| You are here: Main / Customer Services / Public Communications Division / 2009 / Enchanted Lake Sewer Bids Opened |
|
ENCHANTED Mayor Mufi Hannemann announced today that Jas W. Glover the apparent low bidder totaling $2.3 million to upgrade the Enchanted Lake Wastewater Pump Station. Jas W. Glover bid $2,303,508 to modify the facility. Modifications include the replacement of two pumps and discharge piping; replacement of the flow meter; replacement of the emergency generator; installation of an underground storage tank; construction of a new electrical building extension; modification of the existing SCADA system to meet the present ENV requirements; modification of the ventilation system; and replacement of the float control system. Construction is tentatively set to begin in October and take 720 calendars days to complete. The low bidder still must go through a procurement evaluation before the final contract is awarded. -30- Contact: Collins Lam, DDC Deputy Director, 768-8481 Markus Owens, ENV Public Communications Officer, 768-3454 |