You are here:  Main / Customer Services / Public Communications Division / 2009 / Road Work Weekly Report

ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning February 22, 2009, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Kaamilo Ditch Repair:  Work includes demolishing and removing existing rock walls, trees; constructing new reinforced concrete channel; installing new 4-0 chain link fence; providing reinforced concrete jacket for existing 8-inch sewer.

            (Estimated completion date, May 2009)

 

EWA

Ewa Villages, Extension of Kapolei Parkway, Phase 8C (Renton Road to Kolowaka Street)  Work includes Civil, Structural, Electrical and Landscape work to complete the extension of Kapolei Parkway from Renton Road to Kolowaka Street.

            (Estimated completion date, May 2009)

 

HALAWA

Aliipoe Ditch Reconstruction Halawa Heights, Lalawai Drive and Kahema Place area:  Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18 drain pipes.  Install new chain link fence.

            (Estimated completion date, March 2009)

 

HONOLULU

Rehabilitation of Alewa Drive from Wyllie Street to Hoomaikai Street: Work includes removal of existing asphalt concrete and Portland cement concrete pavements, roadway reconstruction with asphalt concrete pavement, reconstruction of existing asphalt concrete berms and concrete gutters, adjustment of utility manhole frames and covers, and installation of pavement markings, and other incidental related work.

            (Estimated completion date, February 2009)

 

Curb Ramps at Various Locations, FY 2008(A) Haupu Pl./N. School St., 2476 N. School St., Allder St./S. King St., Queen St. Midblock, and Mooheau St./Paliuli St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, May 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G and 1I:  New sewer line and manhole installation on Liliha Street (between Maui Street and Hawaii Street), Kuakini Street (between Nuuanu Avenue and Pali Highway).  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1E:  New sewer line and manhole installation on Vinyard Blvd., Malanai Lane, School Street and Stillman Lane.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, February 2009)

 

Kapiolani Area Revised Sewer System Improvements:  New sewer line, CIPP lining, and manhole installation on Kalauokalani, Kona Street, Atkinson Drive, and Ala Moana Blvd.  Sewerwork is ongoing on Kalauokalani.  One lane will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2009)

 

Rehabilitation of Street, Unit 38 Kilauea Avenue from Hunakai Street (Mauka of H-1) to 18th Avenue.  The work includes the reconstruction and resurfacing of the above street; construction of concrete bus pads; curb ramps and associated traffic signal improvements; reconstruction of curbs, gutters and driveways; installation of pavement markings, adjustment of utility covers to grade; tree trimming and root pruning.

            (Estimated completion date, February 2009)

 

Kuliouou Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.

            (Estimated completion date, February 2009)

 

Rehabilitation of Various Streets on Oahu:  Beginning February 9, 2009 resurfacing of Pauoa Road will commence.  Work is expected to begin at Nuuanu Avenue heading east on Pauoa Road.

            (Estimated completion date, February 2009)

 

Nuhelewai Stream Improvements:  Project includes demolishing and removing existing rock walls and trees; constructing new concrete channels, retaining walls and grouted rubble paved work; installing 6-foot-high chain link fence; and installing permanent erosion control.

            (Estimated completion date, February 2009)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and pipe bursting throughout Saint Louis Heights.

            (Estimated completion date, February 2009)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:  New sewer line and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Sewerwork is ongoing on Pua Lane.  Repaving of King, Peterson and Pua lane to follow after sewer work is complete.  Pua Lane One lane in mauka bound direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2009)

 

Sewer rehabilitation on various streets on Wilhelmina Rise.

(Estimated completion date November 2010)

 

KAILUA

Ilimalia Loop/Mokapu Boulevard Sewer Rehabilitation:  Installation of cured in place pipe (CIPP) and manhole rehabilitation within Ilimalia Loop and Mokapu Boulevard.

            (Estimated completion date, February 2009)

 

Rehabilitation of Streets, Unit 46 Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):  Notice to Proceed scheduled for Nov. 17, 2008.  Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings.

 

Kailua Road Sewers Improvement District No. 276:  Installation of new sewer line along Kailua Road between Hahani Street and Aoloa Road.

            (Estimated completion date, February 2009)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:  Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

            (Estimated completion date, February 2009)

 

KANEOHE

Curb Ramps at Various Locations, FY 2008(A) 46-270 Kahuhipa St.: Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, May 2009)

 

KAPOLEI

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):  Clearing, grubbing and mass grading for construction of new 6-lane wide roadway with bike lane, raised median strips, sewer, water, drainage, street lighting and traffic signal systems, fences, sidewalks, curbs, gutters and subdrains, irrigation and landscaping, pavement markings and traffic signs.  Installation of erosion controls and dust fences throughout the project.

            (Estimated completion date March 2009)

 

Renton Road Sewer and Manhole Rehabilitation: Trenching across Fort Barrette Road at Roosevelt Avenue.  One lane of traffic will be open during the trenching.  Steel plates will be put down after the trenching to allow normal traffic movement.  In March the contractor will restore the trench and repave.

