ROAD WORK WEEKLY REPORT

 

(Thu., February 21, 2013) − Scheduled road work for the week beginning February 24, 2013, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below. Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Rehabilitation of Streets, Phase 1 (aka IDIQ #2) Honomanu St.  Completed paving Honomanu St.  Permanent striping, adjusting manhole and installing traffic detector loops to follow.

 

EWA BEACH

Rehabilitation of Localized Streets, Phase 7B Ewa Beach

Aaha Pl, Aama Pl, Aekai Pl, Ahona St, Aiami Pl, Aikanaka Pl, Akaholo St, Akua St, Amio St, Apai Pl, Apoke Pl, Apole Pl, Ewa Beach Rd, Haehae Pl, Hahanui St, Haiamu Pl, Haiamu St, Haiano Pl, Hailipo St, Hainoa Pl, Haipu Pl, Haiwa Pl, Halali Pl, Hamiha Pl, Hamoa Pl, Hanakahi St, Hanaloa Pl, Hanaloa St, Hapalua St, Heleia Pl, Ihipehu St, Ihupani Pl, Kalapu St, Kapana Pl, Kauiki St, Kaunolu St, Kauwili St, Keakaula Pl, Keele Pl, Kehue Pl, Kehue St, Kei Pl, Kekaihili Pl, Kekakia Pl, Keleawe Pl, Kemika Pl, Kilaha Pl, Kilaha St, Kilinahe St, Kilipoe St, Kimopelekane Rd, Koalipehu Pl, Koalipehu St, Komana St, Kuhina St, Laupapa Pl, Laupapa St, Lakana Pl, Lapine Pl, Laukona Lp, Lawalu Pl, Lipaki Pl, Liuliu Pl, Nalomeli Pl, Makaonaona St, Makule Rd, Moneha Pl, Muumuu Pl, North Rd, Oama Pl, Oama St, Onelua Pl, Onelua St, Paaloha St, Papipi Dr, Papipi Rd, Papipi Pl, Parish Dr, Peeone Pl, Pohakupuna Pl, Pohakupuna Rd, Poloula Pl, Pupu Pl, Pupu St.

 

This Rehabilitation of Localized Streets project includes: cold planning; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas identified by the contractor and confirmed by the City; adjustment of utility manhole frames and covers, and street survey monument frame and covers; installation of pavement markers, striping and markings; installation of vehicle detector loops; locating existing manholes, valve boxes, monuments, etc. with GPS survey equipment and providing ArcGIS data files to City Dept. of Planning and Permitting in required data format.

 

Paving completed.

 

Rehabilitation of Localized Streets, Phase 7B Ewa Village

Alaiki St, Ala Loa St, Alana St, Alanui Mauka Pl, Alanui Mauka St, Auwaha St, Bond St, Bryan St, Burke St, Ekemauu St, Halolani St, Hapaiko St, Garton St, Halemano St, Hapua St, Hei Pl, Hookahe Pl, Hoopio St, Hulili St, Imelda St, Kamahoi St, Karayan St, Kikoo St, Kuali St, Kuapuu St, Kupeleko Pl, Kuuwelu Pl, Lako St, Lauo St, Lehu St, Luahine St, Luluka St, Lunanui St, Mahamoe St, Malako St, Maliko St, Miula St, Nale St, Niulelo Pl, Oha St, Olehala St, Oohao St, Orrick St, Paaniana St, Paeheulu St, Paekii St, Paeko St, Pahe St, Paheahea St, Pahika St, Park Row, Pepper Row, Pihi St, Pipeline St, Pohakulepo St, Pualoalo Pl, Pualu St, Puhiko St, Punako St, Puuhala St, Sisal St, Tenney St, Uluhui St and Wili St.

 

This Rehabilitation of Localized Streets project includes: cold planning; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas identified by the contractor and confirmed by the City; adjustment of utility manhole frames and covers, and street survey monument frame and covers; installation of pavement markers, striping and markings; installation of vehicle detector loops; locating existing manholes, valve boxes, monuments, etc. with GPS survey equipment and providing ArcGIS data files to City Dept. of Planning and Permitting in required data format.

Paving streets, adjusting manholes and placing permanent striping on various streets.

 

HALEIWA

Seismic Retrofit of Haleiwa Road Bridge over Paukauila Stream, Bridge No. 602:

Concrete infill shear walls, concrete beam extensions, and repair of spalls and delaminations in concrete columns.

            (Estimated completion date, March 2013)

 

HONOLULU

Rehabilitation of Fern Street Bridge, Bridge No. 209  Repair concrete piles, repair of spalls, concrete delamination in bridge elements, and new weight limit sign and post.

            (Estimated completion date, June 2013)

 

Houghtailing Street Area Sewer Rehabilitation:  Installation and rehabilitation of sewer lines and construction of new manholes along School Street.

