ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning December 20, 2009, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

EWA

Ewa Villages Revitalization Project – Area “D” Drainage Improvements – Near Kapolei Parkway/Park Row/O.R.&L Railroad:  Installation of an 8’ x 6’ box drain and connection to existing 10’x 8’ box drain.

            (Estimated completion date, June 2010)

 

HALAWA

Aliipoe Ditch Reconstruction – Halawa Heights, Lalawai Drive and Kahema Place area:  Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18” drain pipes.  Install new chain link fence.

            (Estimated completion date, December 2009)

 

Rehabilitation of Secondary Streets at Pearl City – Ulune Street (Kahuapaani Street to Kulawea Street), Aiealani Place (Halawa Heights Road to end), Fernridge Place (Halawa Heights Road to end), Halawa Heights Road (Fernridge Place to Mauka end), Hele Mauna Place (Halawa Heights Road to end), Kaimakani Street (Moanalua Road to Ulune Street), Palaialii Place (Halawa Heights Road to end), and Palaialii Way (Palaialii Place to end):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, December 2009)

 

HAWAII KAI

Curb Ramps at Various Locations, FY 2008 (B) – Ainapo St./Kii St., Ainapo St./Kalopa St., Kalopa St./Kii St.,Kapulena Lp./Kii St., Kapulena Lp./Kii St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

Curb Ramps at Various Locations, FY 2006 – Koamano Rd./Lunalilo Home Rd., Kalanipuu St./Lunalilo Home Rd., Waioli St./Hawaii Kai Dr., Hawaii Kai Dr./Lunalilo Home Rd.:  Construction of new curb

ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons, traffic signal pull boxes and vehicle detector loops.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

Curb Ramps at Various Locations, FY 2007 – Lunalilo Home Rd. (Koko Head Elementray School Driveway):  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

HONOLULU

 

Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street: Work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

            (Estimated completion date, December 2009)

 

Amelia Street Relief Sewer – Amelia Street and adjoining School Street:  Installation of a new 16” sewer line underground along Amelia Street and portion of School Street at Amelia Street

            (Estimated completion date, July 2010)

 

Iolani Avenue Retaining Wall:  Construction of new CRM fence wall and installation of soil nail tie backs and reinforced shotecrete facing on retaining wall at 625 Iolani Avenue fronting Dole Community Garden. Restore A.C. sidewalk fronting new CRM wall.  Remove existing trees and re-plant new trees in Dole Community Garden.

            (Estimated completion date, May 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1A and 1C:  New sewer line and manhole installation on Mokauea Street, Kalani Street and Kino Street.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.            (Estimated completion date, December 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1B:  New sewer line and manhole installation on Kopke Street.  Kopke Street and Gulick Ave.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, December 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1D:  New sewer line and manhole installation on Captain Cook and  Lolena Street.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, December 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G:  New sewer line and manhole installation on Kuakini Street (between Nuuanu Avenue and Pali Highway) is ongoing.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, November 2010)

 

Kuliouou Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.  CIPP installation work at Summer Street and May Way.

            (Estimated completion date, December 2009)

 

Reconstruction of Lusitana Street – From Pauoa Avenue to Iolani Avenue  The work includes the reconstruction and resurfacing of the above street; construction of concrete bus landings; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

            (Estimated completion date, December 2009)

 

Curb Ramps at Various Locations, FY 2006 – Mapu Ln./Liliha St., University Ave./S. King St., Kaimuki Ave. Mid Block: Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons and traffic signal pull boxes.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program.  Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves. Re-grade swale and adjust DI to provide positive drainage into existing drain system. Upgrade concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams.  At the intersection of Ahua Street and Awaawaloa Street, abandon existing storm drain on Ahua Street and install new storm drain MH on upstream end of abandoned pipe.

            (Estimated completion date, December 2009)

 

Seismic Retrofit of City Bridges at Various Locations, FY 08 – Nehoa Street Bridge between Makiki St. and Anapuni St., and Lusitana Street Bridge between Ladd Ln. and Andrews Ln.:  Installation of concrete and steel shear keys.  Repair concrete spalls and cracks.  Construction of concrete back wall.

            (Estimated completion date, August 2010)

 

Emergency Repairs at Numana Road Bridge Over Kalihi Stream, Bridge No. 129:  Partial removal of existing metal decking, AC topping, AC curbs, and signage from the bridge roadway surface.  Installation of new metal decking, steel beams, steel bracing, concrete caps over abutments and center pier.  Restoring AC pavement, curbs, transitions, and installation of pavement markings and signage.  Bridge closed 24-hours from September 14, 2009 to November 13, 2009.