            (Estimated completion date March 2009)

 

MAKAKILO

Bridge Rehabilitation Palahia Street Bridge over Awanui Stream repair spalling in bridge elements, replace deck expansion joints, construct new concrete approach slabs, reconstruct gutters, and repair settlements in sidewalk.

            (Estimated completion date, February 2009)

 

Curb Ramps at Various Locations, FY 2008(A) Makakilo Dr./Nohohale St., Makakilo Dr./Newa St., and Aoloko St./Makakilo Dr.: Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, May 2009)

 

MANOA

Rehabilitation of Streets, Unit 50 Kalawao Place (Kalawao St to end), Kalawao Street (Kahaloa Drive to private road), Kalehua Street (Kahaloa Dr to end), Kaloaluiki Street ( Lowrey Ave to Kalawao St), Kanu Street (Lowery Ave to Loi St), Loi Street (East Manoa Rd to Woodlawn Dr), Kahawai Street (Lowrey Ave to Huapala St), Woodlawn Drive (Lowrey Ave to Kahaloa St), Lowrey Avenue (Woodlawn Dr to Kalawao St), Kaaipu Avenue (Oahu Ave to end), Loomis Street (Mauka end to Makai end), Hiehie Street (Kaloaluiki St to end) and Vista Place (Lowrey Ave to end).  Work includes reconstruction and resurfacing of the above roadways; reconstruction of curbs, gutters, sidewalks and driveways; tree removal, pruning and trimming; installation of pavement markings

            (Estimated completion date, February 2009)

 

University Avenue/Maile Way Retaining Wall Repair:  Demolish and reconstruct existing retaining wall including new railings.  Replace affected sidewalks, curbs, gutters and asphalt pavement.  Construct new wheelchair ramps, install new crosswalks, replace street markings, signs and traffic signals. Adjust utility frames and covers; manhole frames and covers; and utility boxes to new finish grade.

            (Estimated completion date, February 2009)

 

MILILANI

Curb Ramps at Various Locations, FY 2008(A) Hakupokano Lp./Kaloapau St.: Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, May 2009)

 

NUUANU

Seismic Retrofit Of City Bridges, Pelekane Drive Bridge Over Nuuanu Stream (Bridge No. 267)

Work involves installation of concrete shear keys, dowels for shear keys and girder strengthening for Pelekane Drive bridge.  Bridge repairs will be provided for the spalled areas along the girders, bottom of bridge slab and sidewalk, corroded rebars along the bridge bottom slab and shear cracks along the girders.  BMP measures and traffic controls will be installed.

            (Estimated completion date, November 2009)

 

SALT LAKE

Bridge Rehabilitation, Salt Lake Boulevard Bridge Over Halawa Stream:  Repair cracks at bridge abutments and deck.  Provide concrete in-fill and reinforcing at spalled areas on bridge girders.  Strengthen girders with reinforce fabric material.

            (Estimated completion date, February 2009)

 

WAIMANALO

Hihmanu Street Sidewalk Improvement:  Installation of sidewalks; curbs and gutters along the makai side of Hihimanu Street.  Also work includes constructing curb inlets, headwalls, retaining walls, steel pipe railings; adjusting manhole covers and fire hydrants; and reconstructing driveway aprons.

            (Estimated completion date, February 2009)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

February 22, 2009 Sunday
7:00AM Starts
10:00AM Ends

MOKULEIA TIME TRIAL sponsored by Cambiamento d'Andaturo.  The event is expected to have 100 participants.  It will start at Waialua High School, to Farrington Hwy., turnaround at Camp Erdman, to end at Waialua High School.  Contact:  David Lum 429-9475, Fax:  839-2094, E-mail:  rhombus01@msn.com 

 

February 24, 2009 Tuesday
6:00PM Starts
10:00PM End
s

NUUANU MARDI GRAS STREET FESTIVAL sponsored by Honolulu Culture & Arts District Association. The event is expected to have 4,000+ participants.  Traffic will be diverted starting 3 pm for setup. The event will close NUUANU AVE., all traffic lanes/sidewalk areas, from Chaplain Ln to King St.  Contact:  Ed Korybski 538-2220, Fax:  842-1962, For more info, visit their website:  http//www.artsdistricthonlulu.com

 

February 28, 2009 Saturday
5:00PM Starts
10:30PM Ends

CHINATOWN CHASE sponsored by the Hawaii Theater Center.  The event is expected to have 300 participants.  The event will close 1) BETHEL ST., between Hotel and Chaplain Ln., 2) PAUAHI ST., between Fort St. Mall and Nuuanu Ave., all traffic lanes/sidewalk areas.  Contact:  Elaine Evans 791-1899 or Wade Kersey 391-1348, Fax:  528-0481

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8390.