May 6, 2010

ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning May 9, 2010, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Curb Ramps at Various Locations, FY 2009 (A) Moanalua Rd./Private Driveway, Ewa of Pali Momi St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, July 2010)

 

EWA

Ewa Villages Revitalization Project Area D Drainage Improvements Near Kapolei Parkway/Park Row/O.R.&L Railroad:  Installation of an 8 x 6 box drain and connection to existing 10x 8 box drain.

            (Estimated completion date, June 2010)

 

HALAWA

Aliipoe Ditch Reconstruction Halawa Heights, Lalawai Drive and Kahema Place area:  Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18 drain pipes.  Install new chain link fence.

            (Estimated completion date, May 2010)

 

Rehabilitation of Secondary Streets at Pearl City Ulune Street (Kahuapaani Street to Kulawea Street), Aiealani Place (Halawa Heights Road to end), Fernridge Place (Halawa Heights Road to end), Halawa Heights Road (Fernridge Place to Mauka end), Hele Mauna Place (Halawa Heights Road to end), Kaimakani Street (Moanalua Road to Ulune Street), Palaialii Place (Halawa Heights Road to end), and Palaialii Way (Palaialii Place to end):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, May 2010)

 

Localized Rehabilitation of Streets, Phase 4, Pearl City, Newtown, Royal Summit,  Pacific Palisades, Pearlridge, Aiea, Aiea Heights, Halawa Heights, and Halawa Valley.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated completion date, May 2010)

 

HAWAII KAI

Curb Ramps at Various Locations, FY 2009 (A), Kalama Valley Kahului St./Kealahou St., Eaea Pl./Olowalu Pl./ Kealahou St., Inuwai Pl./Muolea Pl./Kealahou St., Huialoha St./ Kealahou St., Kealahou St./Manulele Pl., Kealahou St./Mokunoio St., and Kealahou St./Mokuhano St.: Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, July 2010)

 

HONOLULU

Amelia Street Relief Sewer Amelia Street and adjoining School Street:  Installation of a new 16 sewer line underground along Amelia Street and portion of School Street at Amelia Street

            (Estimated completion date, July 2010)

 

Iolani Avenue Retaining Wall:  Construction of new CRM fence wall and installation of soil nail tie backs and reinforced shotecrete facing on retaining wall at 625 Iolani Avenue fronting Dole Community Garden. Restore A.C. sidewalk fronting new CRM wall.  Remove existing trees and re-plant new trees in Dole Community Garden.

            (Estimated completion date, June 2010)

 

Rehabilitation of Localized Streets, Phase 5A Kahala to Kaimuki Area

 

The work includes localized reconstruction of pavement and resurfacing of the streets indicated below; reconstruction of curbs, gutters, sidewalks and driveways are included; tree trimming, pruning and removal will be performed as necessary; post paving activities include permanent pavement markings and adjustment of utility manhole frames and covers to grade.  The affected roadways and limits of work are as follows:

 

18th Avenue, from Harding Avenue to Diamond Head Road, 19th Avenue, from H-1 Freeway to Kilauea Avenue including TMK: 32039051, 20th Avenue, from H-1 Freeway to Kilauea Avenue, 21st Avenue, from Harding Avenue to Kilauea Avenue, 22nd Avenue, from Harding Avenue to End, Ahakea, Street, from Aukai Avenue to Elepaio Street, Ahina Street, from Ahakea Street to Aukai Avenue, Ahuli Place, from Pahoa Avenue to End, Alae Street, from Elepaio Street to Onaha Street, Amau Street, from Hunakai Street to Pueo Street, Apuwai Place, from Kilauea Avenue to End, Aukai Avenue, from Kealaolu Avenue to Kahala Avenue

 

Elepaio Street, from Kilauea Avenue to Kahala Avenue, Farmers Road, from Kealaolu Avenue to Ulumaika Street, Hakaka Place, from Hakaka Street to End, Hakaka Street, from Palekaua Street to End, Honua Street, from Onaha Street to Kolohala Street, Hopeloa Place, from Puu Panini Avenue to End, Huanui Place, from Huanui Street to End, Huanui Street, from 22nd Avenue to Puu Panini Avenue including TMK: 32061018, Hunakai Street, from Waialae Avenue to Kahala Avenue, Hunalewa Street, from 22nd Avenue to Huanui Street, Hunapaa Street, from Huanui Street to End, Iiwi Street, from, Onaha Street to Kolohala Street, Ipo Place, from 22nd Avenue to End

