You are here:  Main / Customer Services / Public Communications Division / 2010 / Road Work Weekly Report

March 19, 2010

 

ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning March 21, 2010, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

EWA

Ewa Villages Revitalization Project – Area “D” Drainage Improvements – Near Kapolei Parkway/Park Row/O.R.&L Railroad:  Installation of an 8’ x 6’ box drain and connection to existing 10’x 8’ box drain.

            (Estimated completion date, June 2010)

 

HALAWA

Aliipoe Ditch Reconstruction – Halawa Heights, Lalawai Drive and Kahema Place area:  Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18” drain pipes.  Install new chain link fence.

            (Estimated completion date, March 2010)

 

Rehabilitation of Secondary Streets at Pearl City – Ulune Street (Kahuapaani Street to Kulawea Street), Aiealani Place (Halawa Heights Road to end), Fernridge Place (Halawa Heights Road to end), Halawa Heights Road (Fernridge Place to Mauka end), Hele Mauna Place (Halawa Heights Road to end), Kaimakani Street (Moanalua Road to Ulune Street), Palaialii Place (Halawa Heights Road to end), and Palaialii Way (Palaialii Place to end):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, April 2010)

 

Localized Rehabilitation of Streets, Phase 4, Pearl City, Newtown, Royal Summit,  Pacific Palisades, Pearlridge, Aiea, Aiea Heights, Halawa Heights, and Halawa Valley.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated completion date, March 2010)

 

HAWAII KAI

Reconstruction of Concrete Sidewalks, Kawaihae Street Area, Hawaii Kai:  Work includes removal and reconstruction of damaged concrete sidewalk, curb and gutter areas; installing root barriers where required, and adjustment of utility boxes to new sidewalk grades, and other incidental related work.

            (Estimated completion date, March 2010)

 

Curb Ramps at Various Locations, FY 2006 – Koamano Rd./Lunalilo Home Rd., Kalanipuu St./Lunalilo Home Rd., Waioli St./Hawaii Kai Dr., Hawaii Kai Dr./Lunalilo Home Rd.:  Construction of new curb

ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons, traffic signal pull boxes and vehicle detector loops.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

HONOLULU

Amelia Street Relief Sewer – Amelia Street and adjoining School Street:  Installation of a new 16” sewer line underground along Amelia Street and portion of School Street at Amelia Street

            (Estimated completion date, July 2010)

 

Iolani Avenue Retaining Wall:  Construction of new CRM fence wall and installation of soil nail tie backs and reinforced shotecrete facing on retaining wall at 625 Iolani Avenue fronting Dole Community Garden. Restore A.C. sidewalk fronting new CRM wall.  Remove existing trees and re-plant new trees in Dole Community Garden.

            (Estimated completion date, June 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1A and 1C:  New sewer line and manhole installation on Mokauea Street, Kalani Street and Kino Street.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.            (Estimated completion date, March 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1B:  New sewer line and manhole installation on Kopke Street.  Kopke Street and Gulick Ave.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1D:  New sewer line and manhole installation on Captain Cook and  Lolena Street.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G:  New sewer line and manhole installation on Kuakini Street (between Nuuanu Avenue and Pali Highway) is ongoing.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, November 2010)

 

Kuliouou Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.  CIPP installation work at Summer Street and May Way.

            (Estimated completion date, March 2010)

 

Curb Ramps at Various Locations, FY 2006 – Mapu Ln./Liliha St., University Ave./S. King St., Kaimuki Ave. Mid Block: Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons and traffic signal pull boxes.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program.  Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves. Re-grade swale and adjust DI to provide positive drainage into existing drain system. Upgrade concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams.  At the intersection of Ahua Street and Awaawaloa Street, abandon existing storm drain on Ahua Street and install new storm drain MH on upstream end of abandoned pipe.

            (Estimated completion date, April 2010)

 

Rehabilitation of Various Streets on Oahu:  Work on Nehoa Street between Makiki St. and Punahou St. is scheduled to begin in March, 2010.  Work is currently being done on curb and gutter repair in the Kahala district. For the Local Rehabilitation of Streets, Phase 1:  Work is progressing in easterly portion of Lanikai.  In Manoa Valley, work is on-going in the central valley with two road crews.

