ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning January 20, 2008, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Newtown Neighborhood – Kaahele Street Improvements, Vicinity of Komo Mai Drive to Moanalua Road.  Work includes adding left turn pockets, pavement markings, and signs.  Change order work has been completed.  Additional extra work may be added.

            (Estimated completion date, January 2008)

 

HAWAII KAI

Reconstruction of Concrete Sidewalks, Kawaihae Street Area, Hawaii Kai  Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

            (Estimated completion date, February 2008)

 

HONOLULU

Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street; work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

            (Estimated completion date, October 2008)

 

Curb ramps at Alexander Street/S. Beretania Street, Isenberg Street/S. Beretania Street, Kaheka Street/Kanunu Stree, Kaheka Street/Makaloa Street, Kalauokalani Way/Makaloa Street, Punahou Street/S. King Street, S. Beretania Street/Keeaumoku Street/Piikoi Street, Kinau Street/Victoria Street, S. Beretania Street/Pensacola Street/Victoria Street, S. Beretania Street/Victoria Street, S. Beretania Street/Ward Avenue, Coyne Street/University Avenue, Dole Street/East-West Road, Dole Street/University Avenue, Kahuna Lane/South King Street, University Avenue/Varsity Place, and Pawaina Street/Paumaka Place:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

            (Estimated completion date, January 2008)

 

Rehabilitation of Beretania Street from N. King St. to Alapai St.  Night work:  roadway reconstruction and paving from Alapai Street to Lauhala Street from January 2 to 11, 2008.  Day work:  construct bus pad between Queen Emma Street and Pali Highway; construct curb ramp at Pali Highway (mauka-Diamond Head corner).

            (Estimated completion date, April 2008)

 

Resurfacing of a Portion of Dillingham Boulevard, Waiakamilo Road to Middle Street.  Adjusting utilities to grade; installation of pavement markings and vehicle loop detectors.

            (Estimated completion date, January 2008)

 

Fort St. Mall & Hotel Street Sewer Replacement/Rehabilitation:  Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

            (Estimated completion date, January 2008)

 

Curb Ramps at Various Locations, FY 2005(3) – Hausten Street/South King Street, Kalakaua Avenue/Kapiolani Boulevard, Hoonanea Street/ Metcalf Street, Campus Road/Metcalf Street/University Avenue, Waialae Avenue/Wihelmina Rise/ 12th Avenue/Alohea Avenue, Alohea Avenue/Wela Street, Alohea Avenue/Edna Street, Mikihana Street/Mooheau Avenue, Francis Street/Upper Street, George Street/Upper Street, Hayden Street/Upper Street, Date Street/Kamoku Street/Kapiolani Boulevard, Young Street/Kaheka Street, 14th Avenue (A)/Waialae Avenue, 14th Avenue (B)/Waialae Avenue, and Elizabeth Street/Waialae Avenue:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

            (Estimated completion date, March 2008)

 

Curb Ramps at Various Locations, FY 2004(3) – Kapiolani Boulevard & Paani Street, Kapiolani Boulevard & Wiliwili Street, Kapiolani Boulevard & Pumehana Street, Kaaha Street & University Avenue, Kalakaua Avenue & Young Street, Kalakaua Avenue & South King Street, Kalakaua Avenue & Philip Street, Kalakaua Avenue & South Beretania Street, Pensacola Street & Nehoa Street, Pensacola Street & Karratti Lane, Pensacola Street & Davenport Street, Pensacola Street & Hassinger Street, Pensacola Street & Kinau Street, Pensacola Street & South Beretania Street, Pensacola Street & Young Street, Pensacola Street & Alohi Way, Pensacola Street & Elm Street, Pensacola Street & Rycroft Street, Pensacola Street & Hoolai Street, Pensacola Street & Kaimaile Street:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Upgrade the traffic signal systems.

            (Estimated completion date, January 2008)

 

Rehabilitation of Keeaumoku Street between Kapiolani Boulevard to Kinau Street; Rycroft Street from Kaheka Street to Sheridan; Sheridan Street between Kapiolani Boulevard to South King Street; South Street from Ala Moana Boulevard to South King Street; University Avenue between Coyne Street to Hihiwai Street.  Reconstruction of concrete curbs and gutters, and new bus pads.  Reconstruction and resurfacing of asphalt pavements.  Adjusting manhole to finish grade, installation of vehicle loop detectors, and permanent pavement markings.  Night paving of Keeaumoku Street to began October 14, 2007.  Day time paving of Rycroft Street tentatively scheduled for Monday, November 5, 2007.

            (Estimated completion date, April 2008)

 

Round Top Drive Emergency Roadway Repairs:  Drilled caissons, tie-back systems, waterline & curbs installed.  Resurfacing and guardrails suspended until completion of Site 3, Phase 1.

            (Estimated completion date, January 2008)

 

Round Top Drive Emergency Roadway Repairs, Site 3, Phase I:  Clearing and grubbing of crib wall area complete.  Installed wire welded fabric in preparation of shotcrete application of existing crib wall.

            (Estimated completion date, January 2008)

 

Round Top Drive Emergency Roadway Repairs, Site 3, Phase II:  Micro-pile installation complete.  Installing reinforcement for crib wall tie-back system and rigid pavement; also included shotcrete wall finish; construct rigid pavement, concrete crib and guardrails.

            (Estimated completion date, January 2008)

 

Sand Island Basin Miscellaneous Sewer Rehabilitation:  Continue replacement of sewer manhole frame and covers and manhole rehabilitation in various locations.  Rehabilitation of the Ward Avenue sewer tunnel, Sand Island Access Road sewerline, Ala Moana Park sewerline, Moanalua sewerline and Nuuanu sewerline are forthcoming.

