Scheduled road work for the week beginning December 29, 2008, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Rehabilitation of Streets, Unit 61 Kaamilo Street (Neki Street to Aiea Heights Drive), Iliee Street (Pakonane Place to Kaamilo Street), Kulawai Street (Kaamilo Street to Akaaka Street), Akaaka Street (Kulawai Street to End), Kalamoho Place (Kaamilo Street to End), Kalawina Place (Kaamilo Street to End).  Limited reconstruction of concrete curbs and gutters and replacement of concrete panels at Alolua Street.  Construction of thirteen (13) asphalt bus pads.  Reconstruction and resurfacing of asphalt pavements.  Adjusting manhole to finish grade and permanent pavement markings. 

            (Estimated completion date, December 2008)

 

Kaamilo Ditch Repair:  Work includes demolishing and removing existing rock walls, trees; constructing new reinforced concrete channel; installing new 4-0 chain link fence; providing reinforced concrete jacket for existing 8-inch sewer.

            (Estimated completion date, May 2009)

 

EWA

Ewa Villages, Extension of Kapolei Parkway, Phase 8C (Renton Road to Kolowaka Street)  Work includes Civil, Structural, Electrical and Landscape work to complete the extension of Kapolei Parkway from Renton Road to Kolowaka Street.

            (Estimated completion date, May 2009)

 

HALAWA

Aliipoe Ditch Reconstruction Halawa Heights, Lalawai Drive and Kahema Place area:  Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18 drain pipes.  Install new chain link fence.

            (Estimated completion date, March 2009)

 

HONOLULU

Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street: Work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

            (Estimated completion date, December 2008)

 

Fort St. Mall & Hotel Street Sewer Replacement/Rehabilitation:  Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

            (Estimated completion date, December 2008)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G and 1I:  New sewer line and manhole installation on Liliha Street (between Maui Street and Hawaii Street), Kuakini Street (between Nuuanu Avenue and Pali Highway).  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1E:  New sewer line and manhole installation on Vinyard Blvd., Malanai Lane, School Street and Stillman Lane.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, February 2009)

 

Kapiolani Area Revised Sewer System Improvements:  New sewer line, CIPP lining, and manhole installation on Kalauokalani, Kona Street, Atkinson Drive, and Ala Moana Blvd.  Sewerwork is ongoing on Kalauokalani.  One lane will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2009)

 

Kuliouou Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.

            (Estimated completion date, February 2009)

 

Rehabilitation of Various Streets on Oahu:  Work on Malia Street between Ainakoa and Kilauea Street is expected to begin in November, 2008.  Paving work is complete on Kahala Avenue.  Striping of Malia Street and Ainakoa Avenue will be completed on December 24, 2008.

            (Estimated completion date, December 2008)

 

Nuhelewai Stream Improvements:  Project includes demolishing and removing existing rock walls and trees; constructing new concrete channels, retaining walls and grouted rubble paved work; installing 6-foot-high chain link fence; and installing permanent erosion control.

            (Estimated completion date, December 2008)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

            (Estimated completion date, January 2009)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:  New sewerline and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Repaving to follow after sewer work is complete.

            (Estimated completion date, December 2008)

 

Sand Island Basin Miscellaneous Sewer Rehabilitation:  Continue replacement of sewer manhole frame and covers and manhole rehabilitation in various locations.  Rehabilitation of the Ward Avenue sewer tunnel, Sand Island Access Road sewerline, Ala Moana Park sewerline, Moanalua sewerline and Nuuanu sewerline are forthcoming.

            (Estimated completion date, December 2008)

 

Sewer rehabilitation on various streets on Wilhelmina Rise.

(Estimated completion date November 2010)

 

KAILUA

Ilimalia Loop/Mokapu Boulevard Sewer Rehabilitation:  Installation of cured in place pipe (CIPP) and manhole rehabilitation within Ilimalia Loop and Mokapu Boulevard.

            (Estimated completion date, December 2008)

 

Rehabilitation of Streets, Unit 46 Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):  Notice to Proceed scheduled for Nov. 17, 2008.  Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings.

 

Kailua Road Sewers Improvement District No. 276:  Installation of new sewer line along Kailua Road between Hahani Street and Aoloa Road.