            (Estimated completion date, March 2010)

 

Seismic Retrofit of City Bridges at Various Locations, FY 08 – Nehoa Street Bridge between Makiki St. and Anapuni St., and Lusitana Street Bridge between Ladd Ln. and Andrews Ln.:  Installation of concrete and steel shear keys.  Repair concrete spalls and cracks.  Construction of concrete back wall.

            (Estimated completion date, August 2010)

 

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, March 2010)

 

Rehabilitation of Secondary Streets at Kaimuki – Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue.  Excavating, reconstructing and resurfacing asphalt concrete pavements and base; reconstructing base at bus stops; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, May 2010)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:  New sewer line and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Sewerwork is ongoing on Pua Lane.  Repaving of King, Peterson and Pua lane to follow after sewer work is complete.  Pua Lane – One lane in mauka bound direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, March 2010)

 

Curb Ramps at Various Locations, FY 2008 (C) – Queen Emma Street (St. Andrew’s Priory Church Driveway), and Maunalei Avenue (Driveway between Pokole Street and Makapuu Avenue):  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights.  The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street.

            (Estimated completion date, March 2010)

 

Sewer rehabilitation on various streets on Wilhelmina Rise.  Installation of cured in place pipe (CIPP), lateral rehailitation, and replacement of sewer lines by open trench.

            (Estimated completion date November 2010)

 

KAILUA

Rehabilitation of Streets, Unit 46 – Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):  Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings.

            (Estimated completion date, March 2010)

 

Kalaheo Avenue/Mokapu Road/Aikahi Loop Sewer Rehabilitation

            (Estimated completion date, March 2010)

 

Rehabilitation of Streets, Unit 63 – Kuukama Street (Kalaheo Ave. to End), Kuuala Street (Kuukama St. to end), Kuumele Place, Kuuhale Street (Kuuala St. to Kainalu Dr.), Kuuniu Street ( Kalaheo Ave. to Kuuala St.), Kuupua Street (Kuuala St. to Kainalu Dr.) and Kuuhoa Place.  Project substantially completed. Contractor addressing punchlist items.

            (Estimated completion date, March 2010)

 

Curb Ramps at Various Locations, FY 2006 – Lunaai Pl./Lunaai St., Lunaanela St./Lunaai St., Lunaanela St./Lunaanela St., Lunahelu St,/Lunaanela St., Lunaai St./Lunahelu St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

Rehabilitation of Streets, Unit 52 – Keolu Drive (Kalanianaole Highway to Akahai Street); Keolu Drive (Akaakaawa Street to Wanaao Road):  Cold planing; resurfacing and reconstruction of asphalt concrete pavements (ACP); adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, sidewalks and Driveways; reconstruction of concrete catch basins; and construction of concrete and asphaltic concrete bus pads.

            (Estimated completion date, March 2010)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:  Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

            (Estimated completion date, April 2010)

 

KANEOHE

Emergency Landslide Remediation Adjacent to Burger King Kaneohe.  Grubb and grade the slope at the corner of Likelike Highway and Kamehameha Highway and constructed a two (2) tier retaining wall with segmental concrete blocks.  The work includes restoration of the access road, Burger Kings parking lot and landscape.

            (Estimated completion date March 2010)

 

Duncan Drive – Puahuula Place Relief Drain  Construction of a relief drainage system, removing existing drainage system and installing larger drain lines, three new inlets, a trench drain and new storm drain manholes.

            (Estimated completion date, March 2010)

 

Kaneohe Bay Drive Trunk Sewer Reconstruction:  Installation of new sewer lines, new manholes, and cured in place pipe (CIPP).  Work will occur on Kaneohe Bay Drive between Mokapu Road and Kuono Place, Kaimalu Place and Way, Ikeanani Drive, and Kuakoa Place.

            (Estimated completion date December 2010)

 

Lilipuna Road Storm Drainage Improvements:  Demolish and remove existing RCP pipe, grated inlet and CRM outlet.  Install new 24” RCP pipe, construct new inlet and outlet structures, construct new CRM retaining wall, and restore A.C. pavement.

            (Estimated completion date, March 2010)

 

Curb Ramps at Various Locations, FY 2006 – Malulani St./Mimo Pl., Miha St./Malulani St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

KAPOLEI

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):  One-year landscape maintenance period for street trees and grassing in progress.

