internal punch list work). (Estimated completion date, January 2009) WAIMANALO Installation of sidewalks; curbs and gutters along the makai side of (Estimated completion date, January 2009) |
| Wednesday, December 31, 2008 |