            (Estimated completion date, continuing through February 2013)

 

Rehabilitation of Kahala Avenue Bridge Over Kapakahi Stream, Bridge No. 319.  Repair of spalls, concrete delamination in bridge elements, and approach slab.

            (Estimated completion date, April 2013)

 

Kapiolani Boulevard Reconstruction (South Street to Ward Avenue): The project will reconstruct the asphalt pavement section and construct new Portland Cement Concrete pavement bus lanes in both directions; reconstruct existing curbs and gutters; reset and installation of rock curbs; installation of a new street lighting and traffic signal system and ancillary pull boxes.  The work includes the coordinating and performing trimming tree canopies and root pruning as necessary under the guidance of certified/qualified arborist.  Also, included will be the adjustment of existing utilities to grade, and permanent pavement markings; and restoration of the traffic loop sensors.

            (Estimated Completion June 2013)

 

King Street Reconstruction between River Street and Bethel Street, Chinatown:  Rehabilitation of sewer lines and select laterals, sewer manhole frame and cover replacement, excavation; Installation and backfill for new 6, 8 & 12 water lines, fire hydrants, valves, manholes; Installation and backfill for new 6 drain lines, inlets and manhole connections; Excavation and backfill for new gas lines; Demolish existing concrete and A.C. pavements to install new work and adjust manholes & valves boxes to grade. Work will include portions of River Street, Kekaulike Street, Maunakea Street, Smith Street, Nuuanu Street and Bethel Street where they intersect with King Street. Multiple lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, May 2013)

 

Rehabilitation of Lusitana Street Bridge, Bridge No. 263:  Project consists of performing repairs and making improvements to the superstructure and railings of Lusitana Street Bridge on Oahu.

            (Estimated completion date, continuing through February 2013)

 

Rehabilitation of Localized Streets, Phase 6B Makiki, Upper Makiki Areas:  The work includes localized reconstruction of pavement and resurfacing of the streets indicated below; reconstruction of curbs, gutters, sidewalks and driveways are included; tree trimming, pruning and removal will be performed as necessary; post paving activities include permanent pavement markings and adjustment of utility manhole frames and covers to grade.  The affected roadways and limits of work are as follows:

 

Aaliamanu Place, from Tantalus Drive to end; Aina Lani Place, from Round Top Drive to end; Aina Lani Way, from Aina Lani Place to end; Alexander Street, from H-1 Freeway to Dole Street; Alihilani Place, from Manoa Road to end; Anapuni Street, from Wilder Avenue to Nehoa Street; Anianiku Street, from Auwaiolimu Street to end; Clark Street, from Punahou Street to end; Clio Street, from Lewalani Drive to Mott Smith Drive; Davenport Street, from Piikoi Street to Pensacola Street; Dominis Street, from Punahou Street to Kewalo Street; Enos Lane, from Makiki Street to end; Ernest Street, from Lunalilo Street to end; Green Street, from Ward Avenue to kokohead end; Haiki Place, from Round Top Drive to end; Hassinger Street, from Pensacola Street to Piikoi Street; Heulu Street, from Liholiho Street to Makiki Street; Hiilani Street, from Tantalus Drive to end; Iaukea Street, from ewa end to mauka end

 

Kalamaku Street, from Moreira Street to end; Kapahu Street, from Auwaiolimu Street to Anianiku Street; Karratti Lane, from Pensacola Street to end; Kauhane Street, from Iaukea Street to end; Kaululaau Street, from Moreira Street to end; Keopua Street, from Moreira Street to end; Kewalo Street, from Lunalilo Street to Nehoa Street; Kolonahe Place, from Tantalus Drive to end; Krauss Street, from Iaukea Street to end; Lewalani Drive, from Nehoa Street to Mott Smith Drive; Liholiho Street, from Lunalilo Street to Heulu Street; Lilo Place, from Mott Smith Drive to end; Luna Place, from Mott Smith Drive to end; Lunalilo Street, from Ernest Street to Ward Avenue

 

Makiki Place, from Makiki Street to end; Makiki Street, from H-1 Freeway to end; Mamane Place, from Round Top Drive to end; Mauna Place, from Mott Smith Drive to end; Maunaihi Place, from Prospect Street to end; Moreira Street, Tantalus Drive to Kalamaku Street; Mott Smith Drive, from Mauna place to Makiki Height Drive; Naale Street, from Kapahu Street to Anianiku Street; Okika Place, from Makiki Street to end; Oneele Place, from Makiki Street to end; Piikoi Place, from Piikoi Street to end; Pililani Place, from Mott Smith Drive to end; Poki Street, from Wilder Avenue to Nehoa Street; Prospect Street, from Ward Avenue to Pensacola Street; Punahou Street, from Nehoa Street to King Street; Spencer Street, from Ward Avenue to Wilder Avenue; Ualakaa Place, from Ualakaa Street to end; Ualakaa Street, from Nehoa Street to end; Victoria Street, from Green Street to Lunalilo Street; Whitney Street, from Dole Street to end

            (Estimated completion, continuing through February 2013)

 

Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program: Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves.  Re-grade swale and adjust existing D.I. frame / cover to provide positive runoff flow into existing Drain system. Reconstruct concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams. Restore existing chain link fence at outlet area. At the intersection of Ahua Street and Awaawaloa Street, provide permanent concrete plug in existing 24 DL.