            (Estimated completion date, March 2008)

 

Rehabilitation of Various Streets on Oahu – St. Louis Drive from Alencastre Street to mauka end, Campbell Avenue from Kapahulu Avenue to Collins Street, Date Street from University Avenue to Kapahulu Avenue, Diamond Head Road from Trousseau Street to Makapuu Avenue, Diamond Head Road from Lighthouse to 3rd Lookout at Kahala end, Fourth Avenue from Waialae Avenue to Harding Avenue, Kapahulu Avenue from Harding Avenue to Kalakaua Avenue, Waialae Avenue from 1st Avenue to 16th Avenue, Dole Street from St. Louis Drive to Wilder Avenue.

            (Estimated completion date January 2008.)

 

KAILUA

Rehabilitation of Kainehe Street (Kihapai Street to Kailua Road) and Hamakua Drive (Kailua Road to Keolu Drive):  Paving, traffic signal upgrades, adjustment utility manholes frames and covers to grade, and vehicle detector loops complete.  Installation of pavement markings, traffic sign and bridge deck joints require intermittent lane closures.

            (Estimated completion date, January 2008)

 

KANEOHE

Kawa Ditch Improvements:  Naumanu Place & Nakuluai Street, Kaneohe:  Removal existing trapezoidal concrete drain channel lining and reconstruction of new concrete rectangular channel.

            (Estimated completion date, January 2008)

 

Miscellaneous Storm Drainage Improvements at Kaneohe Bay Drive (near Hulakai Place):  This project replaces an existing 6’x6’ CRM box culvert drain with a new 6’x6’ precast concrete box culvert crossing Kaneohe Bay Drive near Hulakai Place.  Work includes the restoration of the roadway pavement and existing sidewalk.

            (Estimated completion date, January 2008)

 

NIU VALLEY

Niu Valley WWPS Force Main Reconstruction:  Restoration of the median in Kalaniana’ole Highway between Kawaikui Park and Niu Valley Shopping Center.

            (Estimated completion date January 2008)

 

PEARL CITY

Reconstruction of Concrete Sidewalks, Moanalua Road and Kaahumanu Street:  Contractor working on internal punchlist items.

            (Estimated completion date, January 2008)

 

Localized Rehabilitation of Streets, Phase 2, Various Streets (Manana & Momilani).  Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

            (Estimated completion date, January 2008)

 

WAIPAHU

Waikele Road Improvements:  Work includes widening of Waikele Road and addition of curb and sidewalk fronting Waipahu Intermediate School, from Farrington Highway to Waipahu Flood Control Channel; adjustment of manholes, and boxes on the roadway being widened.

            (Estimated completion date, January 2008)

 

Localized Rehabilitation of Streets, Phase 2, Various Streets  Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

            (Estimated completion date, January 2008)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

January 19-20, 2008 Saturday-Sunday
6:00AM Starts
6:00PM Ends

HURT TRAIL 100 sponsored by HURT. The event is expected to have 80 participants.  It will start at Hawaii Nature Center via trail to Paradise Park in Manoa, via trail to Jackass Ginger, back to Hawaii Nature Center, loop endurance course, end at start/finish area.  Two road crossings per 20 mile loop:  1.  Nahuina/Tantalus Dr.  2.  Moleka Trail/Manoa Cliffs Trail.  Contact: PJ Salmonson 235-0577 Fax: 585-0166  

 

January 20, 2008 Sunday
6:30AM Starts
8:00AM Ends

LeJARDIN FAMILY FUN RUN sponsored by LeJardin Academy.  The event is expected to have 350 runners.  It will start at Lanikai Park, to Aalapapa Dr., to Mokulua Dr., counterclockwise on bike path around Lanikai Loop, end at Lanikai Park.  Contact:  Reed CK Olaso 261-0707 ext. 292 Fax: 262-9339

 

January 20, 2008 Sunday
4:00PM Starts
6:00PM Ends

PARADE OF CHAMPIONS sponsored by City & County of Honolulu/Waikiki Improvement Association. The event is expected to have 1,000 marchers, 20 vehicles, 3 floats, 3 bands.  It will start at Ft. DeRussy to Kalakaua Ave., end at Queen Kapiolani Park.  Contact: Isaac Hokama 527-6090, E-mail:  ihokama1@honolulu.gov  

 

January 21, 2008 Monday
9:00AM Starts
12noon Ends

DR. MARTIN LUTHER KING JR. DAY PARADE sponsored by Martin Luther King Coalition. The event is expected to have 2,000 marchers, 100 vehicles, 20 floats, 6 bands.  It will start at Ala Moana Park, to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave., end at Waikiki Shell Parking Lot in Queen Kapiolani Park.  Contact: Patricia Anthony 384-4038 Fax: 672-4129  

 

January 26, 2008 Saturday
8:00AM Starts
9:30AM Ends

NEWMAN CENTER FUN RUN/WALK sponsored by the Newman Center.  The event is expected to have 200 runners.  The event will start at St. Francis School grounds, to Pamoa Rd., to Alaula Way., to Woodlawn Dr., to Kahaloa Dr., to U turn at Manoa Valley Field, to Kahaloa Dr., to Woodlawn Dr., to Alaula Way, to Pamoa Rd., end at Newman Center on UH campusContact:  Vincent Costello 988-2379, Fax:  988-1752

 

January 26, 2008 Saturday
5:00PM Starts
10:30PM Ends

CHINATOWN CHASE sponsored by the Hawaiian Theatre Center.  The event is expected to have 300 participants.  The event will close Bethel St. between Hotel and Pauahi Sts., all lanes/portion of Koko Head sidewalk area.  Contact:  Elaine Evans 791-1302, Fax:  528-0481

 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8390.

Thursday, January 17, 2008