            (Estimated completion date, December 2008)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:  Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

            (Estimated completion date, January 2009)

 

KANEOHE

Guardrail Improvements - FY2006  Kaneohe on Kamehameha Hwy at Heeia Kea and Lilipuna Road)  Lilipuna Road site: existing guardrails and posts removed, new guardrails and posts installed.  Work completed.  Heeia Kea site:  existing guardrails and posts removed, new guardrails and posts installed.  Site signage to be completed.

 

KAPOLEI

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):  Clearing, grubbing and mass grading for construction of new 6-lane wide roadway with bike lane, raised median strips, sewer, water, drainage, street lighting and traffic signal systems, fences, sidewalks, curbs, gutters and subdrains, irrigation and landscaping, pavement markings and traffic signs.  Installation of erosion controls and dust fences throughout the project.

            (Estimated completion date March 2009)

 

MAKAKILO

Bridge Rehabilitation Palahia Street Bridge over Awanui Stream repair spalling in bridge elements, replace deck expansion joints, construct new concrete approach slabs, reconstruct gutters, and repair settlements in sidewalk.

            (Estimated completion date, February 2009)

 

MANOA

Rehabilitation of Streets, Unit 50 Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end).  Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings

            (Estimated completion date, December 2008)

 

University Avenue/Maile Way Retaining Wall Repair:  Demolish and reconstruct existing retaining wall including new railings.  Replace affected sidewalks, curbs, gutters and asphalt pavement.  Construct new wheelchair ramps, install new crosswalks, replace street markings, signs and traffic signals. Adjust utility frames and covers; manhole frames and covers; and utility boxes to new finish grade.

            (Estimated completion date, February 2009)

 

NUUANU

Seismic Retrofit Of City Bridges, Pelekane Drive Bridge Over Nuuanu Stream (Bridge No. 267)

Work involves installation of concrete shear keys, dowels for shear keys and girder strengthening for Pelekane Drive bridge.  Bridge repairs will be provided for the spalled areas along the girders, bottom of bridge slab and sidewalk, corroded rebars along the bridge bottom slab and shear cracks along the girders.  BMP measures and traffic controls will be installed.

            (Estimated completion date, November 2009)

 

SALT LAKE

Bridge Rehabilitation, Salt Lake Boulevard Bridge Over Halawa Stream:  Repair cracks at bridge abutments and deck.  Provide concrete in-fill and reinforcing at spalled areas on bridge girders.  Strengthen girders with reinforce fabric material.

            (Estimated completion date, December 2008)

 

WAIMANALO

Hihmanu Street Sidewalk Improvement:  Installation of sidewalks; curbs and gutters along the makai side of Hihimanu Street.  Also work includes constructing curb inlets, headwalls, retaining walls, steel pipe railings; adjusting manhole covers and fire hydrants; and reconstructing driveway aprons.

            (Estimated completion date, December 2008)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

January 1, 2009 Thursday
7:00AM Starts
9:00AM Ends

BOSETTI 10K RUN sponsored by the Mid-Pacific Road Runners Club. The run is expected to have 100 runners.  It will start Kealahou St. near Sandy Beach, to Hawaii Kai Dr., to Lunalilo Home Rd., turnaround on Kolokolo St., to Lunalilo Home Rd., to Hawaii Kai Dr., to end at Kealahou St.  Contact:  John Simmonds 373-3609/383-7984, E-mail:  simondsj001@hawaii.rr.com

 

January 1, 2009 Thursday
8:00AM Starts
11:00AM Ends

NEW YEAR CELEBRATION-LANIKAI WOES DAY RUN/PARADE sponsored by the Lanikai Community Association.  The run is expected to have 25 runners.  Parade will consist of 50 marchers, 5 vehicles and 10 floats.  The event will start at Aalapapa Drive to Mokulua Drive and return to Aalapapa Drive.  Contact:  Dana Edmunds 295-3856, Fax: 261-0177, E-mail:  dana@danafoto.com

 

January 2, 2009    Friday
6:00PM Starts
10:00PM Ends

THE MAYOR'S INAUGURAL BLOCK PARTY sponsored by Arts District Merchants Association. The event is expected to have 500+ participants.  The event will close PAUAHI ST., all traffic lanes/sidewalk areas, from Bethel St. to Nuuanu Ave.  Contact:  Ed Korybski 398-7990 or Marsha Rose Joyner 741-4612, Fax:  842-1962 or 395-4612, E-mails:  ekorybski.hcad@gmail.com or  mrjoy@hawaii.rr.com For more info, visit their website:  www.artsdistricthonolulu.com 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8390.