            (Estimated completion date, December 2009)

 

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, January 2010)

 

Rehabilitation of Various Streets on Oahu:  The southbound Pali Highway on-ramp will be closed intermittently between 8:30 a.m. – 3:30 p.m.  One lane of traffic in each direction will be maintained during the reconstruction work. Work on Pauoa Road is complete.  Work on Auwaiolimu Street is approximately 80% complete.  Completion is scheduled for June 26, 2009.  Work on Nehoa Street will commence immediately after the completion of Auwaiolimu Street.

            (Estimated completion date, December 2008)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:  New sewer line and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Sewerwork is ongoing on Pua Lane.  Repaving of King, Peterson and Pua lane to follow after sewer work is complete.  Pua Lane – One lane in mauka bound direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, December 2009)

 

Curb Ramps at Various Locations, FY 2008 (C) – Queen Emma Street (St. Andrew’s Priory Church Driveway), and Maunalei Avenue (Driveway between Pokole Street and Makapuu Avenue):  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

Piikoi Street Drainline Reconnection – Fronting Hawaiiki Tower Driveway.  The work includes excavation of the existing drain line, construction of a new drain manhole and the possible relocation of an existing 12-inch waterline.

            (Estimated completion date, February 2010)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights.  The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street.

            (Estimated completion date, December 2009)

 

Sewer rehabilitation on various streets on Wilhelmina Rise.  Installation of cured in place pipe (CIPP), lateral rehailitation, and replacement of sewer lines by open trench.

            (Estimated completion date November 2010)

 

KAILUA

Hele Ditch Emergency Repairs, Lekeona Street near Hele Street.  Demolish, remove and reconstruct existing concrete drainage ditch with chain link fence.  Grade and grass adjacent slope.

            (Estimated completion date, January 2010)

 

Rehabilitation of Streets, Unit 46 – Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):  Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings.

            (Estimated completion date, December 2009)

 

Kalaheo Avenue/Mokapu Road/Aikahi Loop Sewer Rehabilitation

            (Estimated completion date, December 2009)

 

 

Rehabilitation of Streets, Unit 63 – Kuukama Street (Kalaheo Ave. to End), Kuuala Street (Kuukama St. to end), Kuumele Place, Kuuhale Street (Kuuala St. to Kainalu Dr.), Kuuniu Street ( Kalaheo Ave. to Kuuala St.), Kuupua Street (Kuuala St. to Kainalu Dr.) and Kuuhoa Place:  Tentative Notice to Proceed of May 11, 2009.  Mill and resurface roadway surfaces; reconstruct speed humps; replace pavement markings; and adjust utility manholes to new pavement grade.

            (Estimated completion date, December 2009)

 

Curb Ramps at Various Locations, FY 2006 – Lunaai Pl./Lunaai St., Lunaanela St./Lunaai St., Lunaanela St./Lunaanela St., Lunahelu St,/Lunaanela St., Lunaai St./Lunahelu St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

Rehabilitation of Streets, Unit 52 – Keolu Drive (Kalanianaole Highway to Akahai Street); Keolu Drive (Akaakaawa Street to Wanaao Road):  Cold planing; resurfacing and reconstruction of asphalt concrete pavements (ACP); adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, sidewalks and Driveways; reconstruction of concrete catch basins; and construction of concrete and asphaltic concrete bus pads.

            (Estimated completion date, February 2010)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:  Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

            (Estimated completion date, April 2010)

 

KANEOHE

Emergency Landslide Remediation Adjacent to Burger King Kaneohe.  Grubb and grade the slope at the corner of Likelike Highway and Kamehameha Highway and constructed a two (2) tier retaining wall with segmental concrete blocks.  The work includes restoration of the access road, Burger Kings parking lot and landscape.

            (Estimated completion date December 2009)

 

Duncan Drive – Puahuula Place Relief Drain  Construction of a relief drainage system, removing existing drainage system and installing larger drain lines, three new inlets, a trench drain and new storm drain manholes.

            (Estimated completion date, March 2010)

 

Kaneohe Bay Drive Trunk Sewer Reconstruction:  Installation of new sewer lines, new manholes, and cured in place pipe (CIPP).  Work will occur on Kaneohe Bay Drive between Mokapu Road and Kuono Place, Kaimalu Place and Way, Ikeanani Drive, and Kuakoa Place.

            (Estimated completion date December 2010)

 

Lilipuna Road Storm Drainage Improvements:  Demolish and remove existing RCP pipe, grated inlet and CRM outlet.  Install new 24” RCP pipe, construct new inlet and outlet structures, construct new CRM retaining wall, and restore A.C. pavement.