            (Estimated completion, continuing through February 2013)

 

Curb Ramps at Various Locations, McCully and Central Business District: Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory/street signs. Installation of pavement striping, markings and markers.

 

Rehabilitation of Localized Streets, Phase 6A McCully, Makiki, Moilili Areas  The work includes localized reconstruction of pavement and resurfacing of the streets indicated below; reconstruction of curbs, gutters, sidewalks and driveways are included; tree trimming, pruning and removal will be performed as necessary; post paving activities include permanent pavement markings and adjustment of utility manhole frames and covers to grade.  Paving continues on Victoria Street from King Street to H-1 Freeway deadend.

 

Highway Structure Improvements, Pacific Heights Road Retaining Wall, Vicinity of 2210 Star Road

Removal and reconstruction of approximately 227 L.F. of concrete retaining wall with stone veneer facing; relocate joint utility poles and electrical lines for wall construction; replace existing electrical poles with new poles and lines; relocate existing streetlight fixtures on temporary poles for wall construction; install new streetlight fixtures on new poles; restore AC pavement fronting new wall;

restore pavement markings and markers; relocate existing signs and posts; provide traffic controls during working and non-working hours.

            (Estimated completion date, continuing through February 2013)

 

Bridge Rehabilitation at Various Locations I, FY 2009  Puowaina Drive Bridge over Auwaiolimu Street, Bridge No. 236  Repair of spalls in the concrete elements; repair of deteriorated CRM wall; replacement of concrete railing; strengthening concrete bridge sidewalks; shotcrete facing with soil/rock anchors; and miscellaneous repairs.

            (Estimated completion date, February 2013)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights.  The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street.

            (Estimated completion date, continuing through February 2013)

 

Rock Slide Potential Inspection & Mitigation Improvements, Sierra Drive:  The work consists of clearing vegetation within Project limits, excavate areas to widen roadway shoulder by reducing the embankment slope inclination and/or eliminating overhangs, scaling boulders and potentially unstable rock blocks in designated areas, install shotcrete and drainage system, install chain link fence (with gate) and complete final designs and installation of rock fall fence based on Project Special Provision. The Contractor shall implement construction traffic controls, and water pollution and erosion control measures.

 

Rehabilitation of Streets, Unit 54 Wilhelmina Rise, 13th Avenue to Matsonia Street:  The work includes demolition and reconstruction of the existing PCC pavement and curbs identified on the plan.  Tree trimming, pruning and removal will be performed as necessary and as identified on the plan.  Adjustment of manholes and frames to grade as necessary; post paving activities include permanent pavement markings

            (Estimated Completion date, continuing through February 2013)

 

KAILUA

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Aikahi Park.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal completed.  Kaneohe Bay Drive repair completed.

            (Estimated completion date, June 2013)

 

KAIMUKI

Rehabilitation Of Streets, Unit 57 Kaimuki area

The work includes reconstruction of pavement and resurfacing of streets; reconstruction of curbs, gutters, sidewalks, driveways and bus pads; tree trimming, root pruning and tree removal as necessary; pavement markings and markers, installation of vehicular detector loops, adjustment of street monuments to new finish grade, and adjustment / reconstruction of utility manhole / valve box frames and covers to new finish grade.

 

The affected roadways and limits of work are as follows:  Waialae Avenue from Kapahulu Avenue to 17th Avenue; 5th Avenue from Waialae Avenue to Harding Avenue; 6th Avenue from Harding Avenue to Pahoa Avenue; 7th Avenue from Waialae Avenue to Pahoa Avenue; 8th Avenue from Waialae Avenue to H-1 Freeway; 9th Avenue from Waialae Avenue to H-1 Freeway; 10th Avenue section crossing H-1 Freeway; 11th Avenue from Waialae Avenue to Harding Avenue; 12th Avenue from Waialae Avenue to H-1 Freeway; 13th Avenue from Keanu Street to Claudine Street; 14th Avenue from Waialae Avenue to Keanu Street; 15th Avenue from Waialae Avenue to Noeau Street; 16th Avenue from Waialae Avenue to end (mauka side); 17th Avenue H-1 Freeway to Noeau Street; and Moi Way, Anuhea Place, Ekaha Avenue, Hoku Avenue, Keanu Street, Noeau Street, Claudine Street, Koko Head Drive.