 

Kaalawai Place, from Diamond Head Road to End, Kaikoo Place, from Papu Circle to End, Kaikuono Place, from Papu Circle to End, Kaimanahila Street, from Paikau Street to Hakaka Street, Kaimuki Avenue, from 18th Avenue to Luawai Street, Kala Place, from Aukai Avenue to Kahala Avenue, Kaualio Place, from 22nd Avenue to End, Kealaolu Place, from Kealaolu Avenue to End, Koae Place, from Koae Street to End, Koae Street, from Hunakai Street to Amau Street, Koloa Street, from Kahala Avenue to Elepaio Street, Kolohala Street, from Onaha Street to Elepaio Street, Kuana Street, from Onaha Street to Kolohala Street, Kulamanu Street, from Kahala Avenue to Kulamanu Place

 

Luakaha Place, from Luakaha Street to End, Luakaha Street, from Luawai Street to End, Luawai Place, from Luawai Street to End, Luawai Street, from 20th Avenue to Pahoa Avenue, Makaiwa Street, from Kilauea Avenue to Pueo Street, Makalike Place, from 22nd Avenue to End, Malapua Place, from 22nd Avenue to End, Maunaloa Avenue, from 18th Avenue to 22nd Avenue, Moa Street, from Pueo Street to Makaiwa Street, Noio Street, from Onaha Street to Kolohala Street, Onaha Street, from Kilauea Avenue to Kolohala Street

 

Pahoa Avenue, from Kilauea Avenue to Moa Street and from 18th Avenue to 22nd Avenue, Paikau Street, from 22nd Avenue to Kahala Avenue, Palekaua Place, from Palekaua Street to End, Palekaua Street, from Puu Panini Avenue to Hakaka Street, Pana Place, from Paikau Street to End, Panini Loop, from Puu Panini Avenue to Puu Panini Avenue, Pilialo Street, from Luawai Street to Kaimuki Avenue

Poka Place, from Poka Street to End, Poka Street, from Paikau Street to Diamond Head Road, Pokapahu Place, from Paikau Street to End, Pueo Street, from Kahala Avenue to Hunakai Street, Puulani Place, from Hunakai Street to End, Puu Panini Avenue, from Kilauea Avenue to 22nd Avenue, Ulili Street, from Onaha Street to Kahala Avenue, Ulumaika Street, from Hunakai Street to Hunakai Street, Ulupua Place, from 22nd Avenue to End, Waikui Street, off Kalanianaole Highway, Waiohinu Drive, from Makaiwa Street to Makaiwa Street

            (Estimated Completion November 23, 2010)

 

Curb Ramps at Various Locations, FY 2006 Kaimuki Avenue Mid Block: Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pedestrian push buttons and traffic signal pull boxes.  Installation of pavement striping, markings and markers.

            (Estimated completion date, May 2009)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1A and 1C:  New sewer line and manhole installation on Mokauea Street, Kalani Street and Kino Street.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.            (Estimated completion date, May 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1B:  New sewer line and manhole installation on Kopke Street.  Kopke Street and Gulick Ave.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, May 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1D:  New sewer line and manhole installation on Captain Cook and  Lolena Street.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, May 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G:  New sewer line and manhole installation on Kuakini Street (between Nuuanu Avenue and Pali Highway) is ongoing.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, November 2010)

 

Kuliouou Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, lateral rehabilitation, and some new installation of sewer lines.  CIPP installation work at Summer Street and May Way.

            (Estimated completion date, May 2010)

 

Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program.  Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves. Re-grade swale and adjust DI to provide positive drainage into existing drain system. Upgrade concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams.  At the intersection of Ahua Street and Awaawaloa Street, abandon existing storm drain on Ahua Street and install new storm drain MH on upstream end of abandoned pipe.