            (Estimated completion date, December 2009)

 

Curb Ramps at Various Locations, FY 2006 – Malulani St./Mimo Pl., Miha St./Malulani St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

KAPOLEI

Ewa Villages, Extension of Kapolei Parkway, Phase 8C (Renton Road to Kolowaka Street)  Work includes Civil, Structural, Electrical and Landscape work to complete the extension of Kapolei Parkway from Renton Road to Kolowaka Street.

            (Estimated completion date, December 2009)

 

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):  One-year landscape maintenance period for street trees and grassing in progress.

            (Estimated completion date for landscape maintenance period, April 2010)

 

MANOA

Rehabilitation of Streets, Unit 50 – Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end):  Work includes  reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings.

            (Estimated completion date, December 2009)

 

Rehabilitation of Local Streets, Phase 1:  The contractor is working in three areas on Oahu.  Work is being done on Metcalf Avenue and vicinity in Manoa.  Work is also being done on Lanikaula St. and Kahaloa Dr. in upper Manoa Valley.  Work began in Lanikai on November 16th with Lapa Pl. and Poopoo Pl. being completed.

 

MILILANI

Curb Ramps at Various Locations, FY 2006 – Kukolu St./Hokuula Lp./Kipapa Dr., Hokuula Lp./Kipapa Dr., Ia Pl./Kipapa Dr., Naholoholo St./Kipapa Dr., Wailoa Lp./Kanamee St./Kipapa Dr., Wailoa Lp./Naholoholo St./Kipapa Dr.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

NIU VALLEY

Curb Ramps at Various Locations, FY 2006 – Mahimahi St./Halemaumau St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

Seismic Retrofit of City Bridges at Various Locations, FY 08 – Halemaumau Street Bridge:  Halemaumau St./Haleola St.  Installation of concrete shear keys and restrictor boots.  Repair concrete spalls and cracks.

            (Estimated completion date, August 2010)

 

Curb Ramps at Various Locations, FY 2008 (C) – Halemaumau Street/Haleola Street, Halemaumau Street/Kanau Street, Halemaumau Street/Kawaikui Street, Halemaumau Street/Pia Street:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

NUUANU

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, January 2010)

 

PALOLO

Curb Ramps at Various Locations, FY 2006 – Palolo Terrace/Palolo Ave., Wiliama Pl./Palolo Ave., Kanekopa Pl./Palolo Ave., Lamaloa Pl./Palolo Ave., Ahinahina Pl./Palolo Ave.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

PEARL CITY

Rehabilitation of Secondary Streets at Pearl City – Hoolaulea Street below Moanalua Road  (Waimano Home Road to Hoomoe Road), Nanakai Place (Nanakai Street to end), Nanakai Street (Waimano Home Road to Hoomalu Street), Puu Kipa Street ( Nanakai Street to Nanakai Street):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, December 2009)

 

Guardrail Improvements – FY2006 Phase II  Site C:  Komo Mai Drive – between Hoolaulea and Hoohulu Street:  Replace planter with new concrete sidewalk; install object markers; install standard metal guarail post & spacers.

            (Estimated start date, February 2010)

 

Manana Infrastructure Improvements, Phase VI – Connector Road (Kuala Street to Kuahaka Street)  Construct 60-foot wide roadway from Kuala Street to Kuahaka Street. The work includes, vector control; clearing, grubbing and grading; installation of new storm drain, Heco, Hawaiian Telcom, street light and traffic signal systems; concrete slab protection for existing sewer and water lines; grade adjustments in private lots; new noise and retaining walls, chain link fence and gates: reconstruction of existing drain, water and sewer MHs and valves to new finish grade; installation of curbs, gutters, sidewalks, driveways, curb ramps and sidewalk culverts; installation of irrigation system and landscape improvements; tree removal and pruning in private lots; road paving; pavement markings and markers and street signs.

            (Estimated completion date, December 2010)

 

 

Bridge Rehabilitation At Various Locations  Moanalua Road Bridge Over Waimalu Stream (Bridge No. 910)  Partial demolition and removal of existing curbs, gutters and sidewalks on bridge deck. Reconstruct curbs, gutters, sidewalk and A.C. pavement. Repair spalled, delaminated and hollow sounding areas in bridge soffit, abutments and pier. Repair bridge parapet, metal railing and expansion and cold joints.

            (Estimated completion date, June 2010)

 

Reconstruction of Concrete Sidewalks, Moanalua Road and Kaahumanu Street:  Reconstruct sidewalks, Driveways, curbs, gutters and AC pavement.  Adjust utility boxes to new sidewalk grade.  Tree trimming, root pruning, installing root barriers and removal of trees where required.  Work substantially completed on November 1, 2007.   Contractor needs to complete internal punchlist and warranty work.  Surety Company’s contractor anticipated to start work on November 20, 2009.