            (Estimated completion date April 2010)

 

MILILANI

Curb Ramps at Various Locations, FY 2006 – Kukolu St./Hokuula Lp./Kipapa Dr., Hokuula Lp./Kipapa Dr., Ia Pl./Kipapa Dr., Naholoholo St./Kipapa Dr., Wailoa Lp./Kanamee St./Kipapa Dr., Wailoa Lp./Naholoholo St./Kipapa Dr.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

NIU VALLEY

Curb Ramps at Various Locations, FY 2006 – Mahimahi St./Halemaumau St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, February 2010)

 

Seismic Retrofit of City Bridges at Various Locations, FY 08 – Halemaumau Street Bridge:  Halemaumau St./Haleola St.  Installation of concrete shear keys and restrictor boots.  Repair concrete spalls and cracks.

            (Estimated completion date, August 2010)

 

Curb Ramps at Various Locations, FY 2008 (C) – Halemaumau Street/Haleola Street, Halemaumau Street/Kanau Street, Halemaumau Street/Kawaikui Street, Halemaumau Street/Pia Street:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

NUUANU

Drainage Outfall Improvements for Waolani Stream at Kawananakoa Place – 105-D Kawananakoa Place:  Construction of new SDMH and installation a check valve over the existing 18” RCP drain pipe.

            (Estimated completion date, July 2010)

 

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, March 2010)

 

PALOLO

Curb Ramps at Various Locations, FY 2006 – Palolo Terrace/Palolo Ave., Wiliama Pl./Palolo Ave., Kanekopa Pl./Palolo Ave., Lamaloa Pl./Palolo Ave., Ahinahina Pl./Palolo Ave.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

Rehabilitation of Secondary Streets at Kaimuki – Palolo Avenue, Waialae Avenue to 10th Avenue in Palolo Valley.  Excavating, reconstructing and resurfacing asphalt concrete pavements and base; reconstructing base at bus stops; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, May 2010)

 

PEARL CITY

Rehabilitation of Secondary Streets at Pearl City – Hoolaulea Street below Moanalua Road  (Waimano Home Road to Hoomoe Road), Nanakai Place (Nanakai Street to end), Nanakai Street (Waimano Home Road to Hoomalu Street), Puu Kipa Street ( Nanakai Street to Nanakai Street):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, March 2010)

 

Guardrail Improvements – FY2006 Phase II  Site C:  Komo Mai Drive – between Hoolaulea and Hoohulu Street:  Replace planter with new concrete sidewalk; install object markers; install standard metal guarail post & spacers.

            (Estimated start date, March 2010)

 

Manana Infrastructure Improvements, Phase VI – Connector Road (Kuala Street to Kuahaka Street)  Construct 60-foot wide roadway from Kuala Street to Kuahaka Street. The work includes, vector control; clearing, grubbing and grading; installation of new storm drain, Heco, Hawaiian Telcom, street light and traffic signal systems; concrete slab protection for existing sewer and water lines; grade adjustments in private lots; new noise and retaining walls, chain link fence and gates: reconstruction of existing drain, water and sewer MHs and valves to new finish grade; installation of curbs, gutters, sidewalks, driveways, curb ramps and sidewalk culverts; installation of irrigation system and landscape improvements; tree removal and pruning in private lots; road paving; pavement markings and markers and street signs.

            (Estimated completion date, December 2010)

 

Bridge Rehabilitation At Various Locations  Moanalua Road Bridge Over Waimalu Stream (Bridge No. 910)  Partial demolition and removal of existing curbs, gutters and sidewalks on bridge deck. Reconstruct curbs, gutters, sidewalk and A.C. pavement. Repair spalled, delaminated and hollow sounding areas in bridge soffit, abutments and pier. Repair bridge parapet, metal railing and expansion and cold joints.

            (Estimated completion date, June 2010)

 

Localized Rehabilitation of Streets, Phase 4, Pearl City, Newtown, Royal Summit,  Pacific Palisades, Pearlridge, Aiea, Aiea Heights, Halawa Heights, and Halawa Valley.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, March 2010)

 

Waimalu Sewer Rehabilitation/Reconstruction Phase I:  Installation of new sewer lines/man holes and reconnection of existing sewer laterals along Hekaha, Kanuku, Lokowai, Lii-Ipo, Pahemo, and Olepe.