            (Estimated completion date, May 2010)

 

Maunalaha Road Embankment Improvements:  Work includes roadway excavation; demolition and removal of existing pavements, curbs, gutters, guardrails, and railings; installation of new metal posts, plastic lumber lagging and guardrails; reconstruction and repair of roadway. Contractor will not commence work at the site until May due to material shortage.

            (Estimated completion date, July 2010)

 

Seismic Retrofit of City Bridges at Various Locations, FY 08 Nehoa Street Bridge between Makiki St. and Anapuni St., and Lusitana Street Bridge between Ladd Ln. and Andrews Ln.:  Installation of concrete and steel shear keys.  Repair concrete spalls and cracks.  Construction of concrete back wall.

            (Estimated completion date, August 2010)

 

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, May 2010)

 

Rehabilitation of Secondary Streets at Kaimuki Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street.  Excavating, reconstructing and resurfacing asphalt concrete pavements and base; reconstructing base at bus stops; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, June 2010)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:  New sewer line and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Sewerwork is ongoing on Pua Lane.  Repaving of King, Peterson and Pua lane to follow after sewer work is complete.  Pua Lane One lane in mauka bound direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, May 2010)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights.  The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street.

            (Estimated completion date, May 2010)

 

Sewer rehabilitation on various streets on Wilhelmina Rise.  Installation of cured in place pipe (CIPP), lateral rehailitation, and replacement of sewer lines by open trench.

            (Estimated completion date November 2010)

 

KAILUA

Rehabilitation of Streets, Unit 46 Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):  Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings.

            (Estimated completion date, May 2010)

 

Kalaheo Avenue/Mokapu Road/Aikahi Loop Sewer Rehabilitation:  Installation of Cured In Place Pipe along Mokapu Boulevard, from the intersection of Mokapu and Kalaheo, and Aikahi Loop.

            (Estimated completion date, May 2010)

 

Rehabilitation of Kawailoa Road Bridge over Kaelepulu Stream, Bridge No. 411:  Work includes repair of spalls in the concrete elements; replacement of the deteriorated pedestrian walkway and railing at the upstream side of the bridge; repair of deck joints; replacement of the vehicular guardrail system; and traffic safety improvements at the bridge approaches.

            (Estimated completion date, September 2010)

 

Rehabilitation of Streets, Unit 52 Keolu Drive (Kalanianaole Highway to Akahai Street); Keolu Drive (Akaakaawa Street to Wanaao Road):  Cold planing; resurfacing and reconstruction of asphalt concrete pavements (ACP); adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, sidewalks and Driveways; reconstruction of concrete catch basins; and construction of concrete and asphaltic concrete bus pads.

            (Estimated completion date, May 2010)

 

Seismic Retrofit at City Bridges FY09, Keolu Drive Bridge, and Auloa Road Bridge:  Work consists of making seismic retrofit improvements that include installing: stainless steel bolsters at the deck slab, concrete bolsters/creep blocks, stainless steel plates across expansion joints, and other miscellaneous bridge improvements.

            (Estimated completion date, November, 2010)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:  Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

            (Estimated completion date, May 2010)

 

KANEOHE

Duncan Drive Puahuula Place Relief Drain  Construction of a relief drainage system, removing existing drainage system and installing larger drain lines, three new inlets, a trench drain and new storm drain manholes.

            (Estimated completion date, May 2010)

 

Curb Ramps at Various Locations, FY 2009 (A) Hui Iwa St./Hui Kelu St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, July 2010)

 

Kaneohe Bay Drive Trunk Sewer Reconstruction:  Installation of new sewer lines, new manholes, and cured in place pipe (CIPP).  Work will occur on Kaneohe Bay Drive between Mokapu Road and Kuono Place, Kaimalu Place and Way, Ikeanani Drive, and Kuakoa Place.

            (Estimated completion date December 2010)

 

Kapunahala Road Retaining Wall near 45-866 Anoi Road  Construction of a concrete retaining wall and railing.  Restore AC pavement, AC sidewalk and AC curb.  Traffic detours will be provided after working hours.

            (Estimated completion date, September 2010)

 

KAPOLEI

Extension of Kapolei Parkway, Phase 8B (North-South Road to Renton Road):  One-year landscape maintenance period for street trees and grassing in progress.