            (Estimated completion date, December 2013)

 

KANEOHE

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Kaneohe: Mokulele Dr and Kaneohe Bay Dr.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal at Mokulele Drive completed.

            (Estimated completion date, June 2013)

 

MAILI

Maili Stream Flood Control Improvements.  Scope of work: remove and replace existing damaged concrete channel lining; remove and replace existing chain link fence.

            (Estimated completion date, continuing through February 2013)

 

MAKAHA

Lahilahi Street Drainage Outfall Improvements Ocean side of Lahilahi St./Lahilahi Pl.:  Removal of the existing 30 drain pipe at the shoreline, installation of a duckbill Tideflex Check Valve, construction of a new drain manhole over existing drain pipe, and implementation, maintenance and removal of BMPs.

            (Estimated completion date, continuing through February 2013)

 

MAKAKILO

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Honokai Hale.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal completed.

            (Estimated completion date, June 2013)

 

MILILANI

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Hookanahe St, Kanae St, Ahikao St, Hookaau St, Ainamakua Dr, Hookupu St, Milia St, Meanui St, Lauae St, Milia Pl, Paeli Pl, Ainakuai Pl, Akeake St, Pakau St, Puulu St, Kailewa St, Kahonua St, Alaume St, Alaume Pl, Lauae St, Ahea St, Liho St, Ahea Pl, Lilii Pl, Ahahuina Pl, Aelike St, Aelike Pl, Kahele St, Alenale Pl, Kahele Pl, Hoailona St, Hoailona Pl, Naaualii Pl, Haakualiki St, Haakualiki Pl, Alaoki St, Alaoki Pl, Hookowa St, Hookowa Pl, Kuauna Pl.

The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; arboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Crack sealing at various streets in Mililani Mauka.  Slurry seal and permanent striping to follow.

 

Paving Ainamakua Dr, adjusting MH and adjusting curb and gutter. Permanent striping to follow.

            (Estimated completion date, June 2013)

 

NUUANU

Rehabilitation of Kimo Drive Bridge Over Nuuanu Stream, Bridge No. 260  Repair of spalls, concrete guardrails and bridge girders.

            (Estimated completion, continuing through February 2013)

 

WAIKIKI

Beachwalk Force Main Phase I:  2 Staging pits to be constructed along Ala Wai Boulevard from Kalakaua towards Ala Moana Boulevard for the microtunneling installation of new sewer line.

            (Estimated completion, continuing through February 2013)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

February 24, 2013 Sunday
7:30AM Starts
9:30AM Ends

MOKULEIA TIME TRIAL sponsored by Cambiamento d'Andaturo/Team Core Hawaii.  The event is expected to have 100 participants.  It will start at Waialua High School, to Farrington Hwy., turnaround at Camp Erdman, to end at Waialua High School.  Contact:  Barry Masuda 227-3519, E-mail:  barry_masuda@yahoo.com  

 

March 1, 2013 Friday
7:30PM Starts
1:00AM Ends

FIRST FRIDAY STREET FESTIVAL sponsored by Arts District Merchant Association. The event is expected to have 1,000+ participants.  The event will close HOTEL ST., all traffic lanes/sidewalk areas, from Smith St to Nuuanu Ave.   Contact:  Eric Walden 271-3094,  For more info, visit their website:  http//www.artsdistricthonolulu.com

 

  March 2, 2013 Saturday
6:00AM Starts
11:00AM Ends

HALEIWA TRIATHLON sponsored by North Shore Triathlon. The event is expected to have 200 triathletes.  Swim will be offshore of Halewia Beach Park. Bike race will start at Haleiwa Beach Park transition area, to Kamehameha Hwy., to Joseph Leong by pass road, to Weed Junction, to Kamehameha Hwy., to loop around 2 more times on same course, end at Haleiwa Beach Park transition area. Run will start at transition area, to Police beach along coast, to Eco Camp, to turnaround, to end at Haleiwa Beach Park. Contact: Chris Gardner 372-8885  Email: northshoretriathlon@gmail.com

 

March 2, 2013 Saturday
12noon Starts
2:00PM Ends

MARCH IN MARCH IN HALEIWA sponsored by the Hui O He'e Nalu/Hawaii GMO Justice.  The march is expected to have 800 marchers.  The event will start at 7-11 Parking Lot in Haleiwa Town, 66-632 Kam Hwy., to end at Haleiwa Beach Park.  Contact:  Mahina Chillingworth 368-7749 or Dustin Barca 652-9553, E-mail:  mahina@dahui.com or hawaiigmojustice@yahoo.com

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391.