CONSTRUCTION WEEKLY REPORT

 

Scheduled construction for week beginning March 23, 2009 for the Department of Design & Construction, Civil Division (Construction Management Branch), & Wastewater Division (Construction Management Branch).  Roadwork is normally done between the hours of 8:30 AM & 3:30 PM unless otherwise noted. 

 

***Motorists should anticipate intermittent lane closures when traversing through the area.

 

AIEA

 

Kaamilo Ditch Repair

 

Work includes:  demolishing and removing existing rock walls, trees; constructing new reinforced concrete channel; installing new 4-0 chain link fence; providing reinforced concrete jacket for existing 8-inch sewer.

 

            (Estimated completion date, May 2009)

           

 

HALAWA

 

Aliipoe Ditch Reconstruction Halawa Heights, Lalawai Drive and Kahema Place area:

Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18 drain pipes.  Install new chain link fence.

 

            (Estimated completion date, March 2009)

           

 

HAUULA

 

Curb Ramps at Various Locations, FY 2007 Kawaihemo Pl./Kawaipuna St.:

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

HAWAII KAI

 

Curb Ramps at Various Locations, FY 2006 Koamano Rd./Lunalilo Home Rd., Kalanipuu St./Lunalilo Home Rd., Waioli St./Hawaii Kai Dr., Hawaii Kai Dr./Lunalilo Home Rd.:

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons, traffic signal pull boxes and vehicle detector loops.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Curb Ramps at Various Locations, FY 2007 Lunalilo Home Rd. (Koko Head Elementary School Driveway):

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

CONSTRUCTION SUSPENDED

Reconstruction of Concrete Sidewalks, Kawaihae Street Area, Hawaii Kai:

Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; trimming of trees and cutting, removal of tree roots where the roots have damaged the

areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

 

(Estimated completion date, February 2008)

 

HONOLULU

 

Curb Ramps at Various Locations, FY 2006 Mapu Ln./Liliha St., University Ave./S. King St., Kaimuki Ave. Mid Block:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons and traffic signal pull boxes.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Curb Ramps at Various Locations, FY 2007 Waiakamilo Rd. between Moonui St. & McNeil St., Momolio St./N. School St., Aipaako St./Kuakini St., Ekekela Pl./Liliha St., Ekekela Pl./Keolewa Pl., Auahi St./South St., Hinano St./Leahi Ave., Ahe St. between Ahe Pl. & Kiwaila St., East Hind Dr./Papai St., East Hind Dr./Opihi St., East Hind Dr./Nehu Pl., East Hind Dr./Limu Pl., Kiholo St./West Hind Dr.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Curb Ramps at Various Locations, FY 2008(A) Haupu Pl./N. School St., 2476 N. School St., Allder St./S. King St., Queen St. Midblock, and Mooheau St./Paliuli St.:

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, May 2009)

           

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G and 1I:

New sewer line and manhole installation on Liliha Street (between Maui Street and Hawaii Street), Kuakini Street (between Nuuanu Avenue and Pali Highway).  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

           

(Estimated completion date, March 2009)

           

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1E:

 

New sewer line and manhole installation on Vineyard Blvd., Malanai Lane, School Street and Stillman Lane.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

           

(Estimated completion date, February 2009)

           

 

Kapiolani Area Revised Sewer System Improvements:

 

New sewer line, CIPP lining, and manhole installation on Kalauokalani, Kona Street, Atkinson Drive, and Ala Moana Blvd.  Sewerwork is ongoing on Kalauokalani.  One lane will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

 

            (Estimated completion date, March 2009)

           

 

Nuhelewai Stream Improvements

Project includes:  demolishing and removing existing rock walls and trees; constructing new concrete channels, retaining walls and grouted rubble paved work; installing 6-foot-high chain link fence; and installing permanent erosion control.

 

            (Estimated completion date, April 2009)

           

 

Peterson Lane and Pua Lane Sewer Rehabilitation:

 

New sewer line and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Sewerwork is ongoing on Pua Lane.  Repaving of King, Peterson and Pua lane to follow after sewer work is complete.  Pua Lane One lane in mauka bound direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

 

            (Estimated completion date, March 2009)

           

 

CONSTRUCTION SUSPENDED ~ REVISING CURB AND PAVING PLAN

Reconstruction of Lusitana Street From Pauoa Avenue to Iolani Avenue

The work includes the reconstruction and resurfacing of the above street; construction of concrete bus landings; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

 

            (Estimated completion date, September 2009)

         

 

Rehabilitation of Various Streets on Oahu:  Road work on Pauoa Avenue will resume on March 23, 2009.  Permits from the State DOT is being obtained for work under the Pali Highway.  Work will commence from Lusitana headed towards Nuuanu Avenue.

 

            (Estimated completion date, December 2008)

           

 

Rehabilitation of Street, Unit 38 Kilauea Avenue from Hunakai Street (Mauka of H-1) to 18th Avenue

 

The work includes the reconstruction and resurfacing of the above street; construction of concrete bus pads; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

 

            (Estimated completion date, May 2009)

           

 

Rehabilitation of Streets, Unit 49 Alewa Drive:   Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street: Work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

 

            (Estimated completion date, May 2009)

           

 

Saint Louis Heights Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

 

            (Estimated completion date, December 2009)

           

 

Kuliouou Sewer Rehabilitation:

Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.

           

            (Estimated completion date, April 2009)

           

 

Wilhelmina Rise Sewer Rehabilitation

 

Installation of cured in place pipe (CIPP), lateral rehabilitation, and replacement of sewer lines by open trench.

 

(Est Completion date Nov. 2010)

           

 

KAILUA

 

Curb Ramps at Various Locations, FY 2006 Lunaai Pl./Lunaai St., Lunaanela St./Lunaai St., Lunaanela St./Lunaanela St., Lunahelu St,/Lunaanela St., Lunaai St./Lunahelu St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Curb Ramps at Various Locations, FY 2007 Paopua Lp./Wanaao Rd., Paopua Lp./Paopua Pl., Pamaele St./Paopua Lp., Paopua Lp./Wanaao Rd./Palawiki St., Akumu St. (WWS driveway), Akamai St./Akumu St.:

 

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Maunawili Bridge 2 Over Kamakalepo Stream, Bridge No. 444:

Guard and bicycle rail installation problem:  waiting for Kaikor to address problem of misalignment and over drilled holes in guard & bicycle rails.

           

            (Estimated completion date, June 2009)

           

 

SUSPENDED ~ AWAITING BRIDGE JOINT DETAILS

Rehabilitation of Streets, Unit 42 Kainehe Street (Kihapai Street to Kailua Road) and Hamakua Drive (Kailua Road to Keolu Drive):

 

Paving, traffic signal upgrades, adjustment utility manholes frames and covers to grade, vehicle detector loops and pavement markings complete.  Installation of, traffic signs, bridge deck joints and deficiency require intermittent lane closures and punchlist.

 

            (Estimated completion date, November 2007)

           

 

Rehabilitation of Streets, Unit 46 Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):  Notice to Proceed March 9, 2009.

 

Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings.

 

            (Estimated completion date, December 2008)

           

 

Kailua Road Sewers Improvement District No. 276:

 

Installation of new sewer line along Kailua Road between Hahani Street and Aoloa Road.

 

            (Estimated completion date, April 2008)

           

 

Wanaao Road/Keolu Drive Reconstructed Sewer:

 

Installation of new sewer line along Keolu Dr (Nanialii St. to Wanaao Rd) and Wanaao Rd. (Keolu Dr. to Auwinala Rd).

 

            (Estimated completion date, April 2010)

           

 

Kalaheo Avenue/Mokapu Road/Aikahi Loop Sewer Rehabilitation

            (Estimated completion date, Dec 2009)

           

 

KANEOHE  

 

Curb Ramps at Various Locations, FY 2006 Malulani St./Mimo Pl., Miha St./Malulani St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Curb Ramps at Various Locations, FY 2008(A) 46-270 Kahuhipa St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, May 2009)

           

 

Guardrail Improvements - FY2006

(4 site locations:  2 sites in Kapolei/Makakilo on Farrington Hwy, 2 sites in Kaneohe on Kamehameha Hwy at Heeia Kea and Lilipuna Road)

Lilipuna Road site: Work completed.  Pre-final inspection to be scheduled.

Heeia Kea site:  Work completed.  Pre-final inspection to be scheduled.

 

 

Kaneohe Bay Drive Trunk Sewer Reconstruction

Installation of new sewer lines, new manholes, and cured in place pipe (CIPP).  Work will occur on Kaneohe Bay Drive between Mokapu Road and Kuono Place, Kaimalu Place and Way, Ikeanani Drive, and Kuakoa Place.

 

            (Estimated completion date Dec 2010)

             

 

KAPOLEI

 

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):

Clearing, grubbing and mass grading for construction of new 6-lane wide roadway with bike lane, raised median strips, sewer, water, drainage, street lighting and traffic signal systems, fences, sidewalks, curbs, gutters and subdrains, irrigation and landscaping, pavement markings and traffic signs.  Installation of erosion controls and dust fences throughout the project.

 

            (Estimated completion date April 2009)

           

 

Ewa Villages, Extension of Kapolei Parkway, Phase 8C (Renton Road to Kolowaka Street)

Work includes Civil, Structural, Electrical and Landscape work to complete the extension of Kapolei Parkway from Renton Road to Kolowaka Street.

 

            (Estimated completion date, May 2009)

           

 

Guardrail Improvements - FY2006

(4 site locations:  2 sites in Kapolei/Makakilo on Farrington Hwy, 2 sites in Kaneohe on Kamehameha Hwy at Heeia Kea and Lilipuna Road)

2 sites at Kapolei/Makakilo:  Work completed.  Pre-final inspection to be scheduled.

