ROAD WORK WEEKLY REPORT

 

Scheduled construction for week beginning March 16, 2008, for the Department of Design & Construction, Civil Division (Construction Management Branch), & Wastewater Division (Construction Management Branch).  Roadwork is normally done between the hours of 8:30 AM & 3:30 PM unless otherwise noted. 

 

***Motorists should anticipate intermittent lane closures when traversing through the area.

 

AIEA

 

Newtown Neighborhood Kaahele Street Improvements, Vicinity of Komo Mai Drive to Moanalua Road:

 

Work includes adding left turn pockets, pavement markings, and signs.  Change order work has been completed.  Extra work will be added.

 

            (Estimated completion date, February 2008)

             

Reconstruction of Concrete Sidewalks Halawa Area:

 

Work includes:  removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting and removal of tree roots where the roots have damaged the areas; installing root barriers where required; and adjustment of utility boxes to new sidewalk grades.

 

            (Estimated completion date, August 2008)

           

 

HAWAII KAI

 

CONSTRUCTION SUSPENDED

Reconstruction of Concrete Sidewalks, Kawaihae Street Area, Hawaii Kai:

Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the

areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

 

(Estimated completion date, February 2008)

 

HONOLULU

 

Curb Ramps at Various Locations, FY 2004(3) Kapiolani Boulevard & Paani Street, Kapiolani Boulevard & Wiliwili Street, Kapiolani Boulevard & Pumehana Street, Kaaha Street & University Avenue, Kalakaua Avenue & Young Street, Kalakaua Avenue & South King Street, Kalakaua Avenue & Philip Street, Kalakaua Avenue & South Beretania Street, Pensacola Street & Nehoa Street, Pensacola Street & Karratti Lane, Pensacola Street & Davenport Street, Pensacola Street & Hassinger Street, Pensacola Street & Kinau Street, Pensacola Street & South Beretania Street, Pensacola Street & Young Street, Pensacola Street & Alohi Way, Pensacola Street & Elm Street, Pensacola Street & Rycroft Street, Pensacola Street & Hoolai Street, Pensacola Street & Kamaile Street:

 

Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers.  Upgrade the traffic signal systems.

 

            (Estimated completion date, March 2008)

           

 

Curb Ramps at Various Locations, FY 2003(3) Alexander Street/South Beretania Street, Isenberg Street/ South Beretania Street, Kaheka Street/Kanunu Street, Kaheka Street/Makaloa Street, Kalauokalani Wy./Makaloa Street, Punahou Street/S. King Street, S. Beretania Street/Keeaumoku Street/Piikoi Street, Kinua Street/Victoria Street, South Beretania Street/Pensacola Street/Victoria Street, South Beretania Street/Victoria Street, S. Beretania Street/Ward Ave., Coyne Street/University Ave., Dole Street/East-West Rd., Dole Street/University Avenue, Kahuna Lane/South King Street, University Avenue/Varsity Place, and Pawaina Street/Paumaka Place:

 

Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

 

            (Estimated completion date, November 2007)

           

 

Curb Ramps at Various Locations, FY 2005(3) Hausten Street/South King Street, Kalakaua Avenue/Kapiolani Boulevard, Hoonanea Street/ Metcalf Street, Campus Road/Metcalf Street/University Avenue, Waialae Avenue/Wihelmina Rise/ 12th Avenue/Alohea Avenue, Alohea Avenue/Wela Street, Alohea Avenue/Edna Street, Mokihana Street/Mooheau Avenue, Francis Street/Upper Street, George Street/Upper Street, Hayden Street/Upper Street, Date Street/Kamoku Street/Kapiolani Boulevard, Young Street/Kaheka Street, 14th Avenue (A)/Waialae Avenue, 14th Avenue (B)/Waialae Avenue, and Elizabeth Street/Waialae Avenue:

 

Construct new curb ramps, sidewalks and AC transition.  Install pavement striping, markings and markers, upgrade traffic signal system.

 

            (Estimated completion date, March 2008)

             

Fort Street Mall & Hotel Street Sewer Replacement/Rehabilitation:

 

Sewer line replacement and CIPP work along Hotel Street between Bethel Street and Bishop Street.

           

            (Estimated completion date, December 2006)

             

Nuuanu Stream Emergency Repairs Puiwa Road, Honolulu:

 

Replace 250 feet of existing channel concrete floor and slope lining damaged by heavy rains and match pre-damage conditions.

 

            (Estimated completion date, February 2008)

             

Rehabilitation of Streets, Unit 5A, Beretania Street from N. King Street to Alapai Street:

 

Paving complete, adjust existing manhole frame and covers Alakea Street to North King Street, traffic loop detectors installation from Alakea Street to Nuuanu Avenue, roadway permanent striping from Alakea Street to North King Street.

 

(Estimated completion date, April 2008)

 

SUSPENDED ~ AWAITING PLANS

Rehabilitation of Streets, Unit 10 Street Louis Drive, Dole Street, Frank Street, Eugene Place, Alphonse Place, Robert Place:

 

Awaiting plans and owners permission to reconstruct concrete driveway.

 

            (Estimated completion date PENDING DESIGN)

             

Rehabilitation of Various Streets on Oahu Campbell Avenue from Kapahulu Avenue to Collins Street, Diamond Head Road from Trousseau Street to Makapuu Avenue, 4th Avenue from Waialae Avenue to Harding Avenue, Onipaa Street, Waimanu Avenue:

 

            (Estimated completion date, April 21, 2008)

            

Rehabilitation of Various Streets, Unit 43 Keeaumoku Street between Kapiolani Boulevard to Kinau Street; Rycroft Street from Kaheka Street to Sheridan; Sheridan Street between Kapiolani Boulevard to South King Street; South Street from Ala Moana Boulevard to South King Street; University Avenue between Coyne Street to Hihiwai Street:

 

Reconstruction of concrete curbs and gutters, and new bus pads.  Reconstruction and resurfacing of asphalt pavements.  Adjusting manhole to finish grade, installation of vehicle loop detectors, and permanent pavement markings.  Paving of Keeaumoku Street, Rycroft Street and Sheridan Street complete; installing pavement markings and loop detectors; adjusting manhole to grade.  Night paving of University Avenue complete and will be switching to daytime paving February 25, 2008.  Night paving of South Street on-going; limits to be extended up to Beretania Street.