            (Estimated completion date May 2010)

 

MANOA

Rehabilitation of Local Streets, Phase 1:  Work is on-going on Woodlawn Drive in Manoa.

            (Estimated completion date, May 2010)

 

NIU VALLEY

Seismic Retrofit of City Bridges at Various Locations, FY 08 Halemaumau Street Bridge:  Halemaumau St./Haleola St.  Installation of concrete shear keys and restrictor boots.  Repair concrete spalls and cracks.

            (Estimated completion date, August 2010)

 

NUUANU

Drainage Outfall Improvements for Waolani Stream at Kawananakoa Place 105-D Kawananakoa Place:  Construction of new SDMH and installation a check valve over the existing 18 RCP drain pipe.

            (Estimated completion date, July 2010)

 

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, May 2010)

 

PALOLO

Rehabilitation of Secondary Streets at Kaimuki Palolo Avenue, Waialae Avenue to 10th Avenue in Palolo Valley.  Excavating, reconstructing and resurfacing asphalt concrete pavements and base; reconstructing base at bus stops; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, May 2010)

 

PEARL CITY

Rehabilitation of Secondary Streets at Pearl City Hoolaulea Street below Moanalua Road  (Waimano Home Road to Hoomoe Road), Nanakai Place (Nanakai Street to end), Nanakai Street (Waimano Home Road to Hoomalu Street), Puu Kipa Street ( Nanakai Street to Nanakai Street):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, May 2010)

 

Manana Infrastructure Improvements, Phase VI Connector Road (Kuala Street to Kuahaka Street)  Construct 60-foot wide roadway from Kuala Street to Kuahaka Street. The work includes, vector control; clearing, grubbing and grading; installation of new storm drain, Heco, Hawaiian Telcom, street light and traffic signal systems; concrete slab protection for existing sewer and water lines; grade adjustments in private lots; new noise and retaining walls, chain link fence and gates: reconstruction of existing drain, water and sewer MHs and valves to new finish grade; installation of curbs, gutters, sidewalks, driveways, curb ramps and sidewalk culverts; installation of irrigation system and landscape improvements; tree removal and pruning in private lots; road paving; pavement markings and markers and street signs.

            (Estimated completion date, December 2010)

 

Localized Rehabilitation of Streets, Phase 4, Pearl City, Newtown, Royal Summit,  Pacific Palisades, Pearlridge, Aiea, Aiea Heights, Halawa Heights, and Halawa Valley.  The work includes: cold planing, resurfacing of asphalt concrete pavements, reconstruction of failed pavement areas; adjustment of manhole frame and covers, street survey frame and covers, installation of pavement markings; locating with GPS survey equipment manholes, valve boxes, monuments, etc.

            (Estimated Completion Date, May 2010)

 

Waimalu Sewer Rehabilitation/Reconstruction Phase I:  Installation of new sewer lines/man holes and reconnection of existing sewer laterals along Hekaha, Kanuku, Lokowai, Lii-Ipo, Pahemo, and Olepe.

            (Estimated completion date, September 2010)

 

PEARLRIDGE

Rehabilitation of Secondary Streets at Pearl City Kaonohi Street ( Kaonohi Place to entire loop), and Kaonohi Street (Kamehameha Highway to Moanalua Road):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, May 2010)

 

WAHIAWA

Curb Ramps at Various Locations, FY 2009 (A) Center St. Mid Block between N. Cane St. & Lehua St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, July 2010)

 

WAIALUA

Guardail Improvements FY2006 Phase II.  Site B:  Waialua Beach Road 66-080 Waialua Beach Road to Kiikii Stream:  Remove existing guardrails & concrete posts; provide archaeological monitoring; install object markers; install standard metal guardrail, post & spacers.

            (Estimated start date:  May 2010)

 

WAIANAE

Curb Ramps at Various Locations, FY 2009 (A) McArthur St./Mill St.:  Construction of new curb ramps, sidewalks and A.C. transition.  Installation of pavement striping, markings and markers.