            (Estimated completion date, December 2009)

 

Localized Rehabilitation of Streets, Phase 4, Pearl City, Newtown, Royal Summit,  Pacific Palisades, Pearlridge, Aiea, Aiea Heights, Halawa Heights, and Halawa Valley.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, January 2010)

 

Waimalu Sewer Rehabilitation/Reconstruction Phase I:  Installation of new sewer lines/man holes and reconnection of existing sewer laterals along Hekaha, Kanuku, Lokowai, Lii-Ipo, Pahemo, and Olepe.

            (Estimated completion date, September 2010)

 

PEARLRIDGE

Rehabilitation of Secondary Streets at Pearl City – Kaonohi Street ( Kaonohi Place to entire loop), and Kaonohi Street (Kamehameha Highway to Moanalua Road):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, December 2009)

 

SALT LAKE

Curb Ramps at Various Locations, FY 2006 – Miko St./Ukana St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

WAIANAE

Guardrail Improvements – FY2006 Phase II  Site A:  Mailiili Stream – M3 Channel at Mailiilii Road and Lualualei Homestead Road:  Remove existing guardrails & concrete posts; install standard metal guardrail post & spacers.

            (Estimated completion date:  December 2009)

 

WAHIAWA

Curb Ramps at Various Locations, FY 2006 – Glen Ave./Kolekole Dr., Crest Ave./Glen Ave.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

WAIKIKI

Rehabilitation of Streets, Unit 62 – Ala Wai Boulevard between Kanekapolei Street and Kalakaua Avenue:  Reconstruct identified curbs, gutters, driveways and asphalt roadway.  Resurface asphalt roadways; install permanent pavement markings; restore vehicle loop detectors and raise manhole and valve covers to grade.  Anticipated start date of September 28, 2009; preliminary surveying to start August 19, 2009

            (Estimated completion date, March 2010)

 

Curb Ramps at Various Locations, FY 2006 – Kuhio Ave./Kapahulu Ave.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2009)

 

WAIPAHU

Emergency Repairs to Waipahu Street Arch Bridge Over Waikele Stream (Bridge No. 961)

GRP at south-west anchor wall, a.c pavement, install guardrails, install signage.

            (Estimated completion date December 2009)

 

Waipahu Street Retaining Wall Repair & 16th Avenue Boulder Basin Dam Wall Reconstruction:  Demolish and rebuild retaining wall, curb ramp, and portion of sidewalk adjacent to Waipahu Elementary School.  Awaiting staging area approval from DPR.  Tentative start of construction date set for October 23, 2009.

            (Estimated completion date February 2010)

 

Rehabilitation of Paiwa Street (Farrington Highway to Waipahu Street), Waipahu Street (Hianakiu Street to Kaupu Place), Makoa Street (Puia Street to end to end), Puia Street (Anonui Street to Eleu Street, and Heahea Street to deadend):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, December 2009)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

December 20, 2009 Sunday
7:00AM Starts
9:00AM Ends

HOMEWARD BOUND 5K RUN/WALK sponsored by Homeward Bound 5K Race Committee. The event is expected to have 200 runners.  It will start at Manoa Rec Center,  to Manoa Rd., to Pawaina St., to Pakanu Ave., to E Manoa Rd., to Oahu Ave., to Lowery Ave., to end at Manoa Rec center parking lot.  Contact: Tanna Fukuyama  E-mail: homewardbound5K@gmail.com  For more info visit their website: homewardbound5k.blogspot.com 

 

December 20, 2009 Sunday
2:00PM Starts
3:30PM Ends

MOANALUA VALLEY CHRISTMAS CARAVAN sponsored by Moanalua Valley Community Association. The event is expected to have 6 vehicles.  It will start at Moanalua Valley Neihborhood Park, to Ala Aolani St., to entrance of Moanalua Valley near the Golf Course and return to the Moanalua Valley Neighborhood Park.  Contact:  Matthew Young 722-3447, Fax:  531-8028

 

December 26, 2009 Saturday
5:00PM Starts
10:00PM Ends

EARLY CHRISTMAS CELEBRATION sponsored by Lighthouse Outreach Center. The event is expected to have 400+ participants.  The event will close Pupukahi St., from Farrington Hwy. to along the bend portion of Pupupuhi St.  Roadway is open for Local Traffic only.  Contact:  Pastor Joe Hunkin, Jr. 225-4589 Fax:  680-0823

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391.