 

            (Estimated completion date, April 2008)

             

Rehabilitation of Streets, Unit 49 Alewa Drive:

 

Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street: Work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

 

            (Estimated completion date, October 2008)

          

Rehabilitation of Street, Unit 38 Kilauea Avenue from Hunakai Street (Mauka of H-1) to 18th Avenue

 

The work includes the reconstruction and resurfacing of the above street; construction of concrete bus pads; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

 

            (Estimated completion date, January 2009)

             

Resurfacing of a Portion of Dillingham Boulevard, Waiakamilo Road to Middle Street:

 

Resurfacing, adjustment of utilities to grade and replacement loop detectors complete.  Installation of pavement markings requiring intermittent closures.

 

            (Estimated completion date, February 2008)

            

Sand Island Basin Miscellaneous Sewer Rehabilitation:

 

Continue replacement of sewer manhole frame and covers and manhole rehabilitation in various locations.  Rehabilitation of the Ward Avenue (between Kinau Street and South Beretania Street) sewer tunnel near completion.  Sand Island Access Road sewerline, Ala Moana Park sewerline, Moanalua sewerline and Nuuanu sewerline are forthcoming.

 

            (Estimated completion date, March 2008)

             

KAILUA

 

Ilimalia Loop/Mokapu Boulevard Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP) and manhole rehabilitation within Ilimalia Loop and Mokapu Boulevard.

 

            (Estimated completion date, June 2008)

      

 

Maunawili Bridge 2 Over Kamakalepo Stream, Bridge No. 444:

KAI Hawaii redesign new guard rail posts based on conflict with existing Hawaiian Telcom and HECO conduit.  Force account work:  guard rail redesign (PCD No. 5)

           

            (Estimated completion date, November 2007)

             

SUSPENDED ~ AWAITING BRIDGE JOINT DETAILS

Rehabilitation of Streets, Unit 42 Kainehe Street (Kihapai Street to Kailua Road) and Hamakua Drive (Kailua Road to Keolu Drive):

 

Paving, traffic signal upgrades, adjustment utility manholes frames and covers to grade, vehicle detector loops and pavement markings complete.  Installation of, traffic signs, bridge deck joints and deficiency require intermittent lane closures and punchlist.

 

            (Estimated completion date, November 2007)

        

Saint Louis Heights Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

 

            (Estimated completion date, January 2009)

           


KANEOHE  

 

Kawa Ditch Improvements - Nakumanu Place & Nakuluai Street, Kaneohe:

 

Removal existing trapezoidal concrete drain channel lining and reconstruction of new concrete rectangular channel.

 

            (Estimated completion date, November 2007)

             

KAPOLEI

 

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):

 

Clearing, grubbing and mass grading for construction of new 6-lane wide roadway with bike lane, raised median strips, sewer, water, drainage, street lighting and traffic signal systems, fences, sidewalks, curbs, gutters and subdrains, irrigation and landscaping, pavement markings and traffic signs.  Installation of erosion controls and dust fences throughout the project.

 

            (Estimated completion date March 2009)

          

MANOA

 

Rehabilitation of Streets, Unit 50 Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end):

 

Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings.

 

            (Estimated completion date, November 2008)

      

MILILANI

 

Reconstruction of Concrete Sidewalks, Mililani Area, Fiscal Year 2005-2006:

Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the

areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

 

(Estimated completion date, September 2008)

 

 PEARL CITY

 

Localized Rehabilitation of Streets, Phase 2, Various Streets (Manana & Momilani):

 

Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

 

            (Estimated completion date, March 2008)

 

REMAINING WORK TEMPORARILY SUSPENDED

Reconstruction of Concrete Sidewalks, Moanalua Road and Kaahumanu Street:

 

Reconstruct sidewalks, driveways, curbs, gutters and AC pavement.  Adjust utility boxes to new

sidewalk grade.  Tree trimming, root pruning, installing root barriers and removal of trees where required.

 

Work substantially completed on November 1, 2007. Contractor needs to complete internal punchlist items.

 

            (Estimated completion date, January 2008)

 

Saint Louis Heights Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

 

            (Estimated completion date, January 2009)

 

SALT LAKE

 

Bridge Rehabilitation, Salt Lake Boulevard Bridge Over Halawa Stream:

 

Repair cracks at bridge abutments and deck.  Provide concrete in-fill and reinforcing at spalled areas on bridge girders.  Strengthen girders with reinforce fabric material.

 

            (Estimated completion date, December 2008)

 

WAIPAHU

 

Localized Rehabilitation of Streets, Phase 2, Various Streets (Waipio, Crestview, Seaview):

 

Work includes cold planing; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas; adjustment of utility manhole frame and covers; installation of pavement markings; and locating existing manholes, valve boxes, monuments, etc.

 

            (Estimated completion date, March 2008)

 

Waikele Road Improvements, FY 2004-2005:

 

Work includes widening of Waikele Road and addition of curb and sidewalk fronting Waipahu Intermediate School, from Farrington Highway to Waipahu Flood Control Channel; adjustment of manholes, and boxes on the roadway being widened.  Final Inspection May 29, 2007.

 

(Estimated completion date, August 2007)

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8390.