            (Estimated completion date, July 2010)

 

WAIKIKI

Rehabilitation of Streets, Unit 62 Ala Wai Boulevard between Kanekapolei Street and Kalakaua Avenue:  Reconstruct identified curbs, gutters, driveways and asphalt roadway.  Resurface asphalt roadways; install permanent pavement markings; restore vehicle loop detectors and raise manhole and valve covers to grade.  Anticipated start date of September 28, 2009; preliminary surveying to start August 19, 2009

            (Estimated completion date, May 2010)

 

Rehabilitation of Secondary Streets at Kaimuki Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street.  Excavating, reconstructing and resurfacing asphalt concrete pavements and base; reconstructing base at bus stops; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, June 2010)

 

WAIMANALO

Retaining Walls Along Waikupanaha Street, Box Culvert No. 5.  Demolish existing spillway; construct of new retaining walls; install new GRP; regrade site; install new metal guardrails and posts; install new chain link fence.

 

WAIPAHU

Emergency Repairs to Waipahu Street Arch Bridge Over Waikele Stream (Bridge No. 961)

GRP at south-west anchor wall, a.c pavement, install guardrails, install signage.

            (Estimated completion date May 2010)

 

Waipahu Street Retaining Wall Repair & 16th Avenue Boulder Basin Dam Wall Reconstruction:  Demolish and rebuild retaining wall, curb ramp, and portion of sidewalk adjacent to Waipahu Elementary School.  Awaiting staging area approval from DPR.  Tentative start of construction date set for October 23, 2009.

            (Estimated completion date May 2010)

 

Rehabilitation of Paiwa Street (Farrington Highway to Waipahu Street), Waipahu Street (Hianakiu Street to Kaupu Place), Makoa Street (Puia Street to end to end), Puia Street (Anonui Street to Eleu Street, and Heahea Street to deadend):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, May 2010)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

May 10, 2010 Monday
6:00PM Starts
6:30PM Ends

POLICE WEEK MEMORIAL MARCH sponsored by Honolulu Police Department. The event is expected to have 100 marchers, 6 vehicles, & 1 band.  It will start at Police HQ, to Beretania St., to end at State Capitol grounds. Three (3) makai lanes will be closed from 5:30 pm  Contact:  Lt. Rodney Noguchi 529-3882,  E-mail: rnoguchi@honolulu.gov

 

May 14, 2010  Friday
6:00AM Starts
11:00PM Ends

MURPHY'S KOKUA FRIDAY BLOCK PARTY SERIES #4 sponsored by Murphy's Bar & Grill/Hawaii Literacy. The event is expected to have 300+ participants.  The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St.  Contact Don Murphy 531-0422,  Fax: 533-4943

May 15, 2010 Saturday
6:00AM Starts
12:30PM Ends

TRINITY CHRISTIAN SCHOOL BIATHLON sponsored by Trinity Christian School. The event is expected to have 60 participants. Swim- 520 yards begins at the last posted lifeguard stand on the Kailua Beach Park on the Lanikai end.  A floating marker will be posted to make the turn to transition.  Run:  It will start at Kailua Beach Park, Lanikai end parking lot, to Aalapapa Dr., counterclockwise around Lanika Lp. bike path, to Mokulua Dr., to end at Kailua Beach Park.  Contact:  Nancy Shaw 262-8501, Fax:  261-3916, E-mail:  mfellezs@tcskailua.net 

May 15, 2010  Saturday
6:00AM Starts
1:00PM Ends

32ND ANNUAL VISITOR INDUSTRY CHARITY walk sponsored by Hawaii Hotel Industry Assn. The event will have 9,000 runners/walkers.  It will start at Ala Moana Park's McCoy Pavilion Key Hole area, clockwise around Ala Moana Park, to             Ala Moana Blvd., mauka sidewalk area, to Ala Wai  Promenade area, to Kalakaua  Ave., makai sidewalk area and curb lane, to Koko Hd side of Kapahulu Ave., to Ala Wai Blvd., mauka sidewalk and curb lane, to Seaside Ave., to Aloha Dr., to Lewers St., to Kalia Rd., to Ala Moana Blvd., to end at Ala Moana Park.  Contact: Tina Yamaki  923-0407  Fax: 924-3843  E-mail:  tyamaki@hawaiihotels.org  For more info, visit their website: http://www.charitywalkhawaii.org/  

 

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391.