 

 

Renton Road Sewer and Manhole Rehabilitation

 

Trenching across Fort Barrette Road at Roosevelt Avenue starting February 17, 2009.  One lane of traffic will be open during the trenching.  Steel plates will be put down after the trenching to allow normal traffic movement.  Two months later the contractor will restore the trench and repave.  Total work duration in the area will be from February 17, 2009 to April 17, 2009.

 

URS Corporation

 

MAKAKILO

 

Curb Ramps at Various Locations, FY 2007 Anipeahi St./Anipeahi Pl./Ualahei St., Anipeahi St./Auwaea St.:

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Curb Ramps at Various Locations, FY 2008(A) Makakilo Dr./Nohohale St., Makakilo Dr./Newa St., and Aoloko St./Makakilo Dr.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, May 2009)

           

 

MANOA

Rehabilitation of Streets, Unit 50 Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end):

 

Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings.

 

            (Estimated completion date, May 2009)

           

 

University Avenue/Maile Way Retaining Wall Repair

 

Demolish and reconstruct existing retaining wall including new railings.  Replace affected sidewalks, curbs, gutters and asphalt pavement.  Construct new wheelchair ramps, install new crosswalks, replace street markings, signs and traffic signals. Adjust utility frames and covers; manhole frames and covers; and utility boxes to new finish grade.

 

            (Estimated completion date, March 2009)

           

 

MILILANI  

 

Curb Ramps at Various Locations, FY 2006 Kukolu St./Hokuula Lp./Kipapa Dr., Hokuula Lp./Kipapa Dr., Ia Pl./Kipapa Dr., Naholoholo St./Kipapa Dr., Wailoa Lp./Kanamee St./Kipapa Dr., Wailoa Lp./Naholoholo St./Kipapa Dr.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

Curb Ramps at Various Locations, FY 2008(A) Hakupokano Lp./Kaloapau St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, May 2009)

           

 

NIU VALLEY

 

Curb Ramps at Various Locations, FY 2006 Mahimahi St./Halemaumau St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

NUUANU

 

Seismic Retrofit Of City Bridges, Pelekane Drive Bridge Over Nuuanu Stream (Bridge No. 267)

 

Work involves installation of concrete shear keys, dowels for shear keys and girder strengthening for Pelekane Drive bridge.  Bridge repairs will be provided for the spalled areas along the girders, bottom of bridge slab and sidewalk, corroded rebars along the bridge bottom slab and shear cracks along the girders.  BMP measures and traffic controls will be installed.

 

            (Estimated completion date, November 2009)

           

 

PALOLO

 

Curb Ramps at Various Locations, FY 2006 Palolo Terrace/Palolo Ave., Wiliama Pl./Palolo Ave., Kanekopa Pl./Palolo Ave., Lamaloa Pl./Palolo Ave., Ahinahina Pl./Palolo Ave.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

 

PEARL CITY

 

Curb Ramps at Various Locations, FY 2007 Amokemoke St./Anapanapa St./Aumakua St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

 

REMAINING WORK TEMPORARILY SUSPENDED (Awaiting work schedule from Bonding Company)

Reconstruction of Concrete Sidewalks, Moanalua Road and Kaahumanu Street:

 

Reconstruct sidewalks, driveways, curbs, gutters and AC pavement.  Adjust utility boxes to new sidewalk grade.  Tree trimming, root pruning, installing root barriers and removal of trees where required.

Work substantially completed on November 1, 2007. Contractor needs to complete internal punchlist items.  Awaiting Surety Company contractor to complete the work.

           

 

SALT LAKE

 

Bridge Rehabilitation, Salt Lake Boulevard Bridge Over Halawa Stream:

 

Repair cracks at bridge abutments, girders and deck.  Provide concrete in-fill with reinforcing steel and install steel hangers and reinforce fabric material for strengthening the bridge girders.

Provide bridge deck restoration for installation of steel hanger assembly (Change Order work). 

 

All Contract work described above was substantially completed on January 28, 2009.  Pre-final inspection was conducted on February 19, 2009. Contractor completing cleanup work.

 

            (Estimated completion date, March 2009)

           

 

Curb Ramps at Various Locations, FY 2006 Miko St./Ukana St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

WAIHIAWA

 

Curb Ramps at Various Locations, FY 2006 Glen Ave./Kolekole Dr., Crest Ave./Glen Ave.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

WAIKIKI

 

Curb Ramps at Various Locations, FY 2006 Kuhio Ave./Kapahulu Ave.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, September 2009)

           

 

WAIMANALO

 

Hihimanu Street Sidewalk Improvement:

 

Installation of sidewalks; curbs and gutters along the makai side of Hihimanu Street.  Also work includes constructing curb inlets, headwalls, retaining walls, steel pipe railings; adjusting manhole covers and fire hydrants; and reconstructing driveway aprons.

 

            (Estimated completion date, February 2009)