ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning July 27, 2008, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Reconstruction of Concrete Sidewalks Halawa Area:  Work includes:  removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the areas; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

            (Estimated completion date, August 2008)

 

Rehabilitation of Streets, Unit 61 Kaamilo Street (Neki Street to Aiea Heights Drive), Iliee Street (Pakonane Place to Kaamilo Street), Kulawai Street (Kaamilo Street to Akaaka Street), Akaaka Street (Kulawai Street to End), Kalamoho Place (Kaamilo Street to End), Kalawina Place (Kaamilo Street to End).  Limited reconstruction of concrete curbs and gutters and replacement of concrete panels at Alolua Street.  Construction of thirteen (13) asphalt bus pads.  Reconstruction and resurfacing of asphalt pavements.  Adjusting manhole to finish grade and permanent pavement markings. 

            (Estimated completion date, November 2008)

 

HONOLULU

Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street; work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

            (Estimated completion date, October 2008)

 

Emergency Repair of 42-inch Drain Pipe at 2243 Booth Road and 2260 Kanealii Avenue:  Repair existing 42 drain pipe using cured-in-place-pipe (CIPP) liner, reconstruct existing catch basin and backfill sink hole at 2243 Booth Road.

            (Estimated completion date, July 2008)

 

Rehabilitation of Campbell Avenue from Kapahulu Avenue to Monsarrat Avenue, 4th Avenue from Waialae Avenue to Harding Avenue, Onipaa Street between Maalahi to Mahiole Street, Waimanu Street between Piikoi and Pensecola Queen Street between Ward Avenue and Kamakee St., Diamond Head Road Between Light House to 3rd lookout.  Work will commence in Manoa beginning mid-August (East Manoa Rd., Kahaloa, Lanihulu, Loulu, Kumukoa and Kumu Street).

            (Estimated completion date, September 2008)

 

Fort St. Mall & Hotel Street Sewer Replacement/Rehabilitation:  Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

            (Estimated completion date, July 2008)

 

Curb Ramps at Various Locations, FY 2005(3) Hausten Street/South King Street, Kalakaua Avenue/Kapiolani Boulevard, Hoonanea Street/ Metcalf Street, Campus Road/Metcalf Street/University Avenue, Waialae Avenue/Wihelmina Rise/ 12th Avenue/Alohea Avenue, Alohea Avenue/Wela Street, Alohea Avenue/Edna Street, Mikihana Street/Mooheau Avenue, Francis Street/Upper Street, George Street/Upper Street, Hayden Street/Upper Street, Date Street/Kamoku Street/Kapiolani Boulevard, Young Street/Kaheka Street, 14th Avenue (A)/Waialae Avenue, 14th Avenue (B)/Waialae Avenue, and Elizabeth Street/Waialae Avenue:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

            (Estimated completion date, July 2008)

 

Kalihi/Nuuanu Area Sewer Rehablitation Phase 1F and 1H:  New sewerline and manhole installation on Kuakini Street (between Liliha Street and Nuuanu Avenue), Nuuanu Avenue Ewa Side (between Bates and Judd Street), Prospect Street (near Madeira Street and San Antonio Avenue) and Puowaina Street (between Whiting and Hookui Street).  Lane closures Monday (7/21) thru Friday (7/25), 8:30 a.m. to 3:30 p.m.

 

Kalihi/Nuuanu Area Sewer Rehablitation Phase 1G and 1I:  New sewerline and manhole installation on Liliha Street (between Maui Street and Hawaii Street), Kuakini Street (between Nuuanu Avenue and Pali Highway) and Hialoa Street.  Lane closures Monday (7/21) thru Friday (7/25), 8:30 a.m. to 3:30 p.m.

 

Curb Ramps at Various Locations, FY 2004(3) Kapiolani Boulevard & University Street, Kapiolani Boulevard & Paani Street, Kalakaua Avenue & South King Street, Pensacola Street & Kinau Street:  Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Upgrade the traffic signal systems.

            (Estimated completion date, August 2008)

 

Rehabilitation of Keeaumoku Street between Kapiolani Boulevard to Kinau Street; Rycroft Street from Kaheka Street to Sheridan; Sheridan Street between Kapiolani Boulevard to South King Street; South Street from Ala Moana Boulevard to South King Street; University Avenue between Coyne Street to Hihiwai Street.  Reconstruction of concrete curbs and gutters, and new bus pads.  Reconstruction and resurfacing of asphalt pavements.  Adjusting manhole to finish grade, installation of vehicle loop detectors, and permanent pavement markings.  Paving of Keeaumoku Street, Rycroft Street and Sheridan Street complete; installing pavement markings and loop detectors; adjusting manhole to grade.  Night paving of University Avenue complete and will be switching to daytime paving February 25, 2008.  Night paving of South Street on-going; limits to be extended up to Beretania Street.

            (Estimated completion date, July 2008)

 

Rehabilitation of Kilauea Avenue from Hunakai Street (Mauka of H-1) to 18th Avenue.  The work includes the reconstruction and resurfacing of the above street; construction of concrete bus pads; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

            (Estimated completion date, January 2009)

 

Kuliouou Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.

            (Estimated completion date, February 2009)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

            (Estimated completion date, January 2009)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:  New sewerline and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Repaving to follow after sewer work is complete.  North King Street, between Dillingham Blvd. and Peterson Lane One lane in each direction will be closed Monday (4/28) thru Friday (5/2), 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, November 2008)

 

Sand Island Basin Miscellaneous Sewer Rehabilitation:  Continue replacement of sewer manhole frame and covers and manhole rehabilitation in various locations.  Rehabilitation of the Ward Avenue sewer tunnel, Sand Island Access Road sewerline, Ala Moana Park sewerline, Moanalua sewerline and Nuuanu sewerline are forthcoming.

            (Estimated completion date, July 2008)

 

KAILUA

Ilimalia Loop/Mokapu Boulevard Sewer Rehabilitation:  Installation of cured in place pipe (CIPP) and manhole rehabilitation within Ilimalia Loop and Mokapu Boulevard.

            (Estimated completion date, July 2008)

 

Kailua Road Sewers Improvement District No. 276:  Installation of new sewer line along Kailua Road between Hahani Street and Aoloa Road.

            (Estimated completion date, July 2008)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:  Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

            (Estimated completion date, January 2009)

 

KAPOLEI

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):  Clearing, grubbing and mass grading for construction of new 6-lane wide roadway with bike lane, raised median strips, sewer, water, drainage, street lighting and traffic signal systems, fences, sidewalks, curbs, gutters and subdrains, irrigation and landscaping, pavement markings and traffic signs.  Installation of erosion controls and dust fences throughout the project.

            (Estimated completion date March 2009)

 

MANOA

Rehabilitation of Streets, Unit 50 Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end).  Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings

            (Estimated completion date, November 2008)

 

SALT LAKE

Bridge Rehabilitation, Salt Lake Boulevard Bridge Over Halawa Stream:  Repair cracks at bridge abutments and deck.  Provide concrete in-fill and reinforcing at spalled areas on bridge girders.  Strengthen girders with reinforce fabric material.

            (Estimated completion date, December 2008)

 

WAIMANALO

Hihmanu Street Sidewalk Improvement:  Installation of sidewalks; curbs and gutters along the makai side of Hihimanu Street.  Also work includes constructing curb inlets, headwalls, retaining walls, steel pipe railings; adjusting manhole covers and fire hydrants; and reconstructing driveway aprons.

            (Estimated completion date, October 2008)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

July 26-27, 2008 Saturday-Sunday
Various times

BOCA HAWAII STAGE RACE SERIES-OLOMANA ROAD RACE:  July 26, 2008, Saturday, 7:00AM. The event is expected to have 100 athletes.  It will start at State Maintenance Yard on Kalanianaole  Hwy. to Old Kalanianaole Hwy. clockwise direction, to end at State Maintenance Yard in multiple loops.   TANTALUS TIME TRIAL 4.5 MILES:  July 27, 2008, Sunday, 7:00AM. The event is expected to have 100 athletes.  It will start at Makiki Pumping Station up Tantalus Dr., all the way to the top.  KAKAAKO CRITERIUM:  July 27, 2008, Sunday, 3:00PM. The event is expected to have 100 athletes.  It will start at Mother Waldron Park at Pohukaina St., to South St., to Halekauwila St., to Cooke St., and finish at the park at Pohukaina St., in multiple loops.  Contact: Raul Torres De Sa 223-2622, Fax:  737-8985  For more info,  visit their website:   http://www.bocahawaii.com/  Online registration:  http://www.active.com/

 

August 2, 2008 Saturday
9:00AM Starts
10:00AM Ends

NAMI-HAWAII WALK sponsored by National Alliance on Mental Illness.  The event is expected to have 500 walkers and 10+ vehicles.  It will start at Skygate on the grounds of Honolulu Hale at King St., to Alapai St., to Beretania St., to Bishop St., to King St., to end at skygate (course is along the sidewalk/parking areas and two (2) curb lanes).  Contact:  G.M. Durant 591-1297 or Diane & Nelson Fujio 232-7614/722-6771.  E-mail:  hularabbit@hawaii.rr.com or namihawaii@hawaiiantel.net 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8390.