            (Estimated completion date, September 2010)

 

PEARLRIDGE

Rehabilitation of Secondary Streets at Pearl City – Kaonohi Street ( Kaonohi Place to entire loop), and Kaonohi Street (Kamehameha Highway to Moanalua Road):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, March 2010)

 

SALT LAKE

Curb Ramps at Various Locations, FY 2006 – Miko St./Ukana St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

WAIALUA

Guardail Improvements – FY2006 Phase II.  Site B:  Waialua Beach Road – 66-080 Waialua Beach Road to Kiikii Stream:  Remove existing guardrails & concrete posts; provide archaeological monitoring; install object markers; install standard metal guardrail, post & spacers.

            (Estimated start date:  March 2010)

 

WAHIAWA

Curb Ramps at Various Locations, FY 2006 – Glen Ave./Kolekole Dr., Crest Ave./Glen Ave.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

WAIKIKI

Rehabilitation of Streets, Unit 62 – Ala Wai Boulevard between Kanekapolei Street and Kalakaua Avenue:  Reconstruct identified curbs, gutters, driveways and asphalt roadway.  Resurface asphalt roadways; install permanent pavement markings; restore vehicle loop detectors and raise manhole and valve covers to grade.  Anticipated start date of September 28, 2009; preliminary surveying to start August 19, 2009

            (Estimated completion date, March 2010)

 

Curb Ramps at Various Locations, FY 2006 – Kuhio Ave./Kapahulu Ave.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons.  Installation of pavement striping, markings and markers.

            (Estimated completion date, March 2010)

 

WAIMANALO

Retaining Walls Along Waikupanaha Street, Box Culvert No. 5.  Demolish existing spillway; construct of new retaining walls; install new GRP; regrade site; install new metal guardrails and posts; install new chain link fence.

 

WAIPAHU

Emergency Repairs to Waipahu Street Arch Bridge Over Waikele Stream (Bridge No. 961)

GRP at south-west anchor wall, a.c pavement, install guardrails, install signage.

            (Estimated completion date March 2010)

 

Waipahu Street Retaining Wall Repair & 16th Avenue Boulder Basin Dam Wall Reconstruction:  Demolish and rebuild retaining wall, curb ramp, and portion of sidewalk adjacent to Waipahu Elementary School.  Awaiting staging area approval from DPR.  Tentative start of construction date set for October 23, 2009.

            (Estimated completion date March 2010)

 

Rehabilitation of Paiwa Street (Farrington Highway to Waipahu Street), Waipahu Street (Hianakiu Street to Kaupu Place), Makoa Street (Puia Street to end to end), Puia Street (Anonui Street to Eleu Street, and Heahea Street to deadend):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, March 2010)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

March 21, 2010  Sunday
6:00AM Starts
9:00AM Ends

WATERFRONT at PUULOA TRIATHLON sponsored by Pacific Sport Events. The event is expected to have 300 participants.  Swim: 500 meters- Iroquois Beach out and back course ending on beach near transition area.  Bike: 11 mile- transition area, Iroquois Beach Park-Cormorant Ave-Iroquois Ave-North Rd-West Loch Dr-Iroquois Rd-turnaround at entrance to Lombard Way Housing (Ho Omaka)-West Loch Dr-North Rd-Fort Weaver Rd-Cormorant Ave-end at transition area.  Run: 5K-   Transition area, Iroquois Beach Park-Edgewater Dr-Iroquois Dr-Gannet Ave-106th St-Heron Ave-Ibis Ave-101st St-Iroquois Ave-finish at Iroquois Point Island Club.  Contact: Steven Foster 864-0113, Fax:  685-6666, E-mail:  steve@pacificsportevents.com

 

March 26, 2010 Friday
6:00PM Starts
10:00PM Ends

MURPHY'S KOKUA FRIDAY BLOCK PARTY SERIES #2 sponsored by Murphy's Bar & Grill/Hawaii Academy of Recording Art. The event is expected to have 300+ participants.  The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St.  Contact Don Murphy 531-0422,  Fax: 533-4943

 

March 27, 2010 Saturday
4:00PM Starts
6:00PM Ends

PRINCE KUHIO COMMEMORATION PARADE sponsored by Association of Hawaiian Civic Clubs.  The event is expected to have 800 marchers, 35 vehicles, 2 floats, & 2 bands.  It will start at Kalakaua Ave. at Saratoga Rd., kkhd on Kalakaua Ave., to end at Waikiki Shell parking lot, Queen Kapiolani Park. Contact:  Leimomi Khan 372-0630, E-mail:  khanm@hi808.